HomeMy WebLinkAbout05(D) - Approval of the Downtown South- Memorandum of Agreement with PLSLWD Report
1
MEMORANDUM of AGREEMENT
Prior Lake-Spring Lake Watershed District and City of Prior Lake
Stormwater Volume Management for Fish Point Road Reconstruction
and Prior Lake Downtown South Roadway Reconstruction Projects
(PLSLWD Permit Nos. 21.01, 22.01)
This Memorandum of Agreement (MOA) is entered into by the Prior Lake-Spring Lake Watershed
District, a Minnesota political subdivision with purposes and powers set forth at Minnesota Statutes
chapters 103B and 103D (PLSLWD) and the City of Prior Lake, a Minnesota municipal corporation ("Prior
Lake") (together, the "Parties").
A. For the protection of water resources within its boundaries, pursuant to Minnesota Statutes
§§103D.341 and 103D.345, the PLSLWD has adopted and implements rules requiring permits for land
disturbing activities. The rules require, among other things, that the permittee provide for and maintain
stormwater volume management practices to prevent impact from increased stormwater volume
resulting from hard surface contruction.
B. Prior Lake has received PLSLWD permits for the Fish Point Road Reconstruction Project (Permit No.
21.01) and the Prior Lake Downtown South Roadway Reconstruction Project (Permit No. 22.01). In each
case, Prior Lake has determined, and the PLSLWD has concurred, that volume management practices
could not feasibly be incorporated into the work, and Prior Lake has assumed the obliigation to provide
such practices independently.
C. On March 1, 2021, the Parties entered into a memorandum of agreement by which Prior Lake
committed to provide volume management practices associated with Permit No. 21.01 ("Fish Point
MOA"). Its outstanding obligation under the Fish Point MOA is to provide 1,905 cubic feet of volume
management. On March 8, 2022, the PLSLWD Board of Managers approved Permit No. 22.01,
conditioned on the Parties' entering into a new, superseding memorandum of agreement by which Prior
Lake would provide for the 1,905 cubic feet of stormwater volume associated with Permit No. 21.01 and
an additional 8,554 cubic feet of stormwater volume associated with Permit No. 22.01. This MOA is for
the purpose of fulfilling this condition of Permit No. 22.01.
WHEREFORE the Parties agree as follows, intending to be legally bound:
1. Within 24 months from the effective date of this MOA, at its cost, Prior Lake will provide for one or
more volume management practices affording a total of 10,459 cubic feet of stormwater volume
management to be substantially complete and functional. Prior Lake will complete the practice or
practices promptly thereafter. The practice or practices will:
a. Capture stormwater within the direct drainage area to Prior Lake-Spring Lake.
b. Provide for stormwater abstraction, or otherwise supply excess volume conforming to the
volume conversion factor set forth in the current PLSLWD stormwater management rule.
2
c. Conform to sound engineering design principles and, specifically, to design and freeboard
requirements set forth in the current PLSLWD stormwater management rule.
d. Be sited so that Prior Lake, by fee interest or easement of record, has perpetual access for
inspection and maintenance staging.
The "current" rule, as used here, means the rule in effect at the time Prior Lake completes the 60
percent design.
2. With respect to each practice, Prior Lake will supply the PLSLWD with the feasibility assessment, 60
percent design and 90 percent design for the review and concurrence of the PLSLWD Administrator at
each stage. Within three months after a practice is substantially complete, Prior Lake will provide to the
PLSLWD record drawings prepared by a professional engineer.
3. Prior Lake will maintain the practice in perpetuity in accordance with the inspection and maintenance
requirements of Prior Lake's NPDES MS4 permit. The PLSLWD may enforce those requirements with
respect to the practice or practices subject to this MOA.
4. Prior Lake may be credited for any volume resulting from the practice or practices installed or
constructed under this MOA that exceeds the volume required by this MOA. The amount to be credited
will be as determined by the PLSLWD on the basis of the submitted record drawings. Credit use will be
as the PLSLWD stormwater rule provides at the time that Prior Lake seeks to use the credit.
5. If Prior Lake has not met its obligation under paragraph 1, above, it will, or at any time before the
indicated deadline it may, in place of that obligation pay into the stormwater impact fund maintained by
the PLSLWD under its stormwater rule, in the amount specified by the schedule in place at the time of
payment.
6. PLSLWD concurrence in the design of a practice under this MOA is solely for the purpose of
determining, in its judgment and discretion, that the practice will allow Prior Lake to meet the
requirements of the PLSLWD rule. In performing this role, the PLSLWD makes no representation or
warranty to Prior Lake or any third party as to the adequacy or fitness of the design. Nothing in this
agreement waives or limits any immunity, defense or liability limit that Prior Lake or the PLSLWD enjoys
as a matter of law, with respect to the other party and any third party.
7. The effective date of this MOA is the date is was signed by the Parties. The MOA terminates when the
PLSLWD has confirmed, in writing, the volume provided by Prior Lake to meet paragraph 1, above, and
any volume credit under paragraph 4, or when Prior Lake has made payment under paragraph 5.
Paragraphs 3, 4 and 6 will survive termination. The Fish Point MOA hereby is superseded and no longer
of effect.
8. The above recitals are incorporated into this MOA, which incorporates and supersedes all prior
negotiations, representations or agreements between the Parties, oral or written, concerning Prior
Lake's obligation to provide volume management practices under Permit Nos. 21.01 and 22.01.
3
IN WITNESS THEREOF, the Parties, intending to be legally bound, have caused this Agreement to be
executed by their duly authorized officials.
PRIOR LAKE-SPRING LAKE WATERSHED DISTRICT
Mike Myser, Board President Date
CITY OF PRIOR LAKE
Kirt Briggs, Mayor Date