HomeMy WebLinkAbout9D - Deerfield Ind. Park
16200 Eagle Creek Avenue S.E.
Prior Lake, MN 55372-1714
MEETING DATE:
AGENDA #:
PREPARED BY:
AGENDA ITEM:
DISCUSSION:
CITY COUNCIL AGENDA REPORT
SEPTEMBER 19, 2005
9D
STEVE ALBRECHT, DIRECTOR OF PUBLIC WORKS
CONSIDER APPROVAL OF A RESOLUTION CONSIDERING A REQUEST
TO AMEND THE DEERFIELD INDUSTRIAL PARK DEVELOPMENT
CONTRACT, CITY PROJECT # 03-40
Introduction
As part of their development contract, Eagle Creek Development LLC was to
extend Adelmann Street from existing terminus at Cottonwood Lane to the
property line of Deerfield Industrial Park. Eagle Creek Development LLC has
requested an amendment to the development contract for Deerfield Industrial
Park. The developer incurred additional costs during construction of
Adelmann Street beyond the amounts the City already paid.
History
On August 16, 2004 the City Council approved the development contract and
final plat for Deerfield Industrial Park. The development contract included
reimbursement of $153,406.10 to the developer for construction of Adelmann
Street to the developer's property. As part of the Waterfront Passage
development Adelmann Street should have been constructed to the Deerfield
Industrial Park property. The Developer's Engineer provided costs estimates
for the construction which were included as exhibit "E" to the contract.
Current Circumstances
The developer has requested reimbursement for additional costs incurred
during construction of Adelmann Street for the following items:
1 ) Storm Sewer: The developer's engineer did not include salvage and
replacement of the existing 24-inch storm sewer in Adelmann Street in
the estimate. This work was required for connection to the existing
utilities. This amount for this additional storm sewer works was
$2,156.80.
2) Trench Rock: Even though the utility work was within 50 feet of an
existing storm water pond the developer's engineer did not include
additional trench rock or stabilizing aggregate in the bid. During
construction wet conditions were encountered and additional materials
were required. The amount for these additional materials is $2,390.06.
3) Road Construction: As part of the project review City Staff requested a
pavement design from the developer several times. After the
development contract had been approved the design was submitted
and additional aggregate base was required for the road to meet
minimum design requirements. The total for the additional street
subgrade construction costs was $4,464.00.
4) Off-site Muck Disposal: The City reimbursed the developer for
common and pond excavation associated with the construction of
Adelmann Street. The developer feels that their estimated cost did not
include the cost of disposal of this material. The additional cost for the
off-site muck disposal is $8,100.00.
C: ',n""<n,"',v"",,:,"i"J'n-4n ",,,,,.,,,,'(1' f,' \ ,co,' "'" ,\AIU/U1 rituofpriorblro.com
,.J. ,Lit., '~":""/~'::;' /v: :"".~ j"d",,,. :.V as,.,: ~h.J..~ndus~, wI .D",,\} \.1"sfh.raC! !\gnti<<:3"".... ,71....:7V.~~
Phone 952.447.4230 I Fax 952.447.4245
ISSUES:
FINANCIAL
IMPACT:
ALTERNATIVES:
The developer is requesting an additional $17,110.86 from the City. City Staff
is unaware of any previous reimbursements made to developers for oversizing
or construction of City improvements, due to incorrect estimates provided by
the developer. We have reimbursed for changes made during construction by
the City. The developer should have received written approval from the City
prior incurring additional costs if they planned on requesting reimbursement.
Amending the contract could set a precedent regarding the City's liability for
costs. The following issues should be carefully considered:
1) Other developers who have previously incurred additional costs related
to over-sizing may seek additional reimbursement.
2) The developers often do not receive competitive bids for these items
and thus the City pays more than we would if the costs were bid
competitively. The City reimburses at average project costs based on
City projects.
3) The City does not track oversizing quantities on private developments.
The Developer's Engineer tracks these and we review their quantities if
we have questions. Our inspectors do verify rough field quantities to
ensure the City is getting what we have paid for.
As part of the new development contract adopted by the City Council in June
of 2005 the City has added the following language: "No additiona/oversizing
compensation relating to this Development Contract shall be made unless
approved in writing by the City Engineer and approved by the City Council. /t
is the Deve/oper's responsibility to provide accurate estimates in accordance
with the approved construction plans. "
If the Council wishes to consider additional reimbursement to the developer
staff recommends that only storm sewer, trench rock and street construction
be reimbursed. Had the developer provided accurate estimates for these
items they would have been reimbursed as part of the original contract. The
reimbursement amount for these items is $9,010.86. City staff does not
recommend that additional reimbursement for off-site muck disposal be made.
The City paid for this item as part of the original contract and is not responsible
for where or how the developer disposes of the material.
The City Council should be aware that City Staff is currently considering
drawing on the letter of credit for this development. The required
improvements to Industrial Lane near Paws and Pals have not been completed
at this time as required by the contract. The developer has committed in
writing to the City that the improvements will be completed this fall, starting no
later than October 15, 2005. City Staff will keep the Council apprised of this
situation.
Any reimbursement will be paid for from the Street Oversize, Trunk Sewer and
Water funds. The reimbursement costs are currently available in these funds.
However, other developers may contend that this reimbursement sets a
precedent requiring the City to make similar payments on other developments
that have previously incurred additional costs.
The alternatives are as follows:
1. Approve a Resolution approving the Amendment of the Deerfield Industrial
Contract Agcr;ds 912C5doc
RECOMMENDED
MOTION:
Park Development Contract authorizing reimbursement of $9,010.86 to
Eagle Creek Development LLC.
2. Deny this agenda item, affirming that the Developer did not obtain written
City approval f or additional costs a nd that t he errors were based on the
Developer's construction estimate.
3. Table this item for a specific reason.
Staff recommends alternative #2.
Boyles, City Manager
Contract Agcrida 91 2C5doo
16200 Eagle Creek Avenue S.E.
Prior Lake, MN 55372-1714
RESOLUTION 05-XX
RESOLUTION AMENDING THE DEVELOPMENT CONTRACT FOR
DEERFIELD INDUSTRIAL PARK (CITY PROJECT # 03-40)
MOTION BY:
SECOND BY:
WHEREAS,
The City Council approved the Development Contract for Deerfield
Industrial Park on August 16, 2005; and
WHEREAS,
The Developer has requested and amendment to that contract for the
costs associated with construction of Adelmann Street from Cottonwood
Lane to the Deerfield Industrial Park property; and
WHEREAS,
The additional costs incurred for the City's portion are $9,010.86.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA,
that:
1. The recitals set forth above are incorporated herein.
2. The City Council approves reimbursement of $9,010.86 to Deerfield Industrial Park.
3. The reimbursement shall be apportioned as follows: $2,390.06 from the Trunk Sewer Fund
and $6,620.80 from the Street Oversize Fund.
Passed this 19th day of September 2005.
Hauaen Hauaen
Flemina Flemina
LeMair LeMair
Petersen Petersen
Zieska Zieska
YES
NO
{ Seal }
Frank Boyles, City Manager
{" \r), '''''c'''n'''r,''^'N'';^<jO ,.",'.A''''ldr''dl sl^I""I\D'~v (."I'tUJUJI.U"'citq()f....~l"'lrn.com
~:J, ,t t'\;":::h.~: .;,:, :,:j,L v\,..,.,/~f ._u.....{;:.' Jlc.~" ~ L., g \1. >,;.:, ),,~ !<,J"acr R8~r1\73'~:Jr~.tn.~
Phone 952.447.4230 / Fax 952.447.4245