HomeMy WebLinkAbout05(K) - Resolution Approving a Work Order and Authorize Budget Amendment – Water Quality Credit Pond Project ReportK:\018998-000\Admin\Docs\018998-000 PL Subwatershed Assessment Report.docx
701
XENIA AVENUE S | SUITE 300 | MINNEAPOLIS, MN | 55416 | 763.541.4800 |
WSBENG.COM Memorandum To:
Pete Young, PE,
Water Resources Engineer, City
of Prior Lake From: Jake Newhall,
PE Laura Pietila, EIT Date:
April
22, 2022 Re: Prior Lake Subwatershed Assessment Report WSB Project No. 018998-000 PURPOSE The
City of Prior Lake recently hired WSB to complete a subwatershed assessment of areas
tributary to Prior Lake. This study focuses on stormwater management and surface water quality
within the Upper Prior Lake and Lower Prior Lake watersheds and provides
the
following: An analysis of potential best management practice (BMP) locations on
City -owned parcels. A quantification of the pollutant load reduction for each potential BMP.
A quantification of the volume credits that may
be received for each potential BMP. A decision matrix to compare the potential BMPs. A
recommendation for the installation of one to three BMPs that will result
in stormwater management credits and can be used towards
meeting Prior Lake Spring Lake Watershed District (
PLSLWD) and National Pollutant Discharge Elimination System NPDES) permit requirements for future City projects.
Of particular concern are achievable volume control credits to be used towards meeting PLSLWD rules and
the total phosphorus (TP) loading to Prior Lake, the limiting
nutrient responsible for
the loss of water quality and algae growth in urban lakes. EXISTING WATERSHED CONDITIONS Prior Lake is
one of the most popular water resources in the seven-county metropolitan area of Minneapolis
and attracts thousands of people each year. Both Upper and Lower Prior Lake have been placed
on the impaired waters list for mercury. Upper Prior Lake is also impaired for nutrients.
Improving these resources is important for ecosystem health and is a high priority for the City
of Prior Lake. Installing or enhancing BMPs to reduce pollutants within
the
waterbody’s tributary areas is a step towards improving these important water resources. METHODOLOGY The
Prior Lake subwatershed assessment focuses on areas that are tributary to Upper and Lower
Prior Lakes. To identify potential BMP locations within the study area, a multistep desktop
analysis was completed using ArcGIS Pro, the XPSWMM City-wide model, knowledge of the watershed, and
City input. BMP retrofits or new BMPs were then located and sized to estimate and
maximize pollutant removal. Analysis was performed with the aid of P8,
a commonly used modeling software that evaluates the removal of various pollutants (suspended sediment,
Prior Lake Subwatershed Assessment Report
April 22, 2022
Page 2
removal device (i.e., BMP). The achievable volume credit was then calculated for each proposed
BMP.
Potential BMP Location Analysis
It was assumed that any potential BMPs would be located on City-owned parcels Figure 1, as
attached. Each parcel within the study area was visually reviewed to determine the total tributary
area, the extent of the untreated impervious area, and the location of existing BMPs. Based on
the findings, each parcel was ranked as having low, moderate, or high treatment potential based
on the untreated impervious area draining to the parcel, as shown on Figure 2, as attached. A
technical analysis was completed for the moderate and high ranked parcels to determine the
most promising BMP locations and suitable types. Factors that influence the location and type of
BMP include total drainage area to a specific point, how much untreated impervious area is within
the watershed, land slope, hydrologic soil group (SSURGO Soils), groundwater table depth
Minnesota Hydrogeology Atlas), wetlands (National Wetland Inventory), floodplains (FEMA),
drinking water management areas, and biodiversity significance. See Figure 3a and Figure 3b,
as attached, for the BMP sites that were selected based on the technical analysis.
Pollutant Removal Estimates - P8 Modeling
Utilizing P8 version 3.5, existing and proposed water quality models were built for each potential
BMP location and type. All major basins downstream of the potential BMPs were included in the
P8 models to adequately determine pollutant load reductions at the outfalls to Upper and Lower
Prior Lake.
