HomeMy WebLinkAbout5I Engineering services 2017 Projects Report
4646 Dakota Street SE
Prior Lake, MN 55372
CITY COUNCIL AGENDA REPORT
MEETING DATE: SEPTEMBER 26, 2016
AGENDA #: 5I
PREPARED BY: LARRY POPPLER, CITY ENGINEER/INSPECTIONS DIRECTOR
PRESENTED BY: LARRY POPPLER
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTIONS AUTHORIZING EXECUTION OF
THE CITY’S STANDARDIZED PROFESSIONAL SERVICES CONTRACT FOR
ENGINEERING SERVICES FOR 2017 IMPROVEMENT PROJECTS
DISCUSSION: Introduction
The purpose of this resolution is to consider proposals and authorize the Mayor
and City Manager to execute the City’s Standardized Professional Services Con-
tract for 2017 improvement projects. These services will include preliminary engi-
neering, design services, and project inspection.
History
The City uses the Capital Improvement Program to schedule projects. In this case
the several projects are scheduled for completion in 2017. These projects include
the following:
1. Albany Avenue, Cates Street, CJ Circle, Five Hawks Avenue and Park Av-
enue.
2. Franklin Trail from CSAH 21 to Highway 13 (south)
3. Balsam Street, Sunrise Avenue, Spruce Court, and Spruce Trail
4. Sycamore Trail.
These projects have been identified for several years and are shown in the City’s
Capital Improvement Program.
A pavement management analysis was completed that has reviewed the state of
the City’s paved roads. This study defined classifications that aid in the long term
management of the City’s streets to most cost effectively maintain paved surfaces.
The projects identified above were all rated in a poor category condition with rat-
ings below 35 out of 100. All of these roadways are experiencing extensive pave-
ment cracking making them susceptible to large failures. Patching of these areas
typically lasts for 1-2 years which is not an economical use of our bituminous re-
sources.
Current Circumstances
The engineering department is currently shorthanded without a project engineer.
The project engineer position typically completes the first step which is to complete
the feasibility reports. While a project engineer will be hired and start with the City
shortly, the timing does not allow for the completion of the feasibility study within a
timeframe necessary to keep the project on track for early season bidding. Fur-
thermore, the engineering department is behind in final project documentation for
several City projects and 2016 projects appear to be extending further into fall than
2
originally planned due to weather delays. Consultant assistance would allow time
for City Staff in completion of final project documentation for these projects. Re-
gardless even with full staffing, the current makeup of staffing including a project
engineer could not deliver the entire 2017 reconstruction program.
In order to provide the best value to the taxpayers, the City of Prior Lake has
sought proposals for professional engineering services. This request asked for
proposals to provide engineering services for this project. The Request For Pro-
posals (RFP) was sent to three firms that have good working relationships with the
City and experiences completing projects of this type. One consultant, LHB, did
not provide a proposal.
The cost breakdown for the projects identified in the proposals is shown below:
Consultant: Dedicated
Hours
Average Hourly
Rate
Total Proposal
Rate
WSB and Associates
6529 $98 $637,109
Bolton & Menk
6611 $98 $649,700
The consultant firms were evaluated by the City based upon the following criteria:
• Value of Services (50%)
• Consultants approach and understanding of the projects as described
in a work plan (10%)
• Qualifications/experience of personnel working on the project (20%)
• Consultants ability to deliver the project within the general timelines
proposed (10%)
• Consultants prior experience with the City (10%)
This engineering contract is set up on an hourly, not to exceed basis. To deter-
mine the best value, City Staff has dissected the proposals in reviewing the hourly
rates, number of hours dedicated to the project tasks, personnel assigned on the
project, and the assumptions made within each of the proposals.
Each firm prepared estimates as to the amount of time needed to complete the el-
ements with the RFP. The hours dedicated to specific tasks differs from task to
task between the proposals.
Staff then focused on the competency of the individual completing the tasks and
the associated hourly rates. The Bolton & Menk proposal has a more experienced
team for this project.
Based on the scoring criteria, Bolton and Menk’s proposal scored higher that WSB
due to the experience of the Bolton an Menk team. Bolton and Menk’s residential
reconstruction experience in Prior Lake really stood out during the proposal re-
view.
3
Conclusion
City Staff recommends selecting Bolton & Menk for 2017 street reconstruction pro-
jects.
