HomeMy WebLinkAbout9B Supplemental EAW Ryan Contractinb
MEETING DATE:
AGENDA #:
PREPARED BY:
AGENDA ITEM:
DISCUSSION:
16200 Eagle Creek Avenue S.E.
Prior Lake, MN 55372-1714
CITY COUNCIL AGENDA REPORT
APRIL 3,2006
9B
JANE KANSIER, PLANNING DIRECTOR
CONSIDER APPROVAL OF A RESOLUTION PERTAINING TO THE NEED
FOR A SUPPLEMENTAL EAW FOR CONDITIONAL USE PERMIT 01-19
(RYAN MINING AND EXCAVATION)
I ntrod uction
The purpose of this agenda item is to review a resolution which would bring
the City into compliance with the Court's order as it relates to the need for an
Environmental Assessment Worksheet (EAW) for the Ryan mining and
excavation permit.
History
In 1999, the City received an application for a Conditional Use Permit from
Ryan Contracting to allow the excavation of sand and gravel on 13 acres of the
McKenna and Kinney properties located north of CSAH 42, and north and east
of McKenna Road. Just before the City Council was to consider this CUP, the
Council received a petition for an EAW for the project. The City Council
ultimately agreed to prepare an EAW. This process was completed in
December, 2000.
On February 20, 2001, the City Council made a negative declaration on the
need for an Environmental Impact Statement. On February 27,2001, the City
Council adopted Resolution 01-19, which approved a CUP subject to 37
conditions (see attachment #1). Fifteen of those conditions needed to be
satisfied before the CUP would become valid. Eight additional conditions
needed to be satisfied before Ryan could begin work. Fourteen additional
conditions needed to be satisfied by Ryan on an on-going basis. In addition,
the CUP could be valid for only one year, and was subject to renewal upon
application. The need for Ryan to seek renewal of the permit after one year
gave the Council the ability to consider the information regarding Ryan's
performance and environmental impacts of the project that would be created
during the first year of operations.
In 2001-02, the SMSC challenged the City's negative declaration on the need
for an Environmental Impact Statement, which included a request that the
Court should either prevent Ryan from mining or impose additional conditions
on its operation, beyond those already required in the CUP. In its first ruling,
the Court upheld the City's negative declaration, finding that no further
environmental review was necessary, based on the mitigative nature of the
conditions incorporated into the CUP. In 2002, following a trial, the Court
denied the SMSC's request to prevent mining operations, but imposed several
additional conditions on Ryan's operations to mitigate potential environmental
www.cityofpriorlake.com
Phonl:?952.447.4230 / Fax 952.447.4245
impacts.
A separate City Ordinance authorized the City to cancel Ryan's CUP if Ryan
failed to make substantial use of the premises pursuant to the CUP with in a
one-year period. This provision is similar to provisions in the Building Code
and in Minnesota Statutes. The City tolled the commencement of that one-
year period until the appeal period in the SMSC Litigation expired. After the
litigation and appeal period expired, the one year time period on the CUP
began to run. In January 2004, after staff concluded that Ryan had not
satisfied the preconditions to the validity of the CUP within the one year period
following the litigation, the City cancelled the CUP. Ryan disagreed with the
City's conclusions and procedures, and sued the City. Ryan also contended
that the City lacked statutory authority to impose a one-year term on the CUP
or a requirement that an applicant use a CUP within a one-year period. The
SMSC intervened in that action and aligned itself with the City. In May 2005,
cross-motions for summary judgment were argued, and soon thereafter, a
settlement dialogue began. The SMSC's counsel initially participated in those
settlement discussions, but when the potential for a settlement appeared to be
possible the SMSC dropped out.
Several hours before the City Council was scheduled to consider authorizing
the execution of the draft Settlement Agreement, the City Council received a
copy of a petition requesting the preparation of a revised environmental
assessment worksheet on June 20, 2005. The City received official
notification of its RGU status from the Environmental Quality Board on July 1,
2005. On July 18, 2005, the City Council denied the Shakopee Mdewakanton
Sioux Community's petition for a supplemental Environmental Assessment
Worksheet (Resolution 05-130).
