HomeMy WebLinkAbout5N 4 Sycamore Trail Assessment Report
4646 Dakota Street SE
Prior Lake, MN 55372
CITY COUNCIL AGENDA REPORT
MEETING DATE: SEPTEMBER 18, 2017
AGENDA #: 5N (4)
PREPARED BY: NICK MONSERUD, PROJECT ENGINEER
PRESENTED BY: NICK MONSERUD
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION DECLARING COSTS TO BE AS-
SESSED AND ORDERING PREPARATION OF AN ASSESSMENT ROLL AND
ESTABLISHING THE DATE OF THE ASSESSMENT HEARING FOR THE SYC-
AMORE TRAIL ROAD RECONSTRUCTION IMPROVEMENT PROJECT (PRO-
JECT #TRN17-000005)
DISCUSSION: Introduction
This agenda item is necessary to set an assessment hearing and to establish the
amount to be assessed for the Sycamore Trail Road Improvement Project.
History
Each year the City reconstructs street segments that are scheduled for reconstruc-
tion as part of its Capital Improvement Program (CIP) and have exceeded their
useful design life. The City uses the Capital Improvement Program and its Pave-
ment Management Program to plan for infrastructure improvements and the fi-
nancing for capital improvements. At its September 26, 2016 meeting the City
Council adopted Resolutions 16-118, 16-119, 16-120 and 16-121 authorizing staff
to prepare Feasibility Reports for the 2017 Improvement Projects as outlined in the
CIP.
The M.S. Chapter 429 process applies to all projects that will be financed in whole
or in part through special assessments or bond proceeds.
For bidding purposes the four project areas have been combined into one project.
This was done to simplify the bidding process and to better coordinate construc-
tion scheduling with one contractor.
Sycamore Trail includes improvements to Maplewood Townsite, RLS 33, RLS 94,
RLS 108, and Willows 1st Addition located in Section 3, Township 114, Range 22.
Structures in this area were built between 1928-1988 but most were generally built
in the 1970’s. The proposed improvements include street reconstruction or recla-
mation, storm sewer, storm water quality, sanitary sewer, watermain, concrete
curb and gutter, and appurtenant work.
At the November 28th, 2016 City Council meeting, the Council accepted the feasi-
bility study and scheduled the Public Hearing for January 23rd, 2017.
On January 23, 2017, the City Council held the Public Hearing and adopted Reso-
lution 17-010 ordering the improvement project.
2
Several options for a turnaround were brought to City Council and discussed, ulti-
mately staff was directed to provide a design for a hammerhead. Discussions with
the residents at the end of Sycamore Trail and the Willow Beach Association ulti-
mately determined the design in the plan set at the time. Residents of Sycamore
Trail still opposed a turnaround and requested to have it removed from the design
and the cost applied to burying the electric/cable TV lines.
In addition to the Public Hearing, the City has held three informational meetings to
discuss the project. The last informational meeting was an open house held on
March 29, 2017 and offered residents the opportunity to comment on the proposed
plans. City staff explained the proposed design and went over potential property
impacts individually with residents.
On April 10, 2017 the City Council approved the project plans and specifications
and authorized the advertisement for bids for the 2017 Reconstruction Improve-
ment Projects.
On May 22, 2017 the City Council accepted bids and awarded the City’s standard-
ized construction contract for the 2017 Reconstruction Improvement Projects to
Geislinger and Sons, Inc. At this time the City Council removed the proposed
hammerhead turnaround from the project.
Current Circumstances
The proposed improvements include street reconstruction, storm sewer, storm wa-
ter quality, sanitary sewer, watermain, concrete curb and gutter, and appurtenant
work. Construction of the project is currently ongoing with the anticipated substan-
tial completion date of October 31, 2017.
ISSUES: The Assessment Review Work Group has reviewed and agrees with the assess-
ment map, assessment rate, and method of assessment.
Pursuant to the Assessment Policy, the street and storm sewer reconstruction
should be assessed at up to 40% of the total project cost against the benefiting
properties. As been in past practice in residential neighborhoods, the Assessment
Review Workgroup recommends the unit method of assessment due to the fact that
lots in the project area are of similar size. The remaining amounts should be recov-
ered through the general ad valorem property tax.
The estimated assessment rate per the Feasibility Report is proposed at
$9,459.25/unit. A number of residents have shared their concerns that the as-
sessment rate was high and they are hoping for lower assessments once the bids
have been received. With the bids received, the estimated proposed assessment
is $10,527/unit. The project bid included the hammerhead turnaround. After
awarding the contract, the hammerhead turnaround was removed from the project
allowing additional savings, resulting in a revised assessment amount of
$9,142.22 per unit.
