HomeMy WebLinkAbout9C Cates Area Accept Feasibility Presentation2017 Street Reconstruction Project –
Cates Street Area Improvements
Cates Street, Albany Avenue, CJ Circle, Five Hawks Avenue, Park
Avenue
November 28, 2016
City Council Meeting
Agenda
•Project Objectives
•Project Area
•Existing Conditions/Proposed
Improvements
•Review Methods
•Estimated Project Costs
•Estimated Preliminary
Assessments
•Special Assessment Process (MN
Statutes Chapter 429)
•Preliminary Project Schedule
•Project Feedback
•Recommended Action
Project Objectives
•Reconstruct Deteriorated Streets
•Upgrade/Install City Underground Utilities
•Sanitary Sewer
•Watermain
•Storm Sewer
Project Area
Street Improvements
Street Improvements
•Two Improvement Methods
•Reclaim
•Reconstruct
Street Improvements
(Method 1 -Reconstruction)
•Cates Street, Albany Avenue, CJ Circle and Five
Hawks Avenue
•Existing bituminous streets with little concrete curb and gutter
•Albany Avenue -proposed 28’ width (26’ existing width) with B618
concrete curb & gutter
•All other streets -proposed 30’ width (match existing width) with B618
concrete curb & gutter
•7-ton design street section
•4” Bituminous
•8” Aggregate Base
•12” Granular Material
•Proposed hammerhead turnaround at the end of Five Hawks Avenue
Street Improvements
(Method 2 –Reclamation)
•Park Avenue
•Existing 26’ width with surmountable concrete curb & gutter
•Existing concrete curb and gutter to remain in place (spot repairs)
•7-ton design street section
•4” Bituminous
•8” Reclaim Material
What’s Under the Street
Utility Improvements -Reconstruct Area
Proposed Utility Improvements –Reconstruct Area
•Sanitary Sewer: Replace 8” VCP with 8” PVC
•Water Main: Replace existing with 8” PVC
•Storm Sewer: Replace existing pipes and
catch basins
Utility Improvements –Park Avenue
Proposed Utility Improvements –Park Avenue (Reclaim)
•Sanitary Sewer: No pipe replacement
•Water Main: Replace valves and hydrants
•Storm Sewer: No existing storm sewer
Estimated Project Costs
(Reconstruction)
Estimated Project Costs and Financing (Reconstruction)
ITEM ESTIMATED PROJECT COSTS ASSESSMENTS CITY SHARE
Streets $995,150 $398,060 $597,090
Sanitary Sewer $229,180 $229,180
Watermain $371,180 $371,180
Storm Sewer1 $62,960 $17,184 $45,776
Total $1,658,470 $415,244 $1,243,226
1 Includes $20,000 in Water Quality Improvements that are not assessable
Estimated Project Costs
(Reclamation)
Estimated Project Costs and Financing (Reclamation)
ITEM ESTIMATED PROJECT COSTS ASSESSMENTS CITY SHARE
Streets $192,530 $77,012 $115,518
Sanitary Sewer $1,320 $1,320
Watermain $24,240 $24,240
Total $218,090 $77,012 $141,078
Total Project Cost
ITEM RECONSTRUCTION AREA RECLAMATION AREA TOTAL
Ad Valerum $597,090 $115,518 $712,608
Assessments (40%)$415,244 $77,012 $492,256
Utility Fund -Sewer $229,180 $1,320 $230,500
Utility Fund -Water $371,180 $24,240 $395,420
Water Quality Fund $45,776 $0 $45,776
Assessment Roll (Per Unit) Reconstruction $6,106.53
Assessment Roll (Per Unit) Reclamation $4,477.44
Total $1,658,470 $218,090 $1,876,560
Estimated Project Costs
Estimated Assessments
•MN State Statute Chapter 429 Requires Assessment to be a minimum
of 20% of Bonding Amount
•Street and Storm Assessment 10 Year Period
•Assessment Rate 2% greater than Project Bond Rate (2015 Rate
4.44%)
•More details will Emerge During Public Hearing and Assessment
Hearing Meetings and Mailings
Reconstruction Reclamation
Assessment (40%)
Street & Storm $415,244 $77,012
Assessment –Unit Method
Assessable Units -Reconstruction 68 Units
Assessable Units –Reclamation 17.2 Units
Estimated Unit Assessment –
Reconstruction $6,106.53/Unit
Estimated Unit Assessment –
Reclamation $4,477.44/Unit
Assessment Map
Public Improvement Process
Preliminary Project Schedule
ACTIVITY DATE
Held First Informational Meeting October 19, 2016
Accept Feasibility Report / Call for Public Hearing Tonight
Second Informational Meeting December 2016
Conduct Public Hearing/Order Project December 12, 2016
Third Informational Meeting February 2017
Approve Plans and Specifications / Order Advertisement for Bids February 2017
Open Bids March 2017
Accept Bids/Award Contract April 2017
Begin Construction April/May 2017
Complete Base Course of Bituminous Pavement October 2017
Authorize Amount to be Assessed/Schedule Assessment Hearing October 2017
Conduct Assessment Hearing/Adopt Assessment Roll October 2017
Project Feedback
Informational Meeting
•Held October 19, 2016
•Approx. 18 property owners in attendance
•Introduction to the project
•Discussed typical project, process, and timeline
Project Questionnaire
•17 questionnaires filled out and turned into City
•Concerns expressed about sidewalk installation
•Concerns expressed about ponding at Cates and in driveways
•Interests in more street lighting
Assessment Review Workgroup
•Met on November 16, 2016
•Reviewed the Assessment Map
•Reviewed the Estimated Project Cost
•Reviewed the Unit Method of Assessment
•Discussed the Combination of the Assessments
•Reviewed the Estimated Assessment Amount
Recommended Actions
Resolution
•Accept Feasibility Report
•Call for Public Hearing on December 12, 2016
Staff Recommendation
•Approve Proposed Resolution
Before & After Photos
Questions/Comments