CITY COUNCIL AGENDA REPORT
MEETING DATE: MAY 7, 2018
AGENDA #: 8A
PREPARED BY: JASON WEDEL, PUBLIC WORKS DIRECTOR/CITY ENGINEER
PRESENTED BY: JASON WEDEL
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION AUTHORIZING STAFF TO
COMPLETE CONSTRUCTION PLANS FOR THE BOUDIN STREET/TH13
SIGNAL IMPROVEMENTS AND OBTAIN A QUOTE FROM SCOTT COUNTY
TO INCLUDE THE CONSTRUCTION WITH THE CSAH42 IMPROVEMENTS
DISCUSSION: Introduction
With the upcoming closure of Commerce Avenue at CSAH 42 it is anticipated that
the volume of traffic utilizing the Boudin Street/TH13 intersection will increase. As
such, it is important to modify the existing signal system at that location to provide
a dedicated left turn arrow. The dedicated left turn arrow will facilitate more
vehicles making that turning movement per signal cycle. This will be important for
mitigating the additional traffic flow associated with the revised Commerce Avenue
configuration.
City staff is moving forward with construction plans to modify the Boudin
Street/TH13 signal system which adds a dedicated left turn arrow. The City
Council is being asked to consider approval of the proposed project and
expenditure of City funds to complete the construction work.
History
The current configuration of the intersection of Boudin Street and TH 13 includes a
left, thru, and right turn lane. Despite having a dedicated left turn lane, there is not
a dedicated left turn arrow as part of the signal system. Vehicles wishing to turn
left have a permissive green light which requires them to wait for openings in the
on-coming traffic to make a left turn movement. The left turn lane is approximately
100-feet in length which only provides enough storage for five vehicles. During
a.m. and p.m. peak traffic, it is an issue getting all the left turning vehicles through
the intersection during a single cycle of the signal.
Included as part of the current CSAH 42/TH13 reconstruction project is the closure
of the Commerce Avenue connection at CSAH 42. A new cul-de-sac will be
constructed in its place. Traffic accessing Prior Lake businesses located in the
southwest corner of this intersection will have an increased reliance on the
intersection of Boudin/TH13. It is therefore important to make modifications to the
existing signal system to improve the function of the intersection to the extent
practicable.
Current Circumstances
The proposed Commerce Avenue closure was the primary motivation for
evaluating what improvements could be made at the Boudin Street/TH13
intersection. However, within the last several weeks the County has informed the
City that the construction staging plan has been modified to include two full
closures of CSAH 42 to ensure that most of the construction work is completed in
2018. The closures will be between TH 13 and Quebec Avenue as well as
between Rutgers Avenue and TH13. These closures will increase the volume of
traffic using the Boudin Street/TH13 intersection, increasing the need to make
improvements to the signal system as quickly as possible.
ISSUES: The burden to make the improvements to the existing signal system has fallen
completely on the City of Prior Lake. This is largely due to the limited queuing
area on the Prior Lake side of the intersection. The City did reach out to MnDOT,
Scott County and the City of Savage to see if any of these government entities
would be willing to participate in the proposed improvements, but none of them
has offered to help.
MnDOT owns the north and south legs of the intersection and as such they have
stated that they do not have any issues with the functionality of the signal’s current
configuration for traffic flow on TH13 and therefore would not be interested in
participating. However, they did state that they would not oppose the addition of a
left turn arrow for Boudin Street. The City of Savage owns the South Park Drive
leg of the intersection. Similar to MnDOT, the City stated they do not have any
issues with the functionality of the signal’s current configuration and they also have
multiple alternatives for accessing their businesses and therefore are not
interested in participating in the project.
Scott County stated that the Boudin Street/TH13 signal is not within their
jurisdiction, so they are not willing to participate with the project. However, the
County did offer to utilize their contract for the CSAH 42 project and add the signal
modifications at Boudin Street as a change order to their project. The CSAH 42
project includes the construction of several signal systems, so their contract
includes many of the necessary bid items for this signal work. This will save the
City time and money by avoiding having to complete a standalone construction bid
package and obtaining bids as a separate project.
FINANCIAL
IMPACT:
The estimated cost to complete the signal modifications is $60,000. This includes
construction costs of $48,000 and soft costs (legal, engineering, and
administration) of $12,000. The proposed funding sources are to either use City
State Aid Funds or to include the cost in our 2018 bond issuance and pay for it
through the general tax levy.
If the City Council authorizes staff to move forward with these improvements, the
next step would be for the City to provide construction plans for the proposed
improvements to Scott County. The County will then use those plans to obtain a
quote from their CSAH 42 contractor for the work. The quote will then be brought
back to the City Council for final authorization to proceed. The decision on how to
fund the improvements would need to be made at that time.
ALTERNATIVES: 1. Motion and second to approve a Resolution authorizing City Staff to complete
the construction plans to add a dedicated left turn arrow to the Boudin
Street/TH13 signal and obtain a quote from Scott County to include the
construction of the signal improvements with the CSAH42 project.
2. Deny this item for a specific reason and provide staff with direction.
3. Table this item until some date in the future.
RECOMMENDED
MOTION:
Alternative #1
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 18-___
A RESOLUTION AUTHORIZING STAFF TO COMPLETE CONSTRUCTION PLANS FOR THE
BOUDIN STREET/TH13 SIGNAL IMPROVEMENTS AND OBTAIN A QUOTE FROM SCOTT
COUNTY TO INCLUDE THE CONSTRUCTION WITH THE CSAH 42 IMPROVEMENTS
Motion By: Second By:
WHEREAS, The City of Prior Lake has identified the signal system at the intersection of Boudin
Street/TH13 to be included in a project to add a dedicated left turn arrow; and
WHEREAS, the cost to complete this project is proposed to be funded entirely by the City of
Prior Lake; and
WHEREAS, Scott County has agreed to include the proposed improvements as a change order
to their existing CSAH 42 project and invoice the City the cost of the improvements.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. City Staff are hereby authorized to complete the construction plans for the signal
improvements and obtain a quote from Scott County to include the construction of the signal
improvements with the CSAH 42 project.
3. The construction cost of the signal improvements is anticipated to be no more than $60,000
and the staff is directed to return to the city council to consider a contract for the completion
of this work.
Passed and adopted by the Prior Lake City Council this 7th day of May 2018