HomeMy WebLinkAbout5E 2019 Fish Point Road Reclamation Accept Bids Report
4646 Dakota Street SE
Prior Lake, MN 55372
CITY COUNCIL AGENDA REPORT
MEETING DATE: MARCH 18, 2019
AGENDA #: 5E
PREPARED BY: NICK MONSERUD, ASSISTANT CITY ENGINEER
PRESENTED BY: NICK MONSERUD
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION ACCEPTING BIDS AND AWARD-
ING THE CITY’S STANDARDIZED CONSTRUCTION CONTRACT FOR THE
2019 FISH POINT ROAD RECLAMATION PROJECT (TRN19-000003)
GOAL AREA AND
OBJECTIVE:
Transportation & Mobility
1. Maintain quality local street system based on a financially stable plan that
meets Overall Condition targets.
DISCUSSION: Introduction
The purpose of this agenda item is to ask the City Council to accept bids and
award a construction contract for the 2019 Fish Point Road Reclamation Project.
History
The City uses the Five Year Capital Improvement Program and its Pavement
Management program to plan its infrastructure improvements and the financing for
capital improvements. The section of Fish Point Road from County Road 21 south
to Fawn Meadows Curve is part of the plan for reclamation in 2019. At its October
15, 2018 meeting the City Council adopted Resolution 18-166 authorizing staff to
prepare a Feasibility Report for the Fish Point Road Reclamation Project as out-
lined in the CIP. The primary purpose for proceeding with the project is to upgrade
the street condition. The pavement condition is poor and requires reconstruction
in accordance with the City’s desire to maintain high overall condition index (OCI)
ratings on its roadways.
The Fish Point Road Reclamation Project is considered in the report and includes
a full depth pavement reclamation from County Road 21 south to Fawn Meadows
Curve located in Section 1, Township 114, Range 22. This segment of Fish Point
Road was built in 1994. The proposed improvements include full depth pavement
reclamation, spot curb replacement, replacement of the existing bituminous trail,
and ADA improvements at the existing curb ramps.
The M.S. Chapter 429 process applies to all projects that will be financed in whole
or part through special assessments or bond proceeds.
At its December 17, 2018 meeting the City Council adopted Resolution 18-203 ac-
cepting the Feasibility Report and ordering the public hearing for the Fish Point
Road Reclamation Project.
At its January 22, 2019 meeting the City Council conducted a public hearing and
adopted Resolution 19-010 ordering the preparation of plans and specifications for
the Fish Point Road Reclamation Project.
2
At its February 4, 2019 meeting the City Council adopted Resolution 19-025 ap-
proving the plans and specifications for the Fish Point Road Reclamation Project
and authorizing the advertisement for bids.
In addition to the Public Hearing, City staff has contacted each of the three proper-
ty owners within the project area to provide an opportunity to discuss the project in
an informal setting. Staff provided an update on the proposed improvements, pro-
ject costs, estimated assessments and answered general questions regarding the
project.
Current Circumstances
The City received a total of seven (7) bids on March 8, 2019. The bids have been
checked and tabulated. GMH Asphalt Corporation from Chaska, Minnesota sub-
mitted the low bid in the amount of $388,714.14. The lowest bid was within 5% of
the engineer’s construction estimate of $370,277.00. The bid summary is provid-
ed as follows:
COMPANY BID AMOUNT
GMH ASPHALT CORPORATION $388,714.14
MCNAMARA CONTRACTING $390,801.50
NORTHWEST ASPHALT, INC. $394,656.91
PARK CONSTRUCTION $415,405.20
HARDDRIVES, INC. $439,875.10
VALLEY PAVING, INC. $467,901.65
BITUMINOUS ROADWAYS, INC. $548,180.20
Conclusion
Staff recommends award of this project to GMH Asphalt Corporation.
ISSUES: Pursuant to the Assessment Policy, the street reclamation should be assessed at
up to 40% of the total project cost against the benefiting properties. As been in
past practice in commercial areas, the Assessment Review Workgroup recom-
mends the area method of assessment. The remaining amounts should be recov-
ered through the general tax levy.
