HomeMy WebLinkAbout1B Fish Point Rd (CR44 to TH13) Recon Project Update CCWS Report
Phone 952.447.9800 / Fax 952.447.4245 / www.cityofpriorlake.com
4646 Dakota Street SE
Prior Lake, MN 55372
CITY COUNCIL WORK SESSION AGENDA REPORT
MEETING DATE: DECEMBER 2, 2019
AGENDA #: 1B
PREPARED BY: ANDY BROTZLER, PE, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
NICK MONSERUD, PE, ASSISTANT CITY ENGINEER
PRESENTED BY: STAFF AND PROJECT CONSULTANT
AGENDA ITEM:
TRN 20-000001 FISH POINT ROAD (CR 44 TO TH 13) RECONSTRUCTION
PROJECT UPDATE
DISCUSSION: The reconstruction of Fish Point Road (CR 44 to TH 13) including the full
replacement of utilities is scheduled for 2021. With prior Council authorization,
preliminary survey has been completed and preparation of the feasibility report is
in progress.
Based on the known project challenges including topography, trees, retaining walls
and right-of-way, staff and the project consultant will provide Council an update
and presentation on the anticipated project impacts associated with the
reconstruction of the street and utilities to City standards. Additionally, information
will be presented on alternatives that have been considered on a high level that
would result in a deviation from City standards to potentially minimize impacts to
private property, trees and retaining walls.
Staff is recommending to proceed with the development of a final feasibility report
to be developed in accordance with City standards.