HomeMy WebLinkAbout05(I) - Approve Work Order for Mushtown Rd. – 180th Street Watermain Extension (CP 2021-17) ReportPage 1 of 2
Public Works Consultant Pool
Work Order
Supplemental Agreement to Provide Professional Engineering Services
Mushtown Road – 180th Street Watermain Extension
WSB & ASSOCIATES, INCORPORATED, dba WSB
This work order (“Work Order”) is issued on this 19th day of July 2021 by the City of Prior Lake
(“City”) pursuant to the Public Works Consultant Pool – Master Agreement dated April 20, 2020
(“Contract”) between the City and WSB & Associates, Incorporated, dba WSB (“Consultant”).
Based on the mutual promises and covenants set forth herein, the sufficiency of which are hereby
acknowledged, the City and Consultant agree as follows:
1.Scope of Work Order. Consultant agrees to provide, perform and complete all the services
requested by the City in this Work Order and attached Exhibit 1 (“Work”), which Work shall be
subject to the terms and conditions of this Work Order and the Contract.
2.Term of Work Order. All Work requested by this Work Order shall be completed December
31, 2021.
3.Compensation for Work Order. City agrees to pay the Consultant an estimated sum of
$53,205 as full and complete payment for the Work requested by this Work Order. This
amount does not include fees for acquisition of right of way or any temporary or
permanent easements.
4.Consultant Representative. Consultant has designated Monica Heil, P.E. to manage the
Work Order subject to the supervision of Consultant’s representative.
ISSUED BY CITY OF PRIOR LAKE
___________________________________
City Manager
RECEIVED AND ACCEPTED BY
CONSULTANT
_____________________________________
By:_______________________________
Its:_______________________________
Page 2 of 2
Exhibit 1 – Scope of Work Order
G:\.Clients All\Prior Lake\Proposals\2021 - Mushtown Road Watermain Extension\LTR_MH_ABrotzler-060221-Mushtown Road Watermain Extension.docx 178 E 9TH STREET | SUITE 200 | SAINT PAUL, MN | 55101 | 651.286.8450 | WSBENG.COM
June 2, 2021
Mr. Andy Brotzler, P.E.
Director of Public Works/City Engineer
City of Prior Lake
17073 Adelmann St. SE
Prior Lake, MN 55372
Re: Supplemental Agreement to Provide Professional Engineering Services
Mushtown Road – 180th Street Watermain Extension
Dear Mr. Brotzler:
WSB is pleased to provide you with our proposal for professional services for the preparation of
construction documents and associated services for the extension of watermain in 180th Street
and Mushtown Road. The proposed improvements include approximately 2,600 feet of 12-inch
diameter watermain that provides a closed loop in the water system in this area of the City and to
serve the Parkwood Estates development.
Scope of Services
Generally, the scope of services will include topographic survey, geotechnical evaluation,
preparation of construction documents, bidding assistance, construction contract administration,
construction survey staking, and preparation of record plans.
The following list of tasks is proposed to complement preparation of construction documents
necessary to construct the project:
Task 1: Topographic Survey
WSB will perform a topographic survey to identify the existing terrain features, utilities, culverts,
and miscellaneous topographic features in the project corridor.
▪ Survey will include cross sections at approximately 50-foot intervals and generally will
identify edge-of-bituminous, centerline, shoulder PI, ditch/boulevard.
▪ Driveways from edge of driveway to 10 feet past the right-of-way.
▪ Storm drainage features such as culverts, including inverts, pipe size and material type.
▪ Sanitary sewer manholes.
▪ Watermain gate valves and hydrants.
▪ Significant trees of 4-inch diameter and larger.
▪ Perform Gopher State One Call and survey existing utilities as marked in the project
corridor. Utilities that are not marked by the utility owner will be identified on the plans by
mapping information provided by the utility owner. Utilities will be represented on the
plans as SUE quality level C or D.
Task 2: Geotechnical Evaluation
WSB will perform a geotechnical exploration and evaluation to identify general soil information in
the project corridor consisting of the following items:
▪ Geotechnical Field Work and Evaluation Report
o Access site with CME-55 truck mounted auger drill rig
o Perform six (6) soil borings to depth of about 14.5 feet below grade
▪ If borings are extended due to unsuitable soils at termination depths
Mr. Andy Brotzler, P.E.
June 2, 2021
Page 2
G:\.Clients All\Prior Lake\Proposals\2021 - Mushtown Road Watermain Extension\LTR_MH_ABrotzler-060221-Mushtown Road Watermain Extension.docx
(organics, fills, etc), additional depth may be required at additional cost
per foot.
