HomeMy WebLinkAbout01(A) - Draft 2021-2025 Capital Improvement Program Part 2 of 2 ReportFor the Water Fund:
For the Sewer Fund:
Water Fund 2020 2021 2022 2023 2024 2025
Cash by Purpose
For future capital improvements 1,647,067 1,804,019 1,810,727 823,584 884,835 1,049,158
For following year pay-go capital 2,068,750 931,500 949,240 2,295,730 1,310,979 1,261,640
For private streets replacement 5 - 188,400 228,336 269,869 313,064 357,987
For 3-months of operating cash 639,290 663,903 683,239 697,789 712,583 727,735
For following year debt service 4 735,350 747,525 779,100 784,300 789,000 791,950
Ending Cash 5,090,457 4,335,346 4,450,642 4,871,272 4,010,460 4,188,469
Total Average Number of Customer Bills 9,377 9,502 9,637 9,772 9,897 10,022
Total Water Volume Billed (1,000 of gallons)653,489 667,676 677,396 687,116 696,116 705,116
High Volume Customer (78,000 gallons)4.9%5.4%1.5%1.5%1.5%1.5%
Medium Volume Customer (18,000 gallons)4.6%-12.0%1.5%1.5%1.5%1.5%
Low Volume Customer (8,000 gallons)4.2%-1.5%1.5%1.5%1.5%1.5%
Average Annual % Change in Water Bill for Billing Period 1
Sewer Fund 2020 2021 2022 2023 2024 2025
Cash by Purpose
For future capital improvements 63,396 1,587,714 1,618,614 1,498,053 1,378,310 1,270,677
For following year pay-go capital 1,499,750 1,020,200 875,240 1,148,230 1,209,979 1,261,096
For private streets replacement 5 - 188,400 228,336 269,869 313,064 357,987
For 3-months of operating cash 766,260 785,357 887,867 932,416 979,227 1,028,929
For following year debt service 169,650 274,332 264,700 262,050 259,200 254,825
Ending Cash 2,499,055 3,856,003 3,874,757 4,110,618 4,139,779 4,173,513
Total Average Number of Customer Bills 9,224 9,349 9,484 9,619 9,744 9,869
Total Sewer Volume Billed (1,000 of gallons)545,433 552,933 561,033 569,133 576,633 584,133
High Volume Customer (47,000 gallons)14.1%10.6%2.0%2.0%2.0%2.0%
Medium Volume Customer (12,000 gallons)12.5%-11.4%2.0%2.0%2.0%2.0%
Low Volume Customer (7,000 gallons)11.2%-0.7%2.0%2.0%2.0%2.0%
Average Annual % Increase for Fees and Charges 1, 4
Stormwater Fund 2020 2021 2022 2023 2024 2025
Cash by Purpose
For future capital improvements 667,498 601,767 769,343 709,237 769,816 612,319
For following year pay-go capital 325,000 292,000 60,000 295,000 183,000 407,500
For private streets replacement 3 - - - - - -
For 3-months of operating cash 186,173 187,103 191,013 195,008 199,092 203,266
For following year debt service - - - - - -
Ending Cash 1,178,671 1,080,870 1,020,356 1,199,246 1,151,908 1,223,085
Total Average Number of Residential Equivalent
Units Billed 9,225 9,350 9,485 9,620 9,745 9,870
Per Residential Equivalent Unit 10.0%1.0%1.0%1.0%1.0%1.0%
Average Annual % Increase for Fees and Charges
2020 Budget: Proposed for Year 2021:
2020 Budget: Proposed for Year 2021:
Water Services
Sewer Services
Capital Improvement Plan
City of Prior Lake, Minnesota Contact
2021 2025thru Department Fire
Description
Engine #9221 was purchased in 1996. Per the City’s Equipment Replacement Plan, this vehicle was scheduled to be replaced after 25-years of
service and has been planned for replacement since the city’s 2011-2022 adopted Capital Improvement Program(CIP). As was the council’s
original direction when the replacement plan was created, we have retained this piece of equipment to garner the longest possible useful life. The
Equipment Replacement Plan was created as a budgeting tool to assist in financial planning for major expenditures and to help moderate the annual
fleet replacement budget. The goal is to replace equipment in a timely and cost-effective manner. This engine is currently 24-years old (in 2020)
and in need of replacement. The Fire Department found with the last engine replacement, that the build time took 20 months which extended the
service life of engine #9220 to 27 years. The Fire Department expects a similar build time for this replacement which would extend the service life
of engine #9221 to 27 years.
Project #FD-9221
Justification
As the needs of the fire department have grown over the years, so has the equipment they need to do their jobs. This has required that additional
equipment be added to the existing engine. The weight of the truck has been impacted as a result and there has been a history of the brakes being
undersized for the current weight. In addition, due to the age of the truck it is becoming increasingly difficult to find parts to perform maintenance
which causes extended out of service time. The replacement engine will be designed as a rescue engine which allows for additional equipment to
be carried. This allows the Fire Department to perform several tasks that would normally require several other vehicles and manpower to facilitate.
