HomeMy WebLinkAbout01 23 2017 Joint Water Treatment Facility Discussion PresentationWater Planning &
Joint Water Facility
City Council Work Session
January 23, 2017
Purpose
•Review City water supply needs
•Review options to meet needs
•Partnership with SMSC
•Agreement Terms
•Funding
•Council direction to inform
agreement negotiations
Prior Lake Existing Water System
Water Treatment Plant (WTP) –7.5 MGD
Seven (7) wells
6 wells pump to WTP
1 well not connected (Well 6 –Wilds well)
Used during peak times, not treated (has Fe and Mn)
Firm pumping capacity is pumping rate with largest well out
of service
Firm pumping capacity is 5.26 MGD (24 hour pumping)
Storage
3.25 MG of storage (elevated and ground storage)
2012 Water Issues
Summer of 2012 high water demand
Hot weather and little to no rain
Towers (storage) balance the system
Draw from towers during day (peak usage period)
Fill towers during night (lower usage period)
Risk of Water Ban
Ran all wells during high demand
Not meeting demands
Could not keep towers full
At Risk for water shortage if we lose a well
Added pressure on aquifer (extended pumping)
Prior Lake Existing Agreement
Prior Lake has an agreement with SMSC for water supply
Original agreement for 1 MGD
SMSC constructed a 3rd well in 2015
Revised agreement for 1.2 MGD
Additional well increases Prior Lake’s firm capacity
Allows postponement of Well 10 in CIP
Planning for Water Infrastructure
Significant planning and preparation required for water
infrastructure (WTP, wells and storage)
Permitting (MDH, DNR, water appropriations, etc.)
Design
Construction
Coordination of wells with SMSC
Possible interference (close proximity of wells)
Geology of the area -challenging
Planning for Water Infrastructure
2020 Projected Peak Day Demand 6.95 MGD
Additional Source, Treatment and storage will be needed
at this time
Estimated $16.0 million for:
Two additional wells
WTP
Storage
What are the options?
Prior Lake builds WTP, wells and storage
Seek a Partnership
SMSC
Savage
Currently have 2 interconnects
Different water quality
Cost of Water
Option 1 –Prior Lake Build
Construct new WTP
Use well 6 –pipe to new WTP
Drill new wells (at least 2 to provide firm capacity)
Storage requirements
Elevated
Ground (part of WTP)
Option 2 –Partnership w/SMSC
Size new WTP for both SMSC and Prior Lake
Fe and Mn removal for both Prior Lake and SMSC
Reverse osmosis for SMSC
Use existing wells
Prior Lake Well #6
SMSC –3 existing wells
Meet firm pumping capacity requirements
Storage requirements
Elevated
Ground (part of WTP)
Benefit of Partnership
Prior Lake Only SMSC Only
Joint Prior Lake/SMSC
4.74 MGD
Backwash Pumps
Chemical Feed
Reclaim Tanks
4 Wells
Storage
Prior Lake
HSPs
SMSC
RO
HSPs
2.10 MGD
3 -Filters
3 -HSPs
3 Wells
Storage
2.64 MGD
3 –Filters
RO
3 -HSPs
3 Wells
Storage
Estimated Costs
Estimated Construction Costs
Water Treatment Facility
June 2016
ITEM
NO.