▪ We will utilize flashing lights, signage, and cones for traffic control and
allow traffic to self-regulate around our work zone.
o Samples retrieved during drilling will be returned to our laboratory where they will
be reviewed, classified using the Unified Soil Classification System (USCS) and
logged under the direction of a geotechnical engineer.
o Select samples will be set aside for laboratory testing. We may perform routine
laboratory tests on selected soil samples obtained from the exploration.
o WSB will complete Gopher State One Call (GSOC) utility clearance to have
public underground utilities marked.
▪ Private utilities are the responsibility of the utility owner to mark, and
WSB should be notified of any private underground utilities that are
onsite.
o Some damage could occur to greenspace areas from normal drilling mobilization
and operations. Our proposed services do not include restoration of the site to
pre-conditions.
o Due to recent roadway improvements in the project corridor, no borings will be
taken within the bituminous pavement surfaces.
o Based on the proposed boring depths to depths ( < 15 feet ), MDH well sealing
notification and fees will not be required. If the borings are extended to a depth
of 15 feet or more, additional fees will be charged.
o WSB will prepare a geotechnical report with discussion of subsurface soil and
groundwater conditions and how they may affect the construction of the
watermain.
Task 3: Preparation of Construction Documents (Plans and Specifications)
The construction documents (plans and specifications) will be prepared in accordance with the
City's engineering requirements. The plans will be prepared for horizontal directional drilling
methods of construction.
The plans will generally include the following sheets (or combined items on sheets) for the
proposed improvements:
▪ Title sheet
▪ General Layout plan
▪ Statement of Estimated Quantities
▪ Construction Notes
▪ Typical sections (if necessary)
▪ Standard Details
▪ Existing Conditions and Removals
▪ Watermain plan and profile
▪ Temporary and permanent erosion control plans
The number of plan sheets estimated for this proposal are shown in more detail on the Estimated
Project Fee worksheet enclosed for your reference.
Our staff will perform a GSOC design request for private utility maps, field markings for the
topographic survey, GSOC design meeting and coordination with utility owners.
Task 4: Agency Permits
WSB staff will prepare permit applications for the PL-SLWD and Minnesota Department of Health
Watermain Plan Review. The permit fees are proposed as reimbursable expenses to the project
and are identified on the fee worksheet for reference.
Mr. Andy Brotzler, P.E.
June 2, 2021
Page 3
G:\.Clients All\Prior Lake\Proposals\2021 - Mushtown Road Watermain Extension\LTR_MH_ABrotzler-060221-Mushtown Road Watermain Extension.docx
The fee estimates for work associated with permitting the proposed project within Credit River
Township. include one joint meeting with the City and Township. Once the scope of work
associated with permitting the project within township right of way has been defined, WSB can
provide a separate fee estimate for permitting work associated with the project (Right of way,
traffic control, road closures, as needed or required).
Task 5: Bidding Assistance
During the bidding phase of the project, WSB staff will provide assistance to the City and to plan
holders in responding to pre-bid questions, clarifications, addenda (if necessary) and opening of
bids. Our staff will prepare bid tabulations, bid summary and recommendation letter for
consideration of awarding a contract.
Task 6: Construction Administration
During the construction phase, our staff will attend the pre-construction meeting, prepare the
meeting agenda, and provide meeting summary notes of the discussion at the meeting.
We propose to prepare construction payment vouchers on a monthly basis upon contractor
application for payment, and will coordinate signatures of the contractor, city and our staff for
processing.
Task 7: Construction Survey and Engineering
The construction services includes engineering assistance to the City for the interpretation of
plans and specifications as requested, and a survey crew for construction staking services,
record plan survey, and preparation of record plans for the constructed improvements.
The City plans to provide a resident construction representative to observe construction activities
daily, and document quantities for partial payment to the Contractor. The City representative will
contact WSB to schedule construction staking, and to request clarification of plans and
specifications, on an as-needed basis.
Compensation Summary
Our fees for the scope of services is proposed on an hourly basis, estimated as summarized
below. The fee estimate is provided in a detailed format on the enclosed Estimated Project Fees
Worksheet.