This is the same design that was used in the replacement of engine #9220 in 2018 and has been found to be extremely efficient.
The engine is and has been part of the Capital Improvement Program for some time. As directed by previous city councils the staff has sought to
retain equipment as long as possible before replacing. That is why we have retained this equipment for 25 rather than 20 years. We have previously
saved money by refurbishing Fire vehicles. This practice was evaluated for this equipment but is not feasible since the chassis, transmission, drive
train and engine would have to be upgraded to provide the needed carrying capacity.
Budget Impact/Other
The annual adopted Capital Improvement Program(CIP) has included the City's plan to fund this equipment purchase with bond proceeds.
Useful Life 25 years
Project Name 1996 Peterbilt Pumper Category Equipment: FD-Apparatus
Type Equipment
Total Project Cost:$740,000
Total20212022202320242025Expenditures
740,000740,000Equip/Vehicles/Furnishings
740,000 740,000Total
Total20212022202320242025Funding Sources
740,000740,000410-Equip. Replacement Fund
740,000 740,000Total
Friday, May 29, 2020Page 1Produced Using the Plan-It Capital Planning Software
Andy Brotzler
Cathy Erickson
Kelly Horn
2021-2025 CAPITAL
IMPROVEMENT PROGRAM
Transportation Plan and Utility Funds
August 3, 2020
2021-2025 CIP Schedule
June 15 -Capital Plans Review I
•Equipment
•Park Equipment
•Facilities
•Technology Plan
August 3 -Capital Plans Review II
•Utility Funds –Financial Plans
•Transportation Plan
•Financial Impacts
November 16 -Public Hearing and Adopt 2021-2025 CIP
2021-2025 CIP Schedule
•Utility Study Completed by Northland Public Finance in
2019
•Serves as a guide for the financial management of the
water and sanitary sewer systems
2021-2025 CIP Schedule
Utility Funds
Financial Management Plan
5
Study Objectives:
Utility Funds
Financial Management Plan
6
Study Objectives:
Utility Funds
Financial Management Plan
7
•67% Water Costs and 47% of Sewer Costs are Fixed (not dependent on water & sewer
usage/volume)
•Only 10% of Water and 11% of Sewer Revenues are derived from fixed fees/charges
Utility Funds
Financial Management Plan
8
Study Provided Base Rates Targets:
Utility Funds
Financial Management Plan
9
Water Fund:
Utility Funds
Financial Management Plan
10
Sewer Fund:
Water Fund
Sample Water Bill
11
Water Fund
Financial Management Plan
12
Water Fund 2020 2021 2022 2023 2024 2025
Cash by Purpose
For future capital improvements 1,647,067 1,804,019 1,810,727 823,584 884,835 1,049,158
For following year pay-go capital 2,068,750 931,500 949,240 2,295,730 1,310,979 1,261,640
For private streets replacement 5 - 188,400 228,336 269,869 313,064 357,987
For 3-months of operating cash 639,290 663,903 683,239 697,789 712,583 727,735
For following year debt service 4 735,350 747,525 779,100 784,300 789,000 791,950
Ending Cash 5,090,457 4,335,346 4,450,642 4,871,272 4,010,460 4,188,469
Total Average Number of Customer Bills 9,377 9,502 9,637 9,772 9,897 10,022
Total Water Volume Billed (1,000 of gallons)653,489 667,676 677,396 687,116 696,116 705,116
High Volume Customer (78,000 gallons)4.9%5.4%1.5%1.5%1.5%1.5%
Medium Volume Customer (18,000 gallons)4.6%-12.0%1.5%1.5%1.5%1.5%
Low Volume Customer (8,000 gallons)4.2%-1.5%1.5%1.5%1.5%1.5%
Average Annual % Change in Water Bill for Billing Period 1
Sewer Fund
Sample Sewer Bill
13
Sewer Fund
Financial Management Plan
14
Sewer Fund 2020 2021 2022 2023 2024 2025
Cash by Purpose
For future capital improvements 63,396 1,587,714 1,618,614 1,498,053 1,378,310 1,270,677
For following year pay-go capital 1,499,750 1,020,200 875,240 1,148,230 1,209,979 1,261,096
For private streets replacement 5 - 188,400 228,336 269,869 313,064 357,987
For 3-months of operating cash 766,260 785,357 887,867 932,416 979,227 1,028,929
For following year debt service 169,650 274,332 264,700 262,050 259,200 254,825
Ending Cash 2,499,055 3,856,003 3,874,757 4,110,618 4,139,779 4,173,513
Total Average Number of Customer Bills 9,224 9,349 9,484 9,619 9,744 9,869
Total Sewer Volume Billed (1,000 of gallons)545,433 552,933 561,033 569,133 576,633 584,133
