HomeMy WebLinkAbout10A - C.R. 12 Project Report
MEETING DATE:
AGENDA #:
PREPARED BY:
AGENDA ITEM:
DISCUSSION:
16200 Eagle Creek Avenue S.E.
Prior Lake, MN 55372-1714
CITY COUNCIL AGENDA REPORT
APRIL 3,2006
10A
STEVE ALBRECHT, DIRECTOR OF PUBLIC WORKS
CONSIDER APPROVAL OF A REPORT ON COUNTY ROAD 12 PROJECT
Introduction
At the March 6, 2006, City Council meeting staff was directed to update the
Council on the status of the CR 12 project.
Historv
On August 16, 2004, the City Council passed a resolution formally approving
the CR 12 layout and design from TH 13 to CR 17. This project incorporated
an extensive public involvement process that included three open houses,
three target-group-area meetings and a public hearing that extended over 2
City Council meetings with several hours of testimony by the public.
Residents, namely those in 3rd phase of the project did not support the
approved design that incorporated two sidewalks along CR 12 from Sunset
Trail to the realignment segment. After the City Council completed a detailed
review of the safety and ROW implications of the two-sidewalk design, which is
90-95% complete, the design was approved by the City Council. Upon
passage of the City Council resolution, the County Board approved the project
and the County began project design late in 2004.
Originally, the project was expected to begin construction in 2006. However, in
the fall of 2004, the County revised the Transportation Implementation Plan
and the balance of the project with the exception of the realignment section
(phase 1) and CR 12/TH13 intersection (phase 2) was moved to 2010 due to
budget constraints. The County Road 12 project is being constructed in
phases based on the plans approved in 2004 by the City and County.
Construction of the realignment segment (phase 1) including Spring Lake
Regional Park is well under way. The CR12/TH13 intersection or phase 2 is
scheduled for reconstruction in 2007. Phase 3 of the project which includes
the remaining segments from Elm Avenue west to the realignment segment
and from east of Shoreline Lane to CR 17 are scheduled for 2010.
The County has expended more than $650,000 on project development and
design to date based on the approval received from the City of Prior Lake in
2004.
Current Circumstances
At the March 6, 2006, City Council meeting Jim Weninger of 2591 Spring Lake
Road, Prior Lake, requested that the City Council evaluate the status of the
project and reconvene an advisory committee to evaluate and potentially
redesign certain segments of the project, specifically from Sunset Trail to the
realignment segment. Mr. Weninger also expressed concerns related to the
www.cityofpriorlake.com
Phone 952.447.4230 / Fax 952.447.4245
wildlife crossings and overhead power.
Staff was directed by the Council to provide a status report on the project. City
Staff contacted Leslie Vermillion (County Public Works Director), Mitch
Rasmussen (County Engineer) and Chris Chromy (Project Engineer - Bolton &
Menk) to verify the project status. The following is based on those discussions
and correspondence.
Under County Staff direction, the County's consultant is 90-95% complete with
the plan design for the corridor. Additionally the County will begin the parcel
acquisition process for the balance of the project later this year based on legal
parcel documents that have been completed by the County's consultant. As
previously mentioned the County has expended more than $650,000 to date
on this project. City Staff estimates that more than $200,000 of that money
has been spent on the design from Sunset Trail to the realignment segment of
the project where the two-sidewalk issue has been raised by Mr. Weninger.
City Staff discussed redesign of the corridor with the County and has the
following comments:
1) The City of Prior Lake previously approved the project as designed
based on safety considerations given traffic counts and projections.
Nothing has suggested that the traffic counts or projections are in error
or will change. A detailed analysis of all the sidewalk alternatives was
conducted and considered prior to the decision.
2) Given that the City's position is not arbitrary but based upon analysis
and considerable discussion, the County would not consider a redesign
at this time.
3) Considerable time and money has been spent by the County based on
the design approved by the City of Prior Lake.
4) No other approvals are required at this time from the City to proceed
with the project other than the final Cooperative Agreement. The
Cooperative Agreement is a document that establishes the cost sharing
and responsibilities for construction.
In response to Mr. Weninger's other concerns staff offers the following
clarifications:
1) Considerable time and effort was spent accommodating wildlife in the
corridor. The Project Team decided that the numerous driveway
aprons, which have a 2+-inch rise versus the four-inch rise in
surmountable curb, would sufficiently accommodate turtles and other
wildlife crossings in the residential area. As for the realignment
section, safety considerations on the curves dictated that most of the
segment has barrier type curb. However, several 100 feet at the east
end of the segment near the large wetland have been proposed as
surmountable curb to accommodate wildlife.
2) Mr. Weninger stated that there were only four or so overhead services
at this time that would need to be buried. A field review by staff shows
there are more than 40 services that would need to be buried east of
the Spring Lake Regional Park. The City will be contacting residents
later this spring to discuss burial of power in the corridor as discussed
at our February 6,2006 meeting. As for the City Councils previous
decision to relocate the overhead power in the realignment segment,
this decision does not prevent future burial of that section. At this time
however it is neither practical nor does the City have the funds
available to complete the burial based on reasons discussed at the
February 6 meeting.
ISSUES:
The County does not intend to revisit the aforementioned design
considerations. The County has expended more than $650,000 on this project
in reliance on the 2004 City Council approval.
FINANCIAL
IMPACT:
When the project proceeds as currently designed, the costs detailed in the
Capital Improvement Program for CR 12 should be relatively accurate. The
County has indicated that they will not entertain redesign requests. Were they
to change their mind in the future, I would anticipate the County seeking
reimbursement for funds spent on the design beyond the normal Cooperative
Agreement apportionment and the redesign costs. Depending on the level of
redesign this could cost anywhere from $50,000 to several hundred thousand
dollars. As noted above the County has spent more than $650,000 to date on
this project of which a substantial portion has been dedicated to the segment
from Sunset Trail to the realignment segment.
ALTERNATIVES:
1. Receive and file the report.
RECOMMENDED
MOTION:
Staff recommends alternative number 1.
".,
,
,
B les, City Manager