State Statute does not require the City Council to award Professional Services
Contracts to the lowest cost provider. Instead the city may weigh other factors in
awarding professional service work. The cost per hour for the two firms was identi-
cal. More hours were quoted by Bolton Menk. In this case we believe that the
higher number and allocation of hours was most appropriate to complete the quan-
tity of work contemplated.
Staff also considered: 1.) Proposed allocation of consulting time per project, 2.)
Experience in completing all aspects of previous city public improvement projects,
3.) Previous experience and competence of lead project engineer, 4.) Comprehen-
siveness of proposal.
ISSUES: In order to deliver this project for 2017 construction, the preliminary concepts must
be developed soon. Soil boring and surveying are also necessary and should be
completed as soon as possible. Each consultant has demonstrated through their
proposed schedule that they can meet this timeframe for bidding.
Portions of the work could be removed from the contract and performed by City
Staff if time is available or if the City Council decides not to proceed with a certain
project.
FINANCIAL
IMPACT:
The financial impact of each project will be further analyzed in the Feasibility Re-
ports including the preparation of preliminary assessment calculations. The CIP
estimate for the Albany Avenue, Cates Street, CJ Circle, Five Hawks Avenue and
Park Avenue improvement project is $2,174,932. The CIP estimate for the Franklin
Trail Improvement Project is $2,866,403. The CIP estimate for the Balsam Street,
Sunrise Avenue, Spruce Court and Spruce Trail Improvement Project is
$2,478,346. The CIP estimate for the Sycamore Trail Improvement Project is
$752,182. The engineering costs cited are within the range expected for the pro-
jects and associated work of this magnitude.
ALTERNATIVES: 1. Approve a resolution as part of the consent agenda, authorizing the Mayor and
City Manager to execute a Professional Services Contract with Bolton and
Menk for engineering services to complete the 2017 Improvement Projects.
2. Remove this item from the consent agenda for additional discussion.
RECOMMENDED
MOTION:
A Motion and Second as part of the consent agenda for Alternative Number 1.
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 16-XXX
RESOLUTION AUTHORIZING THE MAYOR AND CITY MANAGER TO EXECUTE THE
CITY’S STANDARDIZED PROFESSIONAL SERVICES CONTRACTS FOR 2017
IMPROVEMENT PROJECTS
Motion By: Second By:
WHEREAS, The 2017-2021 Capital Improvement Program identifies improvement of four areas:
1. Albany Avenue, Cates Street, CJ Circle, Five Hawks Avenue, and Park
Avenue
2. Franklin Trail (south of CSAH 21 to Highway 13)
3. Balsam Street, Sunrise Avenue, Spruce Court, and Spruce Trail
4. Sycamore Trail
; and
WHEREAS, In order to allow for construction and planning in 2017, it is necessary to begin the
feasibility report, surveying, and design at this time; and,
WHEREAS, The City does not have in-house resources to provide these professional services
considering other workload obligations and volume of work to deliver 2017
improvements; and,
WHEREAS, The City solicited proposals for completion of feasibility reports, survey,
geotechnical exploration, design, and construction observation:
Consultant: Dedicated
Hours
Average Hourly
Rate
Total Proposal
Rate
WSB and Associates
6529 $98 $637,109
Bolton & Menk
6611 $98 $649,700
; and,
WHEREAS, The proposal review team has determined that the proposal from Bolton and Menk
provides the best value for the City.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. Bolton & Menk is hereby authorized to provide engineering services for the 2017
Improvement Projects. These services will include feasibility reports, surveying,
geotechnical exploration, design, and construction observation.
C:\Users\aschroeder\Desktop\Engineering services 2017 Projects - Res.docx 2
3. Bolton & Menk is authorized to proceed with the feasibility report, surveying, geotechnical
exploration, and design for 2017 improvement projects.
4. The Mayor and City Manager are authorized to execute the City’s Standardized Professional
Services Contract with Bolton & Menk on behalf of the City for 2017 Improvement Projects.
5. Funding for these engineering services will be drawn from the Construction Fund.
PASSED AND ADOPTED THIS 26th DAY OF SEPTEMBER 2016.
VOTE Hedberg Keeney McGuire Morton Thompson
Aye ☐ ☐ ☐ ☐ ☐
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☐ ☐ ☐
______________________________
Frank Boyles, City Manager