HomeMy WebLinkAbout9D Balsam St Area Accept Feasibiilty Presentation2017 Street Reconstruction Project –
Balsam Street Area Improvements
Balsam Street, Spruce Trail, Spruce Circle, Sunrise Avenue
November 28, 2016
City Council Meeting
Agenda
•Project Objectives
•Project Area
•Existing Conditions/Proposed
Improvements
•Review Methods
•Estimated Project Costs
•Estimated Preliminary
Assessments
•Special Assessment Process (MN
Statutes Chapter 429)
•Preliminary Project Schedule
•Project Feedback
•Recommended Action
Project Objectives
•Reconstruct Deteriorated Streets
•Upgrade/Install City Underground Utilities
•Sanitary Sewer
•Watermain
•Storm Sewer
Project Area
Street Improvements
Street Improvements
•Two Improvement Methods
•Reconstruction
•Reclamation
Street Improvements
(Method 1 -Reconstruction)
•Balsam Avenue (between Sunset Trail and Sunrise Avenue),
Spruce Trail (between Sunset Trail and Sunrise Avenue) and
Sunrise Avenue
•Existing bituminous streets with no concrete curb and gutter
•Proposed City standard 32’ width with B618 concrete curb & gutter
•7-ton design street section
•4” Bituminous
•8” Aggregate Base
•12” Granular Material
Street Improvements
(Method 2 –Reclamation)
•Balsam Street (between Sunrise Avenue and east end),
Spruce Trail (between Sunrise Avenue and 170th Street)
and Spruce Circle
•Existing 32’ width with surmountable concrete curb & gutter
•Existing concrete curb and gutter to remain in place (spot repairs)
•7-ton design street section
•4” Bituminous
•8” Reclaim Material
What’s Under the Street
Proposed Utility Improvements –Reconstruct Area
•Sanitary Sewer: Replace 8” VCP with 8” PVC
•Water Main: Replace existing with 8” PVC
•Storm Sewer: Replace existing pipes and
catch basins
Utility Improvements -Reconstruct Area
Utility Improvements –Reclaim Area
Proposed Utility Improvements –Reclaim Area
•Sanitary Sewer: No pipe replacement
•Water Main: Two new hydrants along Balsam
Street and Spruce Trail
•Storm Sewer: No storm sewer replacement
Estimated Project Costs
(Reconstruction)
Estimated Project Costs and Financing (Reconstruction)
ITEM
ESTIMATED PROJECT
COSTS ASSESSMENTS CITY SHARE
Streets $776,660 $310,664 $465,996
Sanitary Sewer $320,180 $320,180
Watermain $323,140 $323,140
Storm Sewer1 $130,310 $44,124 $86,186
Total $1,550,290 $354,788 $1,195,502
1 Includes $20,000 in Water Quality Improvements that are not assessable
Estimated Project Costs
(Reclamation)
Estimated Project Costs and Financing (Reclamation)
ITEM
ESTIMATED PROJECT
COSTS ASSESSMENTS CITY SHARE
Streets $563,810 $225,524 $338,286
Watermain $14,590 $14,590
Total $578,400 $225,524 $352,876
Estimated Project Costs
Project Funding
ITEM
RECONSTRUCTION
AREA
RECLAMATION
AREA TOTAL
Ad Valerum $465,996 $338,286 $804,282
Assessments (40%)$354,788 $225,524 $580,312
Utility Fund -Sewer $320,180 $0 $320,180
Utility Fund -Water $323,140 $14,590 $337,730
Water Quality Fund $86,186 $0 $86,186
Assessment Roll (Per Unit) Reconstruction $10,434.94
Assessment Roll (Per Unit) Reclamation $4,337.00
Total $1,550,290 $578,400 $2,128,690
Estimated Assessments
•MN State Statute Chapter 429 Requires Assessment to be a minimum
of 20% of Bonding Amount
•Street and Storm Assessment 10 Year Period
•Assessment Rate 2% greater than Project Bond Rate (2015 Rate
4.44%)
•More details will Emerge During Public Hearing and Assessment
Hearing Meetings and Mailings
Reconstruction Reclamation
Assessment (40%)
Street & Storm $354,788 $255,524
Assessment –Unit Method
Assessable Units -Reconstruction 34 Units
Assessable Units –Reclamation 52 Units
Estimated Unit Assessment –
Reconstruction $10,434.94/Unit
Estimated Unit Assessment –
Reclamation $4,337.00/Unit
Assessment Map
Public Improvement Process
Preliminary Project Schedule
ACTIVITY DATE
Held First Informational Meeting October 19, 2016
Accept Feasibility Report / Call for Public Hearing Tonight
Second Informational Meeting December 2016
Conduct Public Hearing/Order Project December 12, 2016
Third Informational Meeting February 2017
Approve Plans and Specifications / Order Advertisement for Bids February 2017
Open Bids March 2017
Accept Bids/Award Contract April 2017
Begin Construction April/May 2017
Complete Base Course of Bituminous Pavement October 2017
Authorize Amount to be Assessed/Schedule Assessment Hearing October 2017
Conduct Assessment Hearing/Adopt Assessment Roll October 2017
Project Feedback
Neighborhood Informational Meeting
•Held October 19, 2016
•Approx. 10 property owners in attendance
•Introduction to the project
•Discussed typical project, process, and timeline
Project Questionnaire
•15 questionnaires filled out and turned into City
•Concerns about lack of street lighting
•Concerns about high vehicle speeds
•Concerns about access during construction
Assessment Review Workgroup
•Met on November 16, 2016
•Reviewed the Assessment Map
•Reviewed the Estimated Project Cost
•Reviewed the Unit Method of Assessment
•Discussed the Combination of the Assessments
•Reviewed the Estimated Assessment Amount
Recommended Actions
Resolution
•Accept Feasibility Report
•Calls for Public Hearing on December 12, 2016
Staff Recommendation
•Approve Proposed Resolution
Before & After Photos
Questions/Comments