CITY COUNCIL AGENDA REPORT
MEETING DATE: MARCH 19, 2018
AGENDA #: 8A
PREPARED BY: NICK MONSERUD, ASSISTANT CITY ENGINEER
PRESENTED BY: NICK MONSERUD
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION ACCEPTING PLANS AND SPECI-
FICATIONS AND AUTHORIZING ADVERTISEMENT FOR BIDS FOR 2018 RE-
CONSTRUCTION PROJECTS (CITY PROJECT TRN18-000001)
DISCUSSION: Introduction
The purpose of this agenda item is to accept the final plans and specifications and
authorize advertisement of bids for our 2018 reconstruction projects. Once bids
are received the funding picture becomes clear for the 2018 construction season.
History
The City uses the Five-Year Capital Improvement Program and its Pavement Man-
agement program to plan its infrastructure improvements and the financing for
capital improvements. Two locations are programmed for improvement in 2018:
Woodside/Huron Area and Franklin Trail from Summer St to CSAH 44. In the
spring of 2017, the City Council authorized staff to prepare Feasibility Reports for
the 2018 project locations. The primary purpose for proceeding with these pro-
jects is to upgrade the street condition and utilities. The pavement condition is
poor in these areas and requires reconstruction in accordance with the City’s de-
sire to maintain a high overall condition index (OCI) rating on its roadways. The
proposed improvements include street reconstruction or reclamation, storm sewer,
storm water quality, sanitary sewer, watermain, concrete curb and gutter, and ap-
purtenant work.
The M.S. Chapter 429 process applies to all projects that will be financed in whole
or part through special assessments or bond proceeds.
In December the City Council held Public Hearings for each of the project loca-
tions.
Current Circumstances
The project plans and specifications are complete. The City has an open house
scheduled for April 4 to share the plans with the Public. Notices for this open
house will be mailed to residents 2 weeks prior. Anyone that is not able to attend
the open house but would like to view the plans, can visit the Engineering Depart-
ment in City Hall to view the plans.
In an effort to optimize the bidding and for coordination purposes, staff is propos-
ing to bid the two project areas as one project for construction. Individual assess-
ments for each project area will be computed based on the quantities used for that
project area.
2
Woodside/Huron Area
The design of the Woodside/Huron area incorporates stormwater improvements in
the City owned property south of Woodside Rd. This area is being used to meet
the Prior Lake Spring Lake Watershed District (PLSLWD) rules for stormwater
management. After discussions with the PLSLWD it was recommended to remove
the wetland in this area and expand a stormwater basin into this area. The plans
also include narrowing the roads to reduce the amount of pavement to maintain
and to reduce the overall impervious area within the City. With the narrowing of
the streets, No Parking signage will be added to one side of each of the streets.
No public testimony was taken at the public hearing. The design in this project
area is fairly straight forward with no added direction from the City Council at previ-
ous meetings.
Franklin Trail
The design of Franklin Trail incorporates narrowing the road to have 11’ drive
lanes and 8.33’ parking lanes. This is consistent with the portion of Franklin Trail
that was reconstructed in 2017 between TH13 and CR21. The reduction in road
width will provide traffic calming in this area and will allow for the addition of side-
walk to the west side for Franklin Trail. Also, incorporated in the design is re-rout-
ing the lift station #3 forcemain north of CSAH 44. The design in this project area
is fairly straight forward with no added direction from the City Council at previous
meetings.
Conclusion
The project plans are ready for bidding. Staff recommends that the City Council
accept the plans and authorize advertisement for bids.
ISSUES: After meeting with WSB to discuss coordination of plans and specifications, it was
decided to have two separate plan sets rather than trying to incorporate two plan
sets into one. This project will still be bid as one project in order to attract a larger
contractor and to provide economies of scale.
FINANCIAL
IMPACT:
Funding tables will be updated based on final bid amounts for presentation to the
City Council at the second meeting in April.
The Woodside/Huron Area Improvement Project is proposed to be financed by
Special Assessments, tax levy, Sewer Fund, Water Fund, and Water Quality Fund.
The funding estimate amounts are shown below:
WOODSIDE/HURON NEIGHBORHOOD
STREET IMPROVEMENT PROJECT -
FUNDING
Tax Levy $945,660
Assessment (40%) $500,940
Utility Fund - Sewer $639,900
Utility Fund - Water $611,600
Water Quality Fund $54,200
Assessment (Per Unit) – $8,280
3
Total $2,752,300
The Capital Improvement Plan estimate for this project was $3,151,691.
The Franklin Trail Area Improvement Project is proposed to be financed by Special
Assessments, tax levy, Sewer Fund, Water Fund, and Water Quality Fund. The
funding of each option and the corresponding estimated amounts are shown be-
low:
FRANKLIN TRAIL AREA IMPROVEMENT
PROJECT - FUNDING
Tax Levy $822,117
Assessment (40%) $357,483
Utility Fund - Sewer $437,700
Utility Fund - Water $294,300
Assessable Acreage 13.95 Acres
Assessment (Per Acre) –
Reconstruction $25,626.00
Total $1,911,600
The Capital Improvement Plan estimate for this project was $2,319,317.
The staff will provide an estimated tax levy impact as part of the April 2, 2018 work
session.
ALTERNATIVES: 1. Motion and second to Approve a Resolution Accepting Plans and Specifica-
tions and Authorizing Advertisement for Bids for the 2018 Project, City Project
#TRN18-000001.
2. Deny this item for a specific reason and provide staff with direction.
3. Table this item until some date in the future.
RECOMMENDED
MOTION:
A motion and a second for approval of Alternative #1.
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 18-___
A RESOLUTION APPROVING THE PLANS AND SPECIFICATIONS AND AUTHORIZING
THE ADVERTISEMENT FOR BIDS FOR THE 2018 IMPROVEMENT PROJECT (CITY
PROJECT TRN18-000001)
Motion By: Second By:
WHEREAS, Pursuant to Resolutions 17-208 and 17-211, adopted on December 11, 2017, the
Assistant City Engineer has prepared plans and specifications for the 2018
Improvement Project (TRN18-000001).
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The plans and specifications, a copy of which is attached hereto and incorporated by
reference herein, are hereby approved.
3. The City Manager shall prepare and cause to be inserted in the official newspaper of the City
and on QuestCDN an advertisement for bids for the making of the improvement pursuant to
the attached plans and specifications. The advertisement shall be published not less than 21
days prior to the bid opening, shall specify the work to be done, and shall state that the bids
will be received by the City Manager at which time the bids will be publicly opened at City Hall
at 4646 Dakota Street SE by the City Engineer. No bids will be considered unless sealed and
filed with the City Manager and accompanied by a cash deposit, cashier’s check, bid bond, or
certified check payable to the City of Prior Lake in the amount of five (5) percent of the amount
of such bid.
4. The City reserves the right to reject any and all bids for any reason as determined solely by the City
Council.
Passed and adopted by the Prior Lake City Council this 19th day of March 2018.
VOTE Briggs McGuire Thompson Braid Burkart
Aye ☐ ☐ ☐ ☐ ☐
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☐ ☐ ☐
______________________________
Frank Boyles, City Manager