HomeMy WebLinkAbout22-014 Receive bids and award contract for the 2022 Stormwater Pond Maintenance Project
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 21-014
A RESOLUTION RECEIVING BIDS AND AWARDING THE CONTRACT FOR THE 2022 STORMWATER
POND MAINTENANCE PROJECT (2021-19)
Motion By: Thompson Second By: Churchill
WHEREAS, Construction of this project will help to satisfy state-mandated stormwater
requirements and support Council goals of protecting and enhancing Prior
Lake’s surface waters; and
WHEREAS, The project was advertised for bids for two weeks beginning December 25,
2021; and
WHEREAS, The City received 9 bids from qualified bidders, ranging from $166,677.87 to
$379,127.59; and
WHEREAS, Peterson Companies, Inc. is the lowest responsible bidder, with a bid of
$166,677.87, which is 17% lower than the engineer’s estimate for this project;
and
WHEREAS, City staff recommends awarding a City Standard Construction Contract to
Peterson Companies, Inc. for the construction of the 2022 Stormwater Pond
Maintenance Project.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and City Manager are hereby authorized to execute the City’s Standard
Construction Contract for the construction of the 2022 Stormwater Pond Maintenance
Project with Peterson Companies, Inc. in the amount of $166,677.87.
3. The funding for this project will come from the Water Quality Fund.
Passed and adopted by the Prior Lake City Council this 18th day of January 2022.
VOTE Briggs Thompson Burkart Braid Churchill
Aye ☒ ☒ ☐ ☒ ☒
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☒ ☐ ☐
______________________________
Jason Wedel, City Manager