Current Circumstances
On August 15, 2005, the SMSC initiated a lawsuit against the City contending
that the denial of its petition for a supplemental EAW was improper. On
December 21, 2005, the City presented to the Court a motion for summary
judgment in the SMSC's lawsuit, arguing that the City properly denied the
EAW petition because Minn. R. 4410.1000 subp. 5 of the Environmental
Review Rules did not require a supplemental EAW if the project did not
substantially change. The SMSC agreed with the City that the lawsuit
presented a legal question about the interpretation of the Environmental
Review Rules, but the SMSC argued that "the City was obligated to review the
impacts of the gravel mine on the surrounding land use because of the
significant changes in the area."
On January 24, 2006, the Court issued the Order denying City's motion for
summary judgment in SMSC's lawsuit, for reasons that implied the Court might
have agreed with the SMSC's interpretation of Minn. R. 4410.1000 subp. 5 of
the Environmental Review Rules. Following a request for clarification of the
Order, the Court explained that the Court agreed with the SMSC's
interpretation of Minn. R. 4410.1000 subp. 5 of the Environmental Review
Rules, that the City should consider changes in the area surrounding the
proposed gravel mine; and that it would be "a ve/y good idea" to prepare a
supplemental EAW.
ISSUES:
FINANCIAL
IMPACT:
ALTERNATIVES:
RECOMMENDED
MOTION:
Reviewed by:
Conclusion
To be consistent with the Court's order, the attached resolution directs staff to
prepare a supplemental EAW.
The cost to prepare an EAW is generally born by the developer. The staff
generally solicits proposals and then chooses a consultant to prepare the
EAW. The developer is required to escrow the cost of this preparation prior to
any work.
In this case, the staff suggests we contract with Liesch Associates, which
prepared the original EAW, to prepare the supplemental EAW. Liesch
Associates has provided staff with a preliminary estimate of $10,000-12,000 to
do this work. The actual cost may be more or less, depending on what new
information, such as traffic estimates, must be gathered.
The cost if this work would be paid by the developer. The City would have the
indirect cost of the staff time required to coordinate and review the preparation
of the EAW.
1. Adopt the attached resolution directing staff to prepare the supplemental
EAW.
2. Defer this item and provide staff with specific direction.
The staff recommends alternative #1.
Frank Boyles, City Manager
16200 Eagle Creek Avenue S.E.
Prior Lake, MN 55372-1714
RESOLUTION 06-xx
Motion By:
Second By:
WHEREAS, On July 18, 2005, the City Council denied the Shakopee Mdewakanton Sioux
Community's petition for a supplemental Environmental Assessment Worksheet
(Resolution 05-130); and
WHEREAS, On August 15, 2005, the SMSC initiated a lawsuit against the City contending that the
denial of its petition for a supplemental EAW was improper; and
WHEREAS, On December 21,2005, the City presented to the Court a motion for summary
judgment in the SMSC's lawsuit, arguing that the City properly denied the EAW petition
because Minn. R. 4410.1000 subp. 5 of the Environmental Review Rules did not
require a supplemental EAW if the project did not substantially change; and
WHEREAS, The SMSC agreed with the City that the lawsuit presented a legal question about the
interpretation of the Environmental Review Rules, but the SMSC argued that lithe City
was obligated to review the impacts of the gravel mine on the surrounding land use
because of the significant changes in the area"; and
WHEREAS, On January 24, 2006, the Court issued the Order denying City's motion for summary
judgment in SMSC's lawsuit, for reasons that implied the Court might have agreed with
the SMSC's interpretation of Minn. R. 4410.1000 subp. 5 of the Environmental Review
Rules; and
WHEREAS, Following a request for clarification of the Order, the Court explained that the Court
agreed with the SMSC's interpretation of Minn. R. 4410.1000 subp. 5 of the
Environmental Review Rules, that the City should consider changes in the area
surrounding the proposed gravel mine; and that it would be "a very good idea" to
prepare a supplemental EAW; and
WHEREAS, The City Council wishes to act consistent with the Court's guidance and interpretation,
as clarified.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The denial of the SMSC's petition for a supplemental EAW (Resolution 05-130) is hereby
rescinded.
3. The City staff is hereby directed to prepare a supplemental EAW with respect to the project subject
to CUP 01-19.
www.cityofpriorlake.com
Phone 952.447.4230 / Fax 952.447.4245
PASSED AND ADOPTED THIS 3RD DAY OF APRIL, 2006.
Hauaen HauQen
Dornbush Dornbush
Erickson Erickson
LeMair LeMair
Millar Millar
YES
NO
Frank Boyles, City Manager
C:\Documents and Settings\frank.PRIORLAKECH\Local Settings\Temporary Internet Files\OLK2A\4-03-06resolution.DOC