HomeMy WebLinkAbout10E - Police/City Hall Project
16200 Eagle Creek Avenue S.E.
Prior Lake, MN 55372-1714
CITY COUNCIL AGENDA REPORT
MEETING DATE:
AGENDA #:
PREPARED BY:
AGENDA ITEM:
CONSIDER APPROVAL OF CHANGE ORDER #1 TO THE POLICE
STATION I CITY HALL CONSTRUCTION PROJECT.
DISCUSSION:
I ntrod uction
The purpose of this agenda item is to receive authorization for change order
#1 for the police station / city hall construction project.
Historv
The general conditions of the contract for the police station / city hall were
worded in a fashion to encourage the contractor receiving the bid to
investigate the extent to which elements of the project were exempt from sales
tax. The contractor, Shaw Lundquist, interpreted the general conditions to
mean that the entire project is exempt from sales tax and so he excluded sales
tax from his bid. Only certain projects like libraries, jails and certain
educational facilities are granted such exemptions under State Statute. Police
stations and city halls are exempted only in regard to certain equipment such
as energy-saving windows, doors, and heating and cooling equipment.
Current Circumstances
The general contractor made a claim against the City in the initial amount of
$198,978 to compensate them for the sales and use tax they failed to include
on certain items called out in the general conditions. As outlined in the
attached letter from Bill Wolters, the City's owner's representative, that
amount was negotiated to $189,993, and then to $171,257. Last week, Mr.
Wolters, John MacNamara of Wold Architects, Suesan Lea Pace and I met
with Tom Meyers of Shaw Lundquist and his attorney. We negotiated a final
amount of $125,000 for this claim.
Conclusion
The City Council should determine if it will approve change order #1.
ISSUES:
The staff has considered the prospect of denying the claim. It is our belief that
the likelihood of success is in question.
FINANCIAL
IMPACT:
The total project budget is $13.5 million. This action would increase the
contract with Shaw Lundquist from $11,157,800 by $125,000 to $11,282,800
(see change order document G701). The total project amount of $13.5 million
would remain the same, but the contingency account would be reduced from
$300,000 to $175,000 (see Constructive Ideas spreadsheet). The Council will
recall that the alternates are funded from sources outside the $13.5 million
www.cityofpriorlake.com
~,,;r'("~i ihlt....i~ ~t:,f""Nr?()T<.....~,..~n{1i:;:\1/'j^10nr2L{'t'1i-"" /;,...~ r, ~ { ,(';;-'<" {v(,,...."'..' '", _<+'_' <'\.r~q (:'/'\(">
1 \,<""m,,,~ V~>':" ,I l.)\ff~",h/" k 'nh)Ptlt5n~'9~2:4'4~:tt'230dr>rFax'~52:l:f4'T4245
ALTERNATIVES:
RECOMMENDED
MOTION:
budget. In addition, the City instructed Mr. Wolters to work closely with the
architect to assure the buildings are engineered and constructed in the most
cost-effective manner while not compromising the aesthetic or functional
integrity of the buildings.
1. Approve change order #1 as recommended.
2. Direct the staff to prepare additional information.
Alternative #1.
I\COU NC: LV\C; N FWfS\2005\1
Constructive Ideas, Inc.
901 Jefferson Avenue, Suite 300
St. Paul, Minnesota 55102
(651) 225-4740. Fax 225-4741
Project: Prior lake Police and City Hall
Prior lake, Minnesota
Architect: Wold Architects and Engineers
St. Paul, Minnesota
Adjustments
Item Description Original Budget Since Bid Day Current Budget Total
1 Fees
Cost of Project Fmancmg $256,639 $ 256,639
Arch/Engineering - Base Building $ 660,000 $ 660,000
Architectural Reimbursables $ 35,000 $ 35,000
Arch. Interior Design - In above $ -
Owner's Representative $ 126,000 $ 126,000
Owner's Representative - Reimburasbles $ 4,200 $ 4,200
Survey - Allow $ 10,000 $ 10,000
Soil Borings - Allow $ 12,500 $ 12,500
Wetland Mitigation - not needed $ -
Owner's Special Testing Durino Construction $ 50,000 $ (10,000) $ 40,000
Subtotal Fees and Reimbursables $ 1,144,339
2 Furniture, Fixtures and Equipment
FF&E from Mav, 2005 budget $390,000 ($90,000) $ 300,000
Subtotal Furniture, Fixtures and Equiprnent $ 300,000
3 Special Systems
Voice and Data Wiring $ 20,000 $ 20,000
Audio Visual Equipment $ 75,000 $ 75,000
Phone Equipment $ 50,000 $ 50,000
Paging System $ 25,000 $ 25,000
Misc. Equipment $ 50,000 $ 50,000
Security ( Cameras, etc.) $ 50,000 $ (50,000) $ -
Move Allowance $ 25,000 $ 25,000
Subtotal Special Systems $ 245,000
4 Other Owner Costs
Land Cost $ 730,000 $ 730,000
Sewer or Utility Relocation $ 50,000 $ (50,000) $ -
Allowance for Dump Site Clean-up $ 75,000 $ (50,000) $ 25,000
Builder's Risk - by Contractor $ -
Permits - City Permit Fee waived $ -
Legal - Allowance $ 25,000 $ (25,000) $ -
Allowance for Asbestos - Survey and Abatement $ 50,000 $ (30,000) $ 20,000
SACIWAC - Allowance $ 40,000 $ (40,000) $ -
Subtotal - Other Owner Costs $ 775,000
5 Project Contingency - Fixed $400,000 $ (275,000) $ 125,000
Subtotal - Contingency $ 125,000
Subtotal - Items 1 thru 5 $2,952,700 ($363,361 ) $2,589,339 $2,589,339
Total Authorized by City Council - May 2, 2005 $13,250,000 $13,250,000 $13,250,000
Amount Available for Construction - September 13, 2005 $10,297,300 $10,660,661 $10,660,661
Apparent Low Bidder. 2nd Bid. Shaw-Lundquist $10,579,700
Xcel Energy Rebate -31,500.00
File: Budget sheet for City Council- 12-19-2005
Page 1
12/13/2005
Constructive Ideas
Planning, Preconstruction & Owner Representative Services · Project Cost Analysis
