Loading...
HomeMy WebLinkAbout7D Sycamore Trail Reconstruction Adopt Assessment PresentationSycamore Trail Reconstruction Improvement Project Assessment Hearing October 16, 2017 Construction Update •Construction began in mid September with the setup of the temporary water services •The project included a temporary street connection to Willow Beach to provide alternative access point to the neighborhood during construction. •They started with watermain, then followed up with sewer and water house services, and then storm sewer. •It is anticipated that the street work will begin next week and should be substantial complete by mid November. Project Schedule ACTIVITY DATE Accept Feasibility Report / Call for Public Hearing Completed Informational Meeting Completed Conduct Public Hearing/Accept Project / Order Plans & Specifications Completed Informational Meeting Completed Approve Plans and Specifications / Order Advertisement for Bids Completed Open Bids Completed Accept Bids/Award Contract Completed Authorize Amount to be Assessed/Schedule Assessment Hearing Completed Construction September to November, 2017 Conduct Assessment Hearing October 16, 2017 Adopt Assessment Roll October 16, 2017 Assessment Map Assessment Calculation Pursuant to the City Assessment Policy, street and storm sewer reconstruction is assessed at 40% of the total project cost to the benefiting properties. Sanitary sewer and watermain costs are paid through the City’s trunk sanitary sewer and water funds. Based on the low bid for the project as well as the actual construction costs to date, the proposed assessment rate is $9,142.22 per unit. The estimated assessment presented in the feasibility report was $9,459.25 per unit. The actual assessment is $317.03 less than the original estimate. Sample Assessment Payments SYCAMORE TRAIL RECONSTRUCTION PROJECT Unit Amount $9,142.22 Term (Years)10 Years APR 3.80% First Year Interest 77 Days Year Principal Interest Annual Payment Remaining Principal Beginning Balance $9,142.22 1 $914.22 $421.71 $1,335.93 $8,228.00 2 $914.22 $312.66 $1,226.89 $7,313.78 3 $914.22 $277.92 $1,192.15 $6,399.55 4 $914.22 $243.18 $1,157.41 $5,485.33 5 $914.22 $208.44 $1,122.66 $4,571.11 6 $914.22 $173.70 $1,087.92 $3,656.89 7 $914.22 $138.96 $1,053.18 $2,742.67 8 $914.22 $104.22 $1,018.44 $1,828.44 9 $914.22 $69.48 $983.70 $914.22 10 $914.22 $34.74 $948.96 $0.00 Totals $9,142.22 $1,985.03 $11,127.25 Assessment Roll No.PID Property Owner Parcel Address Parcel City State Zip Assessible Units Unit Assessment Amount Total Assessments 1 250980010 HACKETT WILLIAM B 3508 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 2 250980020 WARMKA ROBERT E 3498 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 3 250980040 ROBINSON LAURA 3486 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 4 250980050 DAVENPORT WILLIAM G 3478 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 5 250980060 MADER WESLEY M & CHARLOTTE 3470 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 6 250980080 SHORT KIMI C & CHRISTOPHER T 3442 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 7 250980090 JOHNSON MARGARET A 3420 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 8 250980110 SPANIER MICHAEL T & KATHRYN A 3483 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 9 250980130 BAUCHLE JOHN F & DARLA D 3437 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 10 250980160 SUTHERLAND JOSHUA 3415 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 11 250980180 HANSON TIMOTHY D & TAMMIE J 3469 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 12 251060160 SMITH SCOTT J 3385 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 13 251950010 CHOUDEK DANIEL 3454 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 14 252180020 TRUST NUMBER 250 3380 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 15 252180030 CURRY RONALD D & KATHY J 3402 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 16 252180040 EICHTEN THOMAS J & EVE D 3406 SYCAMORE TRL SW PRIOR LAKE MN 55372 1 $9,142.22 $9,142.22 16 $146,275.52 Important Dates •November 15, 2017 Full or partial payments needed by this date to avoid interest. Payments made after this date will include interest for 2017 as well as all of 2018. •May 15, 2018 If no prepayments are made, assessments fill be incorporated into property taxes due beginning on this date. Any Questions?