MEETING DATE:
AGENDA #:
PREPARED BY:
CITY COUNCIL AGENDA REPORT
MARCH 18, 2019
5F
JASON WEDEL, PUBLIC WORKS DIRECTOR
PRESENTED BY: JASON WEDEL
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION ACCEPTING BIDS AND
AUTHORIZING THE MAYOR AND CITY MANAGER TO EXECUTE THE CITY’S
STANDARDIZED CONSTRUCTION CONTRACT FOR THE 2019 MILL AND
OVERLAY IMPROVEMENT PROJECT (STR19-000001)
GOAL AREA AND
OBJECTIVE:
Transportation & Mobility
1.Maintain quality local street system based on a financially stable plan
that meets Overall Condition targets.
DISCUSSION: Introduction
The purpose of this agenda item is to accept the bids and authorize the Mayor and
City Manager to execute the City’s Standardized Construction Contract with
McNamara Contracting.
History
On November 5, 2018 City Council adopted Resolution 18-173 authorizing staff to
prepare a Feasibility Report for the 2019 Overlay Improvement Project which is
the first step in the MS 429 process. On December 17, 2018 City Council accepted
the Feasibility Report and scheduled a Public Hearing. The Public Hearing was
held on January 22, 2019. On February 4, 2019, the construction plans and
specifications were approved and the City Council authorized staff to advertise for
bids. The Assessment Hearing for this project will be held later this fall in either
September or October.
Current Circumstances
Streets to be Overlaid in 2019 as Identified in Feasibility Study
Pike Lake Trail CSAH 42 Carriage Hills Parkway
Fountain Hill Drive Pike Lake Trail End
Fountain Hills Court Fountain Hills Drive End
Robin Road Pike Lake Trail Hummingbird Trail
Hummingbird Trail Pike Lake Trail Bluebird Trail
Bluebird Trail Carriage Hills Parkway End
Partridge Court Bluebird Trail End
Seagull Circle Robin Road End
Hummingbird Court Hummingbird Trail End
Regal Pass NW Jeffers Pass End
Jeffers Pass CSAH 21 Fairway Heights Rd
Majestic Lane Jeffers Pass End
An advertisement of bid was published in both the Prior Lake American and on
Quest CDN with bids being due and opened on March 6, 2019. The City received
seven (7) bids which are listed in the chard below.
Company Total
McNamara Contracting $716,880.80
GMH Asphalt $720,740.23
Valley Paving $752,971.10
Park Construction $771,525.90
Northwest Asphalt $781,818.30
Bituminous Roadways $798,989.00
Midwest Asphalt $857,211.00
The Engineering Estimate for the project was $800,000.
Conclusion
Staff is recommending awarding the contract to the lowest responsible bidder
which is McNamara Contracting.
ISSUES: Per the Assessment Policy (fee schedule), the assessment rate for 2019 for the
street overlay project is $1,266 for single family and $1,013 for multifamily (0.8 X
$1,266). Commercial and industrial parcels are assessed based on the
Residential Equivalent Density (RED). The assessment rate will be adjusted
annually with an escalator based on the Construction Cost Index (CCI). The
assessment period is over 5 years.
Based on the age of the City’s existing streets, the City is entering a time period
where more streets are in need of timely mill and overlay project to extend their
useful lives. The previous method of funding these projects put pressure on the
tax levy.
FINANCIAL
IMPACT:
The 2019 Mill and Overlay Project is proposed to be financed by Special
Assessments, tax levy and PIR Fund reserves. The total cost was budgeted at
$700,000 which includes $439,900 in special assessments and the remaining
funding of $260,100 coming from tax levy and PIR fund reserves. The project as
shown in the feasibility study was estimated at $800,000 which was over budget.
The scope of the project was purposely set to be over the budget in the event that
the City received better than expected bids and could get more work completed.
Since assessments are being utilized, per State Statute notification requirements,
the project scope could be reduced but it cannot be expanded.
Staff recommends moving forward with the project as presented. After discussing
the funding with Finance Director Erickson, it was determined that the $16,880.80
which is in excess of the $700,000 identified in the 2019 Capital Improvement Plan
can be covered be utilizing funds in the PIR Fund that have been received from
assessment prepayments for the previous year’s mill and overlay project.
Ad Valorem $ 95,000.00
PIR Fund Reserves $ 181,980.80
Assessments $ 439,900.00
Total $ 716,880.80
ALTERNATIVES: 1. Motion and a second as part of the consent agenda to approve the
resolution which accepts the bids and authorizes the Mayor and the City
Manager to execute the City’s Standardized Contract with McNamara
Contracting for the 2019 Mill and Overlay Improvement Project.
2. Remove this item from the consent agenda for additional discussion.
RECOMMENDED
MOTION:
Alternative #1
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 19-___
A RESOLUTION ACCEPTING BIDS AND AUTHORIZING THE MAYOR AND CITY
MANAGER TO EXECUTE THE CITY’S STANDARDIZED CONTRACT FOR THE 2019 MILL
AND OVERLAY IMPROVEMENT PROJECT (STR19-000001)
Motion By: Second By:
WHEREAS, The City of Prior Lake is committed to improving the streets within the City by
providing continued maintenance; and
WHEREAS, Continued maintenance of City streets will reduce the need of costly reconstruction
in the near future; and
WHEREAS, A total of seven (7) bids were received for the identified improvements as follows:
Company Total
McNamara Contracting $716,880.80
GMH Asphalt $720,740.23
Valley Paving $752,971.10
Park Construction $771,525.90
Northwest Asphalt $781,818.30
Bituminous Roadways $798,989.00
Midwest Asphalt $857,211.00
WHEREAS,
WHEREAS,
McNamara is the lowest responsible bidder in the amount of $716,880.80; and
The additional cost of $16,880.80 in excess of the Capital Improvement Plan
budget will be covered by utilizing existing funds within the Permanent
Improvement Revolving (PIR) fund that were received from special assessment
payments from previous Mill and Overlay projects.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and City Manager are hereby authorized to execute the City’s Standardized
Contract for the identified streets overlays with McNamara Contracting for an estimated
cost of $716,880.80. Construction contract expenditures will be charged to 450-
43100.00-55010.00-PRI19-000001) The City’s intent is to issue bonds for the special
assessment portion of the project funding. The funds will be drawn from the Permanent
Improvement Revolving (PIR) Fund 450 as shown on the following table.
Ad Valorem $ 95,000.00
PIR Fund Reserves $ 181,980.80
Assessments $ 439,900.00
Total $ 716,880.80
2
3. The City Council authorizes the intent to issue General Obligation Bonds for this project.
4. Proceeds from the bond sale will be deposited in the Permanent Improvement Revolving
Fund.
5. The City has previously made a declaration of official intent (”Declaration”) to reimburse
certain estimated costs for this project from proceeds of bonds in Resolution 19-018.
Passed and adopted by the Prior Lake City Council this 18th day of March 2019.
VOTE Briggs Thompson Burkart Braid Erickson
Aye ☐ ☐ ☐ ☐ ☐
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☐ ☐ ☐
______________________________
Michael Plante, City Manager