HomeMy WebLinkAbout9F Sycamore Trail Accept Feasibility Presentation2017 Street Reconstruction Project –
Sycamore Trail Improvements
Sycamore Trail
November 28, 2016
City Council Meeting
Agenda
•Project Objectives
•Project Area
•Existing Conditions/Proposed
Improvements
•Review Methods
•Estimated Project Costs
•Estimated Preliminary
Assessments
•Special Assessment Process (MN
Statutes Chapter 429)
•Preliminary Project Schedule
•Project Feedback
•Recommended Action
Project Objectives
•Reconstruct Deteriorated Streets
•Upgrade/Install City Underground Utilities
•Sanitary Sewer
•Watermain
•Storm Sewer
Project Area
Street Improvements
Street Improvements
•Reconstruction Improvement Method
Street Improvements
(Reconstruction)
•Sycamore Trail
•Existing bituminous street with small amount of concrete curb and gutter
•Existing street width varies from 16’-23’
•Proposed City standard 24’ width with B618 concrete curb & gutter
•7-ton design street section
•4” Bituminous
•8” Aggregate Base
•12” Granular Material
•No turnaround exists at the end of the street
Dead-End Issues
•Length Exceeds the City Ordinance of 500 feet
•Emergency Access
•Construction Access
•Use of Private Property to Turn Around
•Unsafe Backing Up
•Garbage Truck Operations
•Snow Removal and Other Public Works Operations
•Lack of Neighborhood Connectivity
Dead-End Options
Option 1
•Reconstruct the roadway with no turnaround (match
existing condition)
•Pros:
•Lowest Cost Option
•Lowest Estimated Assessment Amount
•Preferred Option by the Willow Beach Association
Dead-End Options
Option 1
•Reconstruct the roadway with no turn-around (match
existing condition)
•Cons:
•Exceeds City Ordinance
•Emergency Access
•Construction Access
•Use of Private Property to Turn Around
•Unsafe Backing Up Operation
•Garbage Truck Operations
•Public Works Operations
•Lack of Neighborhood Connectivity
Dead-End Options
Option 2
•Install a Small Cul-de-sac
Dead-End Options
Option 2
•Install a Small Cul-de-sac
•Pros:
•Removes Use of Private Property to Turn Around
•Removes Unsafe Backing Up Operation
•Garbage Truck Operations Improved
•Public Works Operations Improved
Dead-End Options
Option 2
•Install a Small Cul-de-sac
•Cons:
•Medium Cost Option With Higher Assessment
than Option 1
•Right of Way/Easement Purchase
•Addition of Retaining Wall
•Exceeds City Ordinance for Length
•Emergency Access
•Construction Access
•Lack of Neighborhood Connectivity
Dead-End Options
Option 3
•Install a Hammer Head Type Turnaround
Dead-End Options
Option 3
•Install a Hammer Head Type Turnaround
•Pros:
•Removes Use of Private Property to Turn Around
•Removes Unsafe Backing Up Operation
•Garbage Truck Operations Improved
•Public Works Operations Improved
•Lower Cost than Option 2
•Slightly Higher Assessment than Option 1
•City Staff Recommended Option
Dead-End Options
Option 3
•Install a Hammer Head Type Turnaround
•Cons:
•Right of Way/Easement Purchase
•Addition of Retaining Wall
•Exceeds City Ordinance for Length
•Emergency Access
•Construction Access
•Lack of Neighborhood Connectivity
Dead-End Options
Option 4
•Extend Sycamore Trail to Willow Beach Street
Dead-End Options
Option 4
•Extend Sycamore Trail to Willow Beach Street
•Pros:
•Removes Use of Private Property to Turn Around
•Removes Unsafe Backing Up Operation
•Garbage Truck Operations Improved
•Public Works Operations Improved
•Emergency Access Improved
•Eliminates Variance from City Code
•Construction Access Improved
•Provides Neighborhood Connectivity
Dead-End Options
Option 4
•Extend Sycamore Trail to Willow Beach Street
•Cons:
•Highest Cost Option
•Highest Assessment
•Addition of Retaining Wall
•Willow beach Association Opposition
•Neighborhood Opposition
What’s Under the Street
Utility Improvements
Proposed Utility Improvements
•Sanitary Sewer: Replace service
lines with 4-inch PVC pipe
•Water Main: Replace with 8”
PVC. Replace service lines
•Storm Sewer: Replacement of
crossing and treatment for
Water Quality
Estimated Project Costs
Project Funding
ITEM
PROJECT COSTS
OPTION 1 OPTION 2 OPTION 3 OPTION 4
Ad Valerum $209,694 $259,296 $240,378 $319,740
Assessments (40%)$151,348 $184,416 $171,804 $228,792
Utility Fund -Sewer $40,100 $40,100 $40,100 $40,100
Utility Fund -Water $201,830 $201,830 $201,830 $201,830
Water Quality Fund $37,328 $37,328 $37,328 $43,448
Assessment Roll (Per Unit)$9,459.25 $11,526.00 $10,737.75 $12,710.67
Total $640,300 $722,970 $691,440 $833,910
Estimated Assessments
•MN State Statute Chapter 429 Requires Assessment to be a minimum
of 20% of Bonding Amount
•Street and Storm Assessment 10 Year Period
•Assessment Rate 2% greater than Project Bond Rate (2015 Rate
4.44%)
•More details will Emerge During Public Hearing and Assessment
Hearing Meetings and Mailings
Option 1 Option 2 Option 3 Option 4
Assessment (40%)
Street and Storm $151,348 $184,416 $171,804 $228,792
Assessment –Unit Method
Assessable Units -Reconstruction 16 Units 16 Units 16 Units 18 Units
Estimated Unit Assessment –
Reconstruction
$9,459.25
/Unit
$11,526.00
/Unit
$10,737.75
/Unit
$12710.67
/Unit
Assessment Map
Public Improvement Process
Preliminary Project Schedule
ACTIVITY DATE
Held First Informational Meeting October 19, 2016
Accept Feasibility Report / Call for Public Hearing Tonight
Second Informational Meeting December 2016
Conduct Public Hearing/Order Project December 12, 2016
Third Informational Meeting February 2017
Approve Plans and Specifications / Order Advertisement for Bids February 2017
Open Bids March 2017
Accept Bids/Award Contract April 2017
Begin Construction April/May 2017
Complete Base Course of Bituminous Pavement October 2017
Authorize Amount to be Assessed/Schedule Assessment Hearing October 2017
Conduct Assessment Hearing/Adopt Assessment Roll October 2017
Assessment Review Workgroup
•Met on November 16, 2016
•Reviewed the Assessment Map
•Reviewed the Estimated Project Cost
•Reviewed the Unit Method of Assessment
•Reviewed the Estimated Assessment Amount
•Reviewed the Dead End Options
Project Feedback
Informational Meeting
•Held October 19, 2016
•Approx. 10 property owners in attendance
•Introduction to the project
•Discussed typical project, process, and timeline
Project Questionnaire
•8 questionnaires filled out and turned into City plus a petition
•Concerns expressed over the width of street
•Concerns expressed about lack of street lights
•Expressed desire for no turnaround or road extension
Recommended Actions
Resolution
•Accept Feasibility Report
•Call for Public Hearing on December 12, 2016
Staff Recommendation
•Approve Proposed Resolution
Before & After Photos
Questions/Comments