The assessment amount will be revised once construction is substantially com-
plete. The assessment hearing will take place in fall of 2019 after substantial com-
pletion of the improvement project.
FINANCIAL
IMPACT:
The Fish Point Road Reclamation Project is proposed to be financed by Special
Assessments and Tax Levy. The funding of each option and the corresponding
estimated amounts are shown below:
3
FISH POINT ROAD RECLAMATION
TOTAL PROJECT - FUNDING
Tax Levy $321,290
Assessment (40%) $124,520
Assessment (Per Acre) – $6,580
Total $445,810
The Capital Improvement Plan estimate for this project was $636,000 with the Tax
Levy component being $572,000 so we are well under budget.
ALTERNATIVES: 1. Approve a Resolution accepting bids and awarding the City’ Standardized
Construction Contract to GMH Asphalt Corporation for the 2019 Fish Point
Road Reclamation Project as part of the consent agenda.
2. Remove this item from the consent agenda for further discussion.
RECOMMENDED
MOTION:
A motion and a second for approval of Alternative #1.
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 19-___
A RESOLUTION ACCEPTING BIDS AND AWARDING THE CITY’S STANDARDIZED
CONSTRUCTION CONTRACT FOR THE 2019 FISH POINT ROAD RECLAMATION
PROJECT (TRN19-000003)
Motion By: Second By:
WHEREAS, Pursuant to an advertisement for bids for the 2019 Fish Point Road Reclamation Project
(City Project #TRN19-000003) which includes full depth pavement reclamation, spot curb
replacement, replacement of the existing bituminous trail, ADA improvements at the
existing curb ramps, turf restoration and appurtenant work; and
WHEREAS, Bids were received, opened, and tabulated according to law; and
WHEREAS, The following bids were received complying with the advertisement:
COMPANY BID AMOUNT
GMH ASPHALT CORPORATION $388,714.14
MCNAMARA CONTRACTING $390,801.50
NORTHWEST ASPHALT, INC. $394,656.91
PARK CONSTRUCTION $415,405.20
HARDDRIVES, INC. $439,875.10
VALLEY PAVING, INC. $467,901.65
BITUMINOUS ROADWAYS, INC. $548,180.20
and;
WHEREAS,
GMH Asphalt Corporation is the lowest responsible bidder.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. GMH Asphalt Corporation is the lowest responsible bidder.
3. The Mayor and City Manager are hereby authorized to enter into the City’s standard contract with GMH
Asphalt Corporation in the name of the City of Prior Lake for the 2019 Fish Point Road Reclamation
Project (Project # TRN19-000003) in the amount of $388,714.14.
4. The City Manager is hereby authorized and directed to return to all bidders the deposits that
accompanied their respective bids.
2
5. The City has previously made a declaration of official intent (”Declaration”) to reimburse certain
estimated costs for this project from proceeds of bonds in Resolution 19 -018.
6. The City Council authorizes funding for these projects as shown in the following table:
FISH POINT ROAD RECLAMATION
PROJECT - FUNDING
Tax Levy $321,290
Assessment (40%) $124,520
Assessment (Per Acre) – $6,580
Total $445,810
7. Construction costs will be recorded in the Construction Fund (#501-43500.00-55050.00 TRN19-
000003) for the 2019 Fish Point Road Reclamation Project.
8. The City Council authorizes the intent to issue General Obligation Bonds for this project.
9. The City Council authorizes an inter-fund loan from the Water Fund if necessary, to provide interim
funding until additional bonds are issued in 2019.
10. Proceeds from the bond sale will be deposited in the Construction Fund.
PASSED AND ADOPTED THIS 18TH DAY OF MARCH 2019.
VOTE Briggs Thompson Braid Burkart Erickson
Aye ☐ ☐ ☐ ☐ ☐
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☐ ☐ ☐
______________________________
Michael Plante, City Manager