HomeMy WebLinkAbout8A TH13 - Duluth Reject Bids Report
4646 Dakota Street SE
Prior Lake, MN 55372
CITY COUNCIL AGENDA REPORT
MEETING DATE: AUGUST 20, 2018
AGENDA #: 8A
PREPARED BY: JASON WEDEL, PUBLIC WORKS DIRECTOR/CITY ENGINEER
PRESENTED BY: JASON WEDEL
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION REJECTING BIDS AND AU-
THORIZING THE PUBLIC WORKS DIRECTOR TO RE-ADVERTISE FOR BIDS
FOR THE 2019 DULUTH AVENUE INTERSECTION IMPROVEMENT PROJECT
(CITY PROJECT #TRN15-000003)
DISCUSSION: Introduction
The purpose of this agenda item is to ask the City Council to reject bids and au-
thorize the Public Works Director to re-advertise for bids in early 2019 for spring
construction of the Duluth Avenue intersection improvements.
History
A feasibility report was originally prepared for the Duluth Avenue Intersection Im-
provement project in January 2015. The feasibility report was accepted and the
project was ordered by the City Council on January 26, 2015. However, due to
projected tax levy impacts, the project construction was delayed.
Due to additional State funding becoming available, the feasibility report was up-
dated in 2018. The updated report included assessments to adjacent properties
that will benefit from the proposed improvements as part of the overall financing of
the project. The revised feasibility report was approved by the City Council on
February 5, 2018 and the public hearing was held on March 5, 2018. At the con-
clusion of the public hearing the City Council approved a resolution ordering the
updated project and the preparation of plans and specifications.
The Duluth Avenue Intersection Improvement Project includes widening the inter-
section to include dedicated left, thru, and right turn lanes on Duluth Avenue in
both directions at the intersection with TH13. It also includes the addition of a right
turn lane into the Holiday Station Store’s northerly entrance, the construction of a
median on Duluth Avenue to restrict the access to the entrance for the Village
Lake Mall to right-in/right-out near the intersection, the construction of a mini
roundabout at the intersection of Duluth and Village Lake Drive, as well as modifi-
cations to several of the southerly entrances to the Village Lake Mall property and
the realignment of the Toronto/Village Lake Drive intersection. The final plans
were approved by the City Council on July 16, 2018 and authorization for advertis-
ing for bids was granted.
Current Circumstances
The City received a total of two (2) bids on August 2018. The bids have been
checked and tabulated. Ryan Contracting Company submitted the low bid in the
amount of $2,406,017.00. The lowest bid was well above the engineer’s estimate
of $1,672,097.60. The bid summary is provided as follows:
2
COMPANY BID AMOUNT
RYAN CONTRACTING COMPANY $2,406,017.00
EUREKA CONSTRUCTION, INC. $2,536,384.33
ENGINEER’S ESTIMATE $1,672,097.60
Conclusion
The low bid is $733,919.40 above the Engineer’s Estimate. Staff and WSB recom-
mends rejection of these bids. There was little interest in this project due to the
amount of work most contractors already have for 2018 and they simply do not
have the capacity to take on additional projects. The evidence for this is that the
City only received two bids for a project of this size and the lowest bid is 44% over
the Engineer’s Estimate. We also spoke with several other contractors who did
not bid and they stated they already have more than enough work for 2018.
ISSUES: By delaying the project and rebidding in early 2019, no work will be done this fall.
The original plan was to get this project completed in the fall of 2018 in advance of
the TH13 project and subsequent closure next year. However, that will no longer
be the case.
Staff will work diligently with both MnDOT and Scott County staff to develop a con-
struction schedule that will reduce the impact of this schedule change with the lo-
cal businesses in the Village Lake area. The proposed construction staging for
TH13 next year involves starting at the southern limits and working north in short
segments. The segment of TH13 at Duluth is not scheduled for construction until
late June or early July. The intent will be to start the construction of Duluth Ave-
nue in mid-April, weather permitting, and be substantially complete with the con-
struction prior to that segment of TH13 being closed.
FINANCIAL
IMPACT:
The City is receiving $710,000 in Cooperative Agreement funds from MnDOT for
this project. City staff have confirmed with MnDOT officials that re-bidding this
project in early 2019 for construction next year will not impact those funds. The
proposed funding for the project will therefore remain the same as shown below:
Special Assessments $163,025
Tax Levy $906,975
MSAS (State Aid) $400,000
MnDOT $710,000
Total $2,180,000
As part of the right of way acquisition for this project there were several temporary
easements that were tied to specific dates for when construction would occur.
Those temporary easements will need to be modified if the project is delayed. Any
cost, if any, with renegotiating those temporary easements will be brought back to
the City Council.
3
There is a potential benefit to rebidding this project next year. If the timing of the
bids can be coordinated with the TH13 reclaim project as well as the CR21/TH13
intersection project there could be an incentive to a contractor to try to get all three
projects and there by aggressively bid the projects since they are located in the
same proximity.
ALTERNATIVES: 1. Approve a Resolution rejecting bids and authorizing the Public Works Director
to re-advertise for bids in early 2019 for the Duluth Intersection Improvement
Project (City Project #TRN15-000003).
2. Deny this item for a specific reason and provide staff with direction.
3. Table this item until some date in the future.
RECOMMENDED
MOTION:
A motion and a second for approval of Alternative #1.
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 18-___
A RESOLUTION REJECTING BIDS AND AUTHORIZING PUBLIC WORKS DIRECTION TO
RE-ADVERTISE FOR BIDS IN 2019 FOR THE DULUTH AVENUE INTERSECTION
IMPROVEMENT PROJECT (TRN15-000003)
Motion By: Second By:
WHEREAS, Pursuant to an advertisement for bids for the Duluth Intersection Improvement
Project (City Project #TRN15-000003) which includes sanitary sewer, water
main, storm sewer, aggregate base, concrete curb and gutter, bituminous
pavement, turf restoration and appurtenant work; and
WHEREAS, Bids were received, opened, and tabulated according to law; and
WHEREAS, The following bids were received complying with the advertisement:
COMPANY BID AMOUNT
RYAN CONTRACTING COMPANY $2,406,017.00
EUREKA CONSTRUCTION, INC. $2,536,384.33
and;
WHEREAS,
WHEREAS,
The engineer’s estimate was $1,672,097.60; and
The low bid is 44% over the engineer’s estimate.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and City Manager are hereby authorized to reject all bids and authorize the
Public Works Director to re-advertise for bids for the Duluth Avenue Intersection
Improvement Project (Project #TRN15-000003).
3. The City Manager is hereby authorized and directed to return to all bidders the deposits that
accompanied their respective bids.
PASSED AND ADOPTED THIS 20TH DAY OF AUGUST 2018.
VOTE Briggs McGuire Thompson Braid Burkart
Aye ☐ ☐ ☐ ☐ ☐
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☐ ☐ ☐
______________________________
Frank Boyles, City Manager