HomeMy WebLinkAbout9E Franklin Trl Area Accept Feasibility Presentation2017 Street Reconstruction Project –
Franklin Trail Improvements
Franklin Trail
November 28, 2016
City Council Meeting
Agenda
•Project Objectives
•Project Area
•Existing Conditions/Proposed
Improvements
•Review Methods
•Estimated Project Costs
•Estimated Preliminary
Assessments
•Special Assessment Process (MN
Statutes Chapter 429)
•Preliminary Project Schedule
•Project Feedback
•Recommended Action
Project Objectives
•Reconstruct Deteriorated Streets
•Upgrade/Install City Underground Utilities
•Sanitary Sewer
•Watermain
•Storm Sewer
Project Area
Street Improvements
Street Improvements
•Reconstruction Improvement Method
Street Improvements
(Reconstruction)
•Franklin Trail
•State Aid collector street
•Existing bituminous street with B618 concrete curb & gutter
•Proposed 44’ wide with B618 concrete curb and gutter to match existing
width
•Removal and replacement of existing sidewalk
•9-ton design street section to meet State Aid Standards
•5” Bituminous
•12” Aggregate Base
•12” Granular Material
•Potential improvements at the intersection of Franklin Trail and Park
Nicollet Avenue
•Traffic Study currently underway
•Potential options include a Roundabout, Mini Roundabout, Left
Turn Lanes, and an All Way Stop
Street Improvements
(Reconstruction)
•Bluff Heights Trail
•Existing bituminous street with no curb and gutter
•Proposed standard 32’ width with B618 concrete curb & gutter
•Proposed sidewalk extension from Franklin Trail to Timber Crest Park
•7-ton design street section
•4” Bituminous
•8” Aggregate Base
•12” Granular Material
What’s Under the Street
Utility Improvements
Proposed Utility Improvements
•Sanitary Sewer: Replace 8” VCP and 12” RCP
with new PVC pipe
•Water Main: Replace existing with 8” PVC
•Storm Sewer: Replacement and extension of
storm sewer system
Estimated Project Costs
Estimated Project Costs and Financing
ITEM
ESTIMATED PROJECT
COSTS ASSESSMENTS CITY SHARE
Streets2 $1,520,720 $505,096 $1,015,624
Sanitary Sewer $434,560 $434,560
Watermain $517,070 $517,070
Storm Sewer1 $193,600 $69,440 $124,160
Total $2,665,950 $574,536 $2,091,414
1 Includes $20,000 in Water Quality Improvements that are not assessable
2 Includes $257,980 in street oversizing costs that are not assessable
Estimated Project Costs
Project Funding
ITEM PROJECT TOTAL
Ad Valerum $1,015,624
Assessments (40%)$574,536
Utility Fund -Sewer $434,560
Utility Fund -Water $517,070
Water Quality Fund $124,160
Assessment Roll (Per Acre) Reconstruction $18,035.52
Total $2,665,950
Estimated Assessments
•MN State Statute Chapter 429 Requires Assessment to be a minimum
of 20% of Bonding Amount
•Street and Storm Assessment 10 Year Period
•Assessment Rate 2% greater than Project Bond Rate (2015 Rate
4.44%)
•More details will Emerge During Public Hearing and Assessment
Hearing Meetings and Mailings
Reconstruction
Assessment (40%)
Street & Storm $574,536
Assessment –Area Method
Assessable Area 31.9 Acres (rounded)
Estimated Area Assessment $18,035.52/Acre
Assessment Map
Public Improvement Process
Preliminary Project Schedule
ACTIVITY DATE
Held First Informational Meeting October 19, 2016
Accept Feasibility Report / Call for Public Hearing Tonight
Second Informational Meeting December 2016
Conduct Public Hearing/Order Project December 12, 2016
Third Informational Meeting February 2017
Approve Plans and Specifications / Order Advertisement for Bids February 2017
Open Bids March 2017
Accept Bids/Award Contract April 2017
Begin Construction April/May 2017
Complete Base Course of Bituminous Pavement October 2017
Authorize Amount to be Assessed/Schedule Assessment Hearing October 2017
Conduct Assessment Hearing/Adopt Assessment Roll October 2017
Assessment Review Workgroup
•Met on November 16, 2016
•Reviewed the Assessment Map
•Reviewed the Estimated Project Cost
•Reviewed the Method of Assessment: Area vs Unit
•Reviewed the Estimated Assessment Amount
Project Feedback
Informational Meeting
•Held October 19, 2016
•Approx. 5 property owners in attendance
•Introduction to the project
•Discussed typical project, process, and timeline
Project Questionnaire
•3 questionnaires filled out and turned into City
•Concerns expressed about current traffic speed
•Concerns expressed about access during construction
Recommended Actions
Resolution
•Accept Feasibility Report
•Call for Public Hearing on December 12, 2016
Staff Recommendation
•Approve Proposed Resolution
Before & After Photos
Questions/Comments