To determine the watershed characteristics for the existing conditions P8 model, a drainage area
was delineated, impervious fraction calculated, and a pervious curve number determined from
soil type and land use. The land slope was used to calculate depression storage.
Topographic information (LiDAR), as-built data, and storm sewer database were used to define
the characteristics of the existing basins (ponds, wetlands, minor lakes) and other BMPs.
The proposed BMPs were preliminarily designed to:
Maximize the runoff received, particularly from catchments not routed through other
basins or existing BMPs;
Emphasize infiltration and filtration capabilities (e.g., infiltration basin, filtration bench) to
more effectively remove the pollutants, including the dissolved fraction as much as
possible.
Other assumptions employed in the P8 model development include:
Because of the urban nature of the watersheds, seventy percent of the impervious areas
were assumed to be directly connected and thirty percent indirectly connected.
Impervious runoff coefficient of one
Half of the directly connected impervious classified as swept twice a year
Three decades of precipitation and temperature distributions for Minneapolis and Saint
Paul (from 1986 to 2015)
One inch per hour filtration rate
The type of BMP (filtration or infiltration) was chosen based on SSURGO soil types.
Infiltration basins may be used in lieu of filtration if additional soil borings indicate
favorable conditions.
Prior Lake Subwatershed Assessment Report
April 22, 2022
Page 3
Volume Control Credit
Volume control credits to meet PLSLWD stormwater management rules were calculated for each
proposed BMP based on the total water quality volume multiplied by a conversion factor, outlined
in Table D.3.1 from the PLSLWD draft rules.
The volume control credit directly corresponds to a new and reconstructed or net new impervious
surface area that may be offset by the construction of the proposed BMP. As stated in the
PLSLWD draft rules for public linear projects, “The volume equal to either 0.5 inches of runoff
from all new and reconstructed impervious surfaces, or 1.0 inches of runoff from the net increase
in impervious area, whichever is greater, must be captured and treated.”
RESULTS
Existing total phosphorus loads from each analyzed watershed are displayed on Figure 4, as
attached, showing that the area with the highest loading rate per year is out of the channel on the
south side of Upper Prior Lake, largely due to the size of the watershed.
Furthering the analysis, the existing pollutant loads were compared to the proposed pollutant
loads as determined by the P8 analysis. The benefits provided in terms of pollutant reduction
were then compared against the “costs” including construction challenges, long term
maintenance, and habitat loss. A Best Management Practice Decision Matrix for TP Reduction
was created to summarize the results. Habitat loss, maintenance, constructability challenges, and
costs were rated with 0 (low), -0.5 (moderate), -1 (high), and -2 (exceeds). Adding values for each
BMP across the matrix, a score was determined. Higher scores indicate a better cost-benefit
analysis. Other numerical choices for scaling the benefits versus costs would lead to the same
ranking. Absent a universal method for scaling the BMP’s effectiveness, the goal of the study was
not to develop a perfect scale but to reliably identify the most effective BMPs. Towards this goal,
the matrix developed serves as a robust selection tool.
Prior Lake Subwatershed Assessment Report
April 22, 2022
Page 4
1Primary focus of pollutant removal in treatment structures such as these is TSS. Some particulate phosphorus will also be removed
associated with large particles.
The anticipated volume control credit and associated impervious surface offset that may be
achieved by each of the proposed BMPs are displayed in the Best Management Practice
Decision Matrix for Volume Control Credit. A pre-feasibility level cost estimate is also presented
for each proposed BMP.
Location
Best Management
Practice
TP Pollutant
Reduction at
Outfall to Prior
Lake (lbs/yr)
Habitat Loss Maintenance
Constructability
Challenges
Cost Total Score
Lakefront Park
Iron Enhanced Infiltration
Basin
7.4 -2 -1 -2 -1 1.4
Underground Filtration
Gