HomeMy WebLinkAbout10C - 2006 Lift Station Project 16200 Eagle Creek Avenue S.E. Prior Lake, MN 55372-1714 MEETING DATE: AGENDA #: PREPARED BY: AGENDA ITEM: DISCUSSION: ISSUES: CITY COUNCIL AGENDA REPORT JANUARY 17, 2006 10C CRAIG ELDRED, STREET AND UTILITIES SUPERVISOR CONSIDER APPROVAL OF A RESOLUTION AUTHORIZING THE MAYOR AND CITY MANAGER TO EXECUTE THE STANDARD PROFESSIONAL SERVICES CONTRACT WITH ADVANCED ENGINEERING AND ENVIRONMENTAL SERVICES, INC. (AE2S) TO PROVIDE PROFESSIONAL ENGINEERING SERVICES FOR THE 2006 LIFT STATION REHABILITATION PROJECT. I ntrod uction The purpose of this agenda item is for the City Council to authorize execution of a Standard Professional Services Contract with Advanced Engineering and Environmental Services, Inc. (AEzS) to provide Professional Engineering Services for the 2006 Lift Station Rehabilitation Project. Costs for this project are from the sewer operating fund and not property taxes. History Because of the topography of the Prior Lake community, the City's sewer system relies upon 38 lift stations. In 2003, AEzS (formerly WSB) Consulting Engineers along with City staff completed an audit of all the lift stations throughout Prior Lake to ascertain the status and inventory the components of each lift station. Once completed, AEzS and staff put together a Comprehensive Management and Rehabilitation Schedule, and also instituted a Sanitary Sewer Lift Station Standard Policy. To date, 17 lift stations have been rehabilitated. Current Circumstances For the 2006 Lift Station Project, staff has identified Butternut and Forsythe lift stations for rehabilitation. Rehabilitation includes replacement of pumps, guide rails, electrical panels, and other electrical components; wet well covers and hatches. Generally, the concrete wet wells are in good condition and do not require replacement. Additionally, the Deerfield lift station is scheduled for control panel replacement of existing level controller, back up controller and appurtenant equipment. AEzS is the Engineering Consultant reviewing new development and rehabilitation of Prior Lake's future and existing lift stations. www.cityofpriorlake.com Phone 952.447.4230 / Fax 952.447.4245 AEzS submitted a proposal to prepare plans and specifications for the 2006 Lift Station Rehabilitation and perform construction engineering inspection for a cost not to exceed $33,500.00. AE2S will be using Kaeding and Associates to perform the electrical engineering work which is included in the proposal. FINANCIAL IMPACT: The funding for this project will come from the Sewer Operating Fund since it is the rehabilitation of existing sewer infrastructure. Staff estimates the total cost of engineering, equipment and actual repairs to be approximately $250,000.00, which is drawn from the sewer operating fund. Based upon the engineering inspection, equipment needing replacement is identified, and bids are solicited based upon standardized equipment. Once the Council has approved the bid, the work is completed and inspected. ALTERNATIVES: There are three alternatives for the City Council to consider: 1. Approve a resolution that authorizes the City to enter into its Standard Professional Services Contract with Advance Engineering and Environmental Services, Inc. to provide engineering services for a fee not to exceed $33,500.00. 2. Deny this item for a specific reason and provide staff with direction. 3. Table this item to a certain date in the future. RECOMMENDED MOTION: A motion and second to approve Resolution 06-XX authorizing the Mayor and City Manager to execute the Standard Professional Services Contract with Advanced Engineering and Environmental Services, Inc. to provide professional engineering services for the 2006 Lift Station Rehabilitation Project. REVIEWED BY' 1\ ~.. 'l~( ,tf I1l Steve Albrecht, Public Works Director C\!Jocumcrt" 2nd Sottinq,,\cgreonLoC8i rehebiHtation (<1) doe 16200 Eagle Creek Avenue S.E. Prior Lake, MN 55372-1714 RESOLUTION 06-xx A RESOLUTION TO AUTHORIZE THE MAYOR AND CITY MANAGER TO EXECUTE THE STANDARD PROFESSIONAL SERVICES CONTRACT WITH ADVANCE ENGINEERING AND ENVIRONMENTAL SERVICES, INC. TO PROVIDE PROFESSIONAL ENGINEERING SERVICES FOR THE 2006 LIFT STATON REHABILITATION PROJECT. Motion By: Second By: WHEREAS, City staff has identified three lift stations requiring rehabilitation this year; including Butternut, Forsythe and Deerfield lift stations; and WHEREAS, The adopted Capital Improvement Plan for 2006-2011 has identified these rehabilitation projects as a priority for the City; and WHEREAS, Advanced Engineering and Environmental Services, Inc. services, including final design, bidding, construction, and post construction are required for this project. NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA as follows: 1. The recitals set forth above are incorporated herein. 2. The Mayor and City Manager are authorized to execute the City's Standard Professional Services Contract with Advanced Engineering and Environmental Services, Inc. for the 2006 Lift Station Rehabilitation Project for a total fee not to exceed $33,500.00. 3. The funding for the contract is to be drawn from the Sanitary Sewer Operating Fund. PASSED AND ADOPTED THIS 17th DAY OF JANUARY, 2006. YES NO Hauaen Haugen Dornbush Dornbush Erickson Erickson LeMair LeMair Millar Millar Frank Boyles, City Manager C'\Documonts 2nd Scttings\cqf8en\Looai mhabhtation resoiution (3)DOC www.cityofpriorlake.com Phone 952.447.4230 / Fax 952.447.4245