▪ Task 1: Topographic Survey $ 5,939
▪ Task 2: Geotechnical Evaluation $ 5,904
▪ Task 3: Preparation of Construction Documents $ 25,237
▪ Task 4: Agency Permits $ 1,643
▪ Task 5: Bidding Assistance $ 1,104
▪ Task 6: Construction Administration $ 1,548
▪ Task 7: Construction Survey and Engineering $ 10,805
Reimbursable Expenses (Permit Fees) $ 1,025
Total Fee $53,205
Our proposed scope and estimated fees do not include acquisition of right of way, temporary or
permanent easements. However, when the design work is completed and it is determined
easements will be required, WSB can provide a separate fee estimate for right of way services.
Mr. Andy Brotzler, P.E.
June 2, 2021
Page 4
G:\.Clients All\Prior Lake\Proposals\2021 - Mushtown Road Watermain Extension\LTR_MH_ABrotzler-060221-Mushtown Road Watermain Extension.docx
Thank you for the opportunity to provide professional services to the City of Prior Lake for the
Mushtown-180th Street Watermain Extension Project. Feel free to contact me if you have any
questions.
Sincerely,
WSB
Monica Heil, P.E.
Vice President of Municipal Services
(952) 737-4675
MHeil@wsbeng.com
Attachments
cc: Nick Monserud, PE, City of Prior Lake
Paul Hornby, WSB
pth
Estimated Hours
Senior Senior Senior
Project Project Engineering Engineering Engineering Project Survey Two-Person Geotechnical Geotechnical Office Total
Manager (MUN)Engineer Specialist VI Specialist II Technician III Engineer Coordinator Suvey Crew Engineer Drill Rig & Crew Technician Hours Fee
Task Description PTH KK TC DH BS CB PH/JH DH KP
Data Collection
1.0 Topographic Survey 1 4 26 31 5,939.00$
2.0 Geotechnical Evaluation & Report 2 6 16 24 5,904.00$
3.0 Plans, Specs, Bid and Construction
3.1 Project Management 8 2 2 12 2,112.00$
3.2 GSOC coordination 2 2 260.00$
3.3 GSOC Meeting 4 4 520.00$
3.4 Plans -$
A. Title Sheet 1 2 1 3 286.00$
B. General Layout 1 4 2 6 572.00$
C. Statement of Quantities/Notes 1 2 4 6 12 1,368.00$
D. -$
E. Typical Section/Pavement Details -$
F. Standard Details 1 2 1 3 286.00$
G. -$
H. General Construction Notes 1 1 1 2 2 6 702.00$
I. Exisitng Conditions and Removal Plans 2 2 4 4 4 14 1,700.00$
J. Construction Plan and Profile Watermain.4 4 8 10 60 16 98 10,132.00$
-$
K. Erosion Control Plan 2 1 4 8 4 17 1,874.00$
-$
3.5 Specifications 2 4 8 6 20 2,556.00$
3.6 Engineers Opinion of Construction Cost 1 2 4 7 993.00$
3.7 Meetings 2 2 4 654.00$
3.9 QA/QC 2 6 8 1,222.00$
4.0 Permits (PL-SLWD, MnDOH)1 1 4 6 855.00$
4.1 Meeting - City and Credit River Twp. (R/W permit reqmnts)4 4 788.00$
5.0 Bidding Assistance 2 4 2 8 1,104.00$
-$
6.0 Construction Administration 4 8 12 1,548.00$
7.0 Construction Engineering Support 8 4 12 2,128.00$
7.1 Preconstruction Meeting 2 2 4 654.00$
7.2 Construction Staking 6 20 26 4,832.00$
7.3 Record Plan Survey 6 6 1,194.00$
7.4 Record Plan Preparation 1 4 16 21 1,997.00$
44 37 19 102 68 10 52 6 16 16 370 52,180.00$
Grand Total Hours 44 37 19 102 68 10 52 6 16 16 370 52,180.00$
Hourly Rate 197.00 138.00 148.00 120.00 78.00 130.00 142.00 199.00 145.00 290.00 95.00
Grand Total Direct Labor Costs 8,668.00$ 5,106.00$ 2,812.00$ -$ 7,956.00$ 8,840.00$ 1,420.00$ 10,348.00$ 870.00$ 4,640.00$ 1,520.00$ 52,180.00$
Reimbursable Expenses -
Permit Fees:
PL-SLWD 500.00$
MnDOH 150.00$
Spring Lake Twp 375.00$
Subtotal Expenses 1,025.00$
Total Fee (Hourly estimated fee) 53,205.00$
Exhibit C.1 - Estimated Project Fees
Mushtown Road/180th Street Watermain Extension
City of Prior Lake, MN