3
FINANCIAL
IMPACT:
The Sycamore Trail Road Improvement Project is proposed to be financed by Spe-
cial Assessments, tax levy, Sewer Fund, Water Fund, and Water Quality Fund. The
amount shown in the table below is an estimate based on the bid prices received.
Funding sources and amounts are as shown below:
Estimated Project Costs and Financing (Option 1)
ITEM
ESTIMATED PRO-
JECT COSTS ASSESSMENTS CITY SHARE
Streets2 $321,136 $128,454 $192,681
Sanitary Sewer $17,899 $17,899
Watermain $178,000 $178,000
Storm Sewer1,2 $79,884 $17,821 $62,063
Total $596,919 $146,276 $450,643
1 Includes $35,331 in Water Quality Improvements that are not assessable
2 Includes Option 1 - Dead End
Total Assessed $146,276
Number of Units 16
Unit Assessment $9,142.22
Unit Assessment from Prelim Report $9,459.25
ALTERNATIVES: 1. Motion and second as part of the consent agenda to approve a resolution de-
claring the costs to be assessed, ordering the preparation of the proposed as-
sessment rolls for the Sycamore Trail Road Improvement Project #TRN17-
000005, and establishing October 16, 2017 for the assessment hearing date.
2. Motion and second to remove this item from the consent agenda for additional
discussion.
RECOMMENDED
MOTION:
Motion and second for approval of alternative #1.
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 17-___
A RESOLUTION DECLARING COSTS TO BE ASSESSED AND ORDERING PREPARATION OF
PROPOSED ASSESSMENT ROLL FOR THE SYCAMORE TRAIL ROAD IMPROVEMENT PROJECT
#TRN17-000005 AND ESTABLISHING THE DATE OF THE ASSESSMENT HEARING AND
PUBLICATION THEREOF
Motion By: Second By:
WHEREAS,
WHEREAS,
Costs have been determined for the improvement of Sycamore Trail, Project
#TRN17-000005, the total cost for the improvements are $596,919; and
The City Manager notifies the City Council that such proposed assessment will be
completed and filed in the City Manager’s office for public inspection.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1.The recitals set forth above are incorporated herein.
2.The portion of the cost of such improvements to be paid by the City is hereby declared to be $450,643,
and the portion of the cost to be assessed against benefited property owners is declared to be $146,276.
3.Assessments shall be payable on an equal principal installment method extending over a period of 10
years for street improvements. The first installment shall be the annual principal plus interest calculated
from the public hearing date to the end of this year plus twelve months of the next year and shall bear
interest at the rate of 3.80% per annum from the date of the adoption of the assessment resolution.
4.The City Manager, with the assistance of the City Engineer shall forthwith calculate the proper amount to
be specially assessed for such improvements against every assessable lot, piece or parcel of land within
the district affected, without regard to cash valuation, as provided by law, and shall file a copy of such
proposed assessment in the office of the City Manager for public inspection.
5.The City Manager shall upon the completion of such proposed assessment notify the City Council thereof.
6.A public hearing shall be held on the 16th day of October, 2017, in City Council Chambers at 7:00 P.M.
to pass upon such proposed assessment and at such time and place all persons owning property affected
by such improvement will be given the opportunity to be heard with reference to such assessment.
7.The City Manager is hereby directed to cause a notice of the public hearing on the proposed assessment
to be published once in the official newspaper of the City at least two weeks prior to the hearing, and the
City Manager shall also cause mailed notice to be given to the owner of each parcel des cribed in the
assessment roll not less than two weeks prior to the hearing.
8.The owner of any property so assessed may, at any time prior to certification of the assessment to the
County Auditor, pay the whole of the assessment on such property, with intere st accrued to the date of
payment, to the City Finance Director, except that no interest will be charged if the entire assessment is
paid within 30 days from the adoption of the assessment. The owner may, at any time thereafter, pay to
the City Finance Director the entire amount of the assessment remaining unpaid, with interest accrued to
December 31 of the year in which such payment is made. Such payment must be made before November
11 or interest will be charged through December 31 of the succeeding yea r.
2
PASSED AND ADOPTED THIS18th DAY OF SEPTEMBER 2017.
VOTE Briggs McGuire Thompson Braid Burkart
Aye ☐ ☐ ☐ ☐ ☐
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☐ ☐ ☐
______________________________
Frank Boyles, City Manager