December 12, 2005
Mr. Frank Boyles, City Manager
City of Prior Lake
16200 Eagle Creek Avenue, S.E.
Prior Lake, Minnesota 55372
Re: Sales Tax Issue
Dear Frank:
This letter is to summarize for you the sales tax issue on the new Prior Lake Police and
City Hall project.
As you know, there was a claim made by Shaw Lundquist for additional sales tax on
certain materials for the project which, according to the General Conditions, were
described as being exempt from Minnesota sales tax. The claim was originally submitted
on October 18, 2005 in the amount of One Hundred Ninety Eight Thousand Nine
Hundred Seventy-Eight Dollars ($198,978.00). This claim precipitated several actions on
the part of Wold Architects and Engineers, myself, and Suesan Pace, your city attorney.
First the claim was reviewed and rejected for lacking documentation and for being
excessive in that the contractor was asking for sales tax on electrical materials which
were not referenced as being tax exempt, and they were requesting an overhead and profit
allowance of 10% of the total amount of the claim. As a result of this initial rejection, the
contractor lowered the requested overhead and profit from 10% to 5% of the claim. This
lowered the claim total to One Hundred Eighty-Nine Thousand, Nine Hundred Ninety-
Three Dollars ($189,993.00). This revised claim was received on October 31,2005. On
November 4,2005 there was a letter from Wold Architects to Shaw Lundquist which
again requested additional information to support their claim and pointed out the error in
the electrical calculation. This letter caused Shaw Lundquist to review their claim, and
on November 10, 2005 they resubmitted with a revised electrical value. This lowered the
claim to an amount of One Hundred Seventy-One Thousand, Two Hundred Fifty-Seven
Dollars ($171,257.00).
While this correspondence was taking place, research was being done regarding the tax
issue. However, it was determined that "There is no explicit exemption under Minnesota
law for the City of Prior Lake Project." The project did not meet the criteria in that it was
901 Jefferson Avenue, Suite 300 · St. Paul, MN 55102. (651) 225-4740. Fax (651) 225-4741
www.constructiveideasinc.com
Mr. Frank Boyles
December 12, 2005
Page 2
contracted for on a "lump sum" basis and not on a separate "material and labor" basis.
Also, the legislation under which the General Conditions were apparently prepared was
specific to libraries and possibly county jail facilities but would not cover city police
facilities or city hall facilities. On November 2, 2005 a memo was issued from the city
attorney to this effect.
Contemporaneously with this research, we had requested additional documentation:
specifically, access to Shaw Lundquist's bid documents in order to verify if, in fact, Shaw
Lundquist had deducted sales tax as a result of their interpretation of the General
Conditions. Our immediate access to these documents was delayed since Shaw
Lundquist claimed our request was "unreasonable and this has nothing to do with the
issue at hand." After some negotiations between Shaw Lundquist's attorney and the Prior
Lake city attorney, access to the Shaw Lundquist document was provided to me, and on
Monday, November 21, 2005 I reviewed their documents.
As a result of my review, I noted that a bid deduction of One Hundred Twenty Five
Thousand Dollars ($125,000.00) apparently had been taken prior to the bid being
submitted. The note on the sheet titled this reduction "Bid adj tx." My findings were put
in my letter to you of November 23, 2005 along with several questions regarding this
apparent deduction and questions on whether or not some of the materials in question
could still be considered tax exempt under a general sales-tax exemption for energy
efficient equipment. Finally, a meeting was arranged at the offices of the Halleland law
firm with Tom Meyers of Shaw Lundquist, his attorney, yourself, Suesan Pace, John
McNamara of Wold Architects and Engineers, and myself to see ifthis claim could be
settled on an equitable basis.
The result of this meeting was to reach a resolution of this claim for an amount of One
Hundred Twenty-Five Thousand Dollars ($125,000.00) with no allowance for overhead
and profit. This amount is Seventy-Three Thousand Nine Hundred Seventy-Eight
Dollars ($73,978.00) less than the original claim. This is the amount that we are
requesting the City Council approve to resolve this issue.
This amount would be charged against the project contingency which had been identified
as Two Hundred Fifty Thousand Dollars ($250,000.00). This would leave the balance of
$125,000.00 as our contingency going forward. This is a very small contingency for this
early in the project. In order to protect this contingency, the architects and engineers,
City personnel and myself will be continually reviewing the documents to see if any
value engineering cost saving strategies can be identified. Any items noted would be
brought before the City for approval prior to their being implemented on the project.
It is regrettable that this tax issue occurred, but I feel it is in the City's best interest to
dispense with it on this settlement basis and not pursue it through litigation.
Mr. Frank Boyles
December 12, 2005
Page 3
If you need copies of my earlier correspondence to your or attachments, please give me a
call.
Sincerely,
CONSTRUCTIVE IDEAS, INC.
~I:!~
President
/oww
cc: Mr. Bill O'Rourke - City of Prior Lake
Ms. Suesan Pace - Halleland Lewis Nilan Sipkins & Johnson, P.A.
Mr. Mike Cox - Wold Architects and Engineers