RESOLUTION 17-068
A RESOLUTION ACCEPTING BIDS AND AUTHORIZING THE EXECUTION OF THE CITY’S
STANDARD CONSTRUCTION CONTRACT FOR THE PURCHASE AND INSTALLATION OF
THE MAINTENANCE CENTER ROOF
Motion By: McGuire Second By: Burkart
WHEREAS, The Maintenance Center roof project was identified in the 2017 Capital Improvement
Program; and
WHEREAS, The City received bids from six qualified vendors
Company Base Bid Alternate 1 Total
Ballman Roofing $211,278 $148,479 $359,757
GAG Sheet Metal $243,800 $350,950 $594,750
Thomas Finn Co $459,904 $155,509 $615,413
Commercial Roofing $285,575 $121,880 $406,455
Nieman Roofing $266,000 $194,000 $460,000
McPhillips Roofing $325,000 $95,000 $420,000
; and
WHEREAS, Ballman Roofing is a qualified vendor and has been recommended by Oertel Architects, the
architect for the project, and;
WHEREAS, City Staff recommends award of the City’s Standardized Construction Contract to
Ballman Roofing, for the City’s Maintenance Center Roof Replacement
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and the City Manager are authorized to execute the City’s Standardized Cosntruction
Contract with Ballman for an amount of $ 359,757.00.
3. Funding for these services will be drawn from Account # 440-49400.00-55520.00
Passed and adopted by the Prior Lake City Council this 22nd day of May, 2017
VOTE Briggs McGuire Thompson Braid Burkart
Aye ☒ ☒ ☒ ☒ ☒
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☐ ☐ ☐
______________________________
Frank Boyles, City Manager