ITEM DESCRIPTION ESTIMATED COST
SMSC Prior Lake Joint Facility
1 Performance Bond & Insurance $250,000 $250,000 $425,000
2 Mobilization $420,000 $420,000 $550,000
3 Excavation, Utilities, Roads, Landscaping $2,180,000 $1,450,000 $2,650,000
4 Reinforcing Steel, Concrete Work, Precast $2,150,000 $1,950,000 $2,750,000
5 Masonry $950,000 $950,000 $1,250,000
6 Structural & Miscellaneous Metals $250,000 $250,000 $325,000
7 Rough & Finished Carpentry $75,000 $75,000 $85,000
8 EPDM Roofing, Insulation, Caulking $145,000 $145,000 $245,000
9 H.M. Doors, Overhead Doors $110,000 $110,000 $140,000
10 Painting and Interior Finishes $250,000 $250,000 $325,000
11 Process Equipment $2,275,000 $1,750,000 $3,150,000
12 Process Piping & Mechanical $2,320,000 $2,100,000 $2,950,000
13 Electrical, Controls & Generator $2,150,000 $1,950,000 $2,700,000
14 2 –Additional Wells $0 $1,500,000 $0
15 Raw Water Lines $0 $1,000,000 $1,000,000
Subtotal $13,525,000 $14,150,000 $18,545,000
Contingency –5%$675,000 $707,500 $927,250
ESTIMATED CONSTRUCTION COST $14,200,000 $14,857,500 $19,472,250
Estimated Costs
Construction Cost Comparison
Estimated
Construction
Cost
Community’s
Share of Joint
Facility
Total Savings
with Joint
Facility
SMSC $14,200,000 $10,804,238 $3,395,762
Prior Lake $14,857,500 $8,668,013*$6,189,487
Joint $19,472,250
*Current Agreement includes capital in volume wholesale rate ($/1,000 gallons
purchased). No up front capital was required.
Partnership with SMSC
Prior Lake owns source water
Prior Lake only pays for treatment of water
Prior Lake responsible for building wells and raw
watermains to SMSC WTP
Prior Lake responsible for operation and maintenance
of wells
Potential sale of raw water to SMSC
Agreement Terms
Responsibilities
Design and Construction SMSC with approvals by the City at key points in the process.
Operation The SMSC will own and operate the plant. A separate operational agreement
will be drafted such that treatment at all three plants is optimized.
Water Allocation
Perpetual Right The City will have a perpetual right to treatment of water.
Allocation Amount 2.1 million gallons per day (MGD).
Payments
Fixed Annual The City’s share of the permanent assets is estimated to be $9.968 million
(includes engineering, admin, legal). The City will make fixed annual
payments for 25 years financed at 3%.
Operation, Maintenance
and Replacement
Actual cost to operate and maintain the Prior Lake portion of the treatment
plant paid at a rate per 1,000 gallons actually pumped. Fixed for first five
years with annual review and adjustment thereafter.
Permanent Asset
Replacement
Addresses financing or reserve of funds for future replacements or expansions
not accounted for in the OM&R.
Agreement Terms
Enforcement and Remedy
Limited Waiver of
Sovereign Immunity
SMSC has indicated a willingness to provide a limited waiver of sovereign
immunity in lieu of a cash escrow. Should the SMSC default on the agreement,
the City would have the right to bring suit against the SMSC in Scott County
District Court using Minnesota Laws specially related to this agreement.
Option B for Default If the SMSC does not agree to a limited waiver of sovereign immunity, the
other remedy option for default is the use of an escrow account. In this option
the SMSC would establish an escrow account which will increase annually to
equal the amount of the City’s Fixed payments. These funds would be
available to the City in case of an SMSC default.
Other
Term The agreement has a perpetual term.
Termination Termination of the agreement must be mutually agreed upon.
Annexation Area The agreement will address SMSC purchase of land in the City’s
comprehensively planned areas for annexation and development.
Funding Sources
Fixed Payment
Water Storage Fund ($1.5 million)
Trunk Fund ($900,000)
3 Primary Sources
Trunk Water Charge (Acre)
Water Tower Charge (Unit)
Water Connection Charge (Unit)
Secondary Funding Source –Water Fund
Operation, Maintenance, and Replacement
User Rates
Next Steps
Additional Negotiation based on Council Input
SMSC Business/General Council Approval March 2017
City Council Approval March/April 2017
Design 4-6 Months
Regulatory Review ~6 Weeks
Construction 20 months (Start late summer 2017)
WTF online Spring 2019