HomeMy WebLinkAbout9A 2017 CIP Project Update2017 CIP Project Update Before and After 2017 Mill & Overlay Project Cardinal Ridge Neighborhood Before and After 2017 Mill & Overlay Project Five Hawks Franklin Trail •Pipe work between Brunswick and Bluff Hts Trail •Work somewhat behind schedule •Working around private utilities and traffic •Second pipe crew coming •Contaminated soil Aug. 14th Franklin Trail Balsam Area •Work on track •1-2 weeks of remaining pipework •Street construction underway Balsam Area Cates Area Cates Area and Sycamore Trail •Removals occurring •Cates area to begin in 1-2 weeks when Balsam pipe workers complete •Sycamore Trail to begin in early September