HomeMy WebLinkAbout02 27 2023 CCWS TH 13 Trail Planning Analysis UpdateTH 13 Trail Planning Analysis Update
February 22, 2023
1
1
Background
Park and Trail System Plan (2020) identified Citywide trail gaps and the estimated costs to construct
2020 estimate to construct this 2.9-mile segment along TH 13 was $9.19M
2
2
TH 13 Trail Planning Analysis Scope
Identify Alignment Alternatives
Evaluate aerial utility conflicts within the TH 13 ROW
Engage partner agencies
Solicit public input on the alternatives
Identify potential funding opportunities
3
3
Option 1
4
4
5
5
6
6
7
7
8
8
9
9
10
10
Option 2
11
11
12
12
13
13
14
14
15
15
16
16
Alternative Comparisons
17
17
Total Project Cost Estimates
18
18
Decision Matrix
19
19
Next Steps
Receive feedback from the Council
Continue to work with MnDOT to evaluate an option for an on-street, barrier-separated trail at the northerly end of the corridor
Seek public input
Identify a preferred alternative
Identify potential funding options