HomeMy WebLinkAbout8A Reconstruction Accept Bids Presentation2018 Street Reconstruction Project
April 16, 2018
Project Area
Project Area
Project Schedule
ACTIVITY DATE
Held First Informational Meeting June, 2017
Accept Feasibility Report / Call for Public Hearing November 20, 2017
Second Informational Meeting December 6, 2017
Conduct Public Hearing/Order Project December 11, 2017
Approve Plans and Specifications / Order Advertisement for Bids March 19, 2018
Neighborhood Open House April 4, 2018
Open Bids April 4, 2018
Accept Bids/Award Contract April 16, 2018
Begin Construction May 2018
Complete Base Course of Bituminous Pavement September 2018
Authorize Amount to be Assessed/Schedule Assessment Hearing September 2018
Conduct Assessment Hearing/Adopt Assessment Roll October 2018
Bids Received
COMPANY BID AMOUNT
HESELTON CONSTRUCTION, LLC.$3,734,561.53
S.M. HENTGES & SONS, INC.$3,895,217.40
LATOUR CONSTRUCTION $3,958,002.30
NORTHWEST ASPHALT, INC.$3,967,701.69
GEISLINGER AND SONS, INC.$4,171,654.45
RYAN CONTRACTING COMPANY $4,253,612.55
Estimated Project Costs
Project Funding –Woodside/Huron Neighborhood
ITEM PROJECT TOTAL
Tax Levy $899,358
Assessments (40% Street & Storm Sewer)$585,369
Sewer Fund $467,176
Water Fund $556,461
Water Quality Fund $347,831
Total $2,856,195
*Funding amounts listed above include indirect costs.
Estimated Project Costs
Project Funding –Franklin Trail
ITEM PROJECT TOTAL
Tax Levy $861,459
Assessments (40% Street & Storm Sewer)$399,036
Sewer Fund $378,748
Water Fund $220,439
Total $1,859,682
*Funding amounts listed above include indirect costs.
Questions?