High Volume Customer (47,000 gallons)14.1%10.6%2.0%2.0%2.0%2.0%
Medium Volume Customer (12,000 gallons)12.5%-11.4%2.0%2.0%2.0%2.0%
Low Volume Customer (7,000 gallons)11.2%-0.7%2.0%2.0%2.0%2.0%
Average Annual % Increase for Fees and Charges 1, 4
Stormwater Fund
Sample Sewer Bill
15
2020
Total Fee 16.57
2021
Total Fee 16.74
% Increase 1.0%
Stormwater Customers
Stormwater Fund
Financial Management Plan
16
Stormwater Fund 2020 2021 2022 2023 2024 2025
Cash by Purpose
For future capital improvements 667,498 601,767 769,343 709,237 769,816 612,319
For following year pay-go capital 325,000 292,000 60,000 295,000 183,000 407,500
For private streets replacement 3 - - - - - -
For 3-months of operating cash 186,173 187,103 191,013 195,008 199,092 203,266
For following year debt service - - - - - -
Ending Cash 1,178,671 1,080,870 1,020,356 1,199,246 1,151,908 1,223,085
Total Average Number of Residential Equivalent
Units Billed 9,225 9,350 9,485 9,620 9,745 9,870
Per Residential Equivalent Unit 10.0%1.0%1.0%1.0%1.0%1.0%
Average Annual % Increase for Fees and Charges
Combined Impact –All Funds
Sample Bill
17
Customers High Volume Customer Medium Volume Customer Low Volume Customer
Gallons Water Billed for Billing Period 78,000 18,000 8,000
Gallons Sewer Billed for Billing Period 47,000 12,000 7,000
Stormwater REU 1 1 1
2020
Capital Facility Charge 10.00 10.00 10.00
Water 497.63 93.40 42.90
Sewer 185.33 49.18 29.73
Stormwater 16.57 16.57 16.57
Total Fee 709.53 169.15 99.20
2021
Base Fee - Water & Sewer 37.00 37.00 37.00
Capital Facility Charge - - -
Water 509.88 66.64 27.20
Sewer 193.45 31.00 17.50
Stormwater 16.74 16.74 16.74
Total Fee 757.07 151.38 98.44
% Increase 6.7%-10.5%-0.8%
Multi-Family Residential -
Water and Sewer
◼Usage Rates
–Water: $5.00 per 1,000 gallons
–Sewer: $3.50 per 1,000 gallons
◼Base Rates
–Varies; Dependent on the number of multi-family
units on property
Private Street Utility Surcharge
Utility Financial Plans –
Next Steps
September 2020
Council Approves Preliminary
Utility Fund Budgets
December 2020
Council Approves 2021 Rate
Structure and Utility Rates
1st Quarter 2021
Implement New Rate Structure
and Utility Rates
3rd Quarter 2021
Implement New Utility Billing
Software System
Transportation Plan
Transportation Plan Map
Street Overlay Plan
23
•Assumes tax levy per current CIP
•No annual project for 2021-2023 to build fund
balance
2020 2021 2022 2023 2024 2025
PIR Fund (F450)
Use of Funds:
Street Overlay Project 758,000$ -$ -$ -$ 300,000$ 500,000$
Transfer to Debt Service Funds 280,000 287,000 319,000 239,000 131,000 48,000
Total Use of Funds 1,038,000$ 287,000$ 319,000$ 239,000$ 431,000$ 548,000$
Sources of Funds:
Special Assessment Revenue 190,000 173,000 166,000 126,000 87,000 61,000
Bond Proceeds 258,000 163,200 50,000 90,000
Tax Levy 80,000 120,000 155,000 190,000 225,000 240,000
Interest Earnings 7,000 1,000 4,000 4,100 5,500 4,400
Total Source of Funds 535,000$ 457,200$ 325,000$ 320,100$ 367,500$ 395,400$
Change in Fund Balance (503,000) 170,200 6,000 81,100 (63,500) (152,600)
Beginning Fund Balance 559,000$ 56,000$ 226,200$ 232,200$ 313,300$ 249,800$
Ending Fund Balance 56,000$ 226,200$ 232,200$ 313,300$ 249,800$ 97,200$
Financial Impacts
Annual projected total CIP tax levy by component
2021 2022 2023 2024 2025
Equipment
Revolving Fund
650,000 700,000 750,000 800,000 850,000
Revolving Park
Equip Fund
375,000 405,000 440,000 485,000 535,000
Facilities
Management Fund
80,000 105,000 140,000 165,000 190,000
PIR Fund 120,000 155,000 190,000 225,000 240,000
Debt Service 3,559,808 3,769,033 3,767,796 3,741,240 3,895,099
Total CIP Tax Levies 4,784,808 5,134,033 5,287,796 5,416,240 5,710,099
2021-2025 CIP
Tax Levies:
Projected CIP Tax Levy
Debt Projection
25
Debt Projection
26
Debt Projection
27
28
The tax levy
and debt
service impacts
of the CIP have
been
incorporated
into the long-
range financial
plan.
Next steps:
•Proposed utility rates incorporated into
2021 Preliminary Budgets
•Budget Workshop –September 8, 2020
•September 21 –Adopt Preliminary
Budgets and Preliminary Tax Levy
•CIP Public Hearing –November 16, 2020
Council Discussion
29
Questions/Discussion