HomeMy WebLinkAbout05(E) - Approve Work Order for the 2022 Lift Station Rehabilitation Project ReportPage 1 of 2
Public Works Consultant Pool Work Order
2022 Lift Station Rehabilitation Project
BOLTON & MENK
This work order (“Work Order”) is issued on this 22nd day of February 2022 by the City of Prior
Lake (“City”) pursuant to the Public Works Consultant Pool – Master Agreement dated April 20,
2020 (“Contract”) between the City and Bolton & Menk (“Consultant”).
Based on the mutual promises and covenants set forth herein, the sufficiency of which are hereby
acknowledged, the City and Consultant agree as follows:
1.Scope of Work Order. Consultant agrees to provide, perform and complete all the services
requested by the City in this Work Order and attached Exhibit 1 (“Work”), which Work shall be
subject to the terms and conditions of this Work Order and the Contract.
2.Term of Work Order. All Work requested by this Work Order shall be completed by
December 31, 2022.
3.Compensation for Work Order. City agrees to pay the Consultant an hourly not to
exceed amount of $62,000 as full and complete payment for the Work requested by this
Work Order.
4.Consultant Representative. Consultant has designated Seth Peterson to manage the Work
Order subject to the supervision of Consultant’s representative.
ISSUED BY CITY OF PRIOR LAKE
___________________________________
City Manager
RECEIVED AND ACCEPTED BY
CONSULTANT
___________________________________
By:________________________________
Its:________________________________
Page 2 of 2
Exhibit 1 – Scope of Work Order
N:\Proposals\Prior Lake\Wilds Lift Station\Wilds Quaker Lift Station Proposal Letter revised.docx
January 14, 2022
Mr. Andy Brotzler, P.E. Mr. Andy Stephes
Public Works Director/City Engineer Utilities Foreman
City of Prior Lake City of Prior Lake
17073 Adelman St. SE 17073 Adelmann St. SE
Prior Lake, MN 55372 Prior Lake, MN 55372
Re: Wilds and Quaker Lift Stations
Prior Lake, Minnesota
Dear Mr. Brotzler and Mr. Stephes,
Thank you for providing us this opportunity to assist you with the rehabilitation plans for the Wilds and
Quaker Lift Station projects. Bolton & Menk, Inc., has the technical expertise, experience, and resources
to complete this project for the City and we appreciate your consideration.
Based on our understanding, the project will consist of the following major components:
Wilds Lift Station
•Replacement of existing pumps
•Replacement of existing control panel
•Replacement of existing piping and valves
•Replacement of existing wet well and valve vault top slabs and hatches
•Miscellaneous piping and site work
•Replacement of existing bituminous driveway
Quaker Lift Station
•Remove existing pumps, piping, manhole and controls
•Install new package lift station in new location
o Duplex pumps
o Integrated control panel
•Install new, small diameter forcemain to existing manhole
A soil boring may be required for the Quaker lift station since the new station will be relocated. We have
not included soil borings in our design tasks or fee estimate but will assist with coordinating a soil boring
if required. The City would pay the geotechnical engineering fees directly if a soil boring is required.
We have identified three (3) tasks in order to complete the work as described above. A summary of the
tasks is described below:
Task 1 – Preliminary Design Phase
•Assemble and review existing site data (surveys, preliminary plans, as-built information, etc.)
•Topographic survey (to be completed by Bolton & Menk – survey already completed for Wilds lift
station)
EXHIBIT 1
Mr. Andy Brotzler and Mr. Andy Stephes
Date: January 14, 2022
Page: 2
N:\Proposals\Prior Lake\Wilds Lift Station\Wilds Quaker Lift Station Proposal Letter revised.docx
• Complete preliminary design summary
Task 2 – Final Design Phase
• Prepare final plans and specifications
• Design review meetings with City staff (if needed)
• Construction cost estimates
• Bidding services
Task 3 – Construction Phase
• Construction administration
• Construction observation
• Construction staking (to be completed by Bolton & Menk)
• Coordinating start-up services
• Record drawings
Seth Peterson, P.E., will serve as the primary contact and the lead designer for the lift station
improvements. Mr. Peterson has successfully completed many similar projects and brings a wealth of
experience to this project. Jacob Humburg, P.E. and Kaija Ornes-Ward will serve as design engineers
assisting Mr. Peterson. Mr. Humburg and Ms. Ornes-Ward have been involved in the design of numerous
lift station projects in their careers with Bolton & Menk. Sheldon Sorensen, P.E., from Barr Engineering,
will provide the electrical and controls engineering for this project. Mr. Sorensen has worked with Bolton
& Menk, Inc., for over 25 years on a variety of projects ranging from lift station upgrades to large water
treatment facilities.
We understand that the City would like this project to be bid as soon as possible in 2022 and have the
project completed in 2022. The plan is to bid both projects together with one set of construction
documents. We will work diligently to obtain the initial information needed as quickly as possible and to
achieve this desired design schedule.
We propose to complete the above design and construction phase services for a total estimated fee of
$62,000. The following is a summary of our fees:
Design Phase
Preliminary Design Phase ................................................. $12,000
Final Design Phase ............................................................ $21,000
Subtotal Not-to-Exceed Fixed Fee ................................. $33,000
Construction Phase
Construction Administration ............................................. $11,500
Construction Observation ................................................ $15,500
Record Drawings .............................................................. $2,000
Subtotal Estimated Fee ................................................... $29,000
Total Estimated Fee ........................................................ $62,000
Mr. Andy Brotzler and Mr. Andy Stephes
Date: January 14, 2022
Page: 3
N:\Proposals\Prior Lake\Wilds Lift Station\Wilds Quaker Lift Station Proposal Letter revised.docx
Because the engineer has no direct control over the scheduling or operations of the project contractor,
construction phase services described in this proposal are estimated based on similar projects and are
proposed to be provided on an hourly basis at the rates noted.
We do not expect there to be any permit fees required for this project since these are existing lift stations
in existing sewered areas. However, should any permits be required, Bolton & Menk will assist the City
in application process and the permit application fees shall be the responsibility of the City.
Thank you for the opportunity to present this proposal. We look forward to working with you and your
staff. If you need any additional information or have any questions on the above, please do not hesitate to
give me a call at (612) 803-5223.
Respectfully submitted,
Bolton & Menk, Inc.
Seth A. Peterson, P.E.
Principal Environmental Engineer
City of Prior Lake
Wilds and Quaker Lift Station Rehab Projects
Task No.Work Task Description
Principle in ChargeProject ManagerProject EngineerDesign TechnicianElectrical EngineerClericalSurvey CrewTotal
Hours Total Cost
1.0 Preliminary Design 4 8 9 0 10 0 46 77 $12,045
2.0 Final Design 10 17 48 24 20 16 0 135 $21,000
3.0 Construction 14 44 80 4 15 16 12 185 $29,050
Total Hours 28 69 137 28 45 32 58 397
Average Hourly Rate $235.00 $170.00 $145.00 $140.00 $200.00 $90.00 $140.00
Subtotal $6,580 $11,730 $19,865 $3,920 $9,000 $2,880 $8,120
$62,095Total Not-to-Exceed Fee
Bolton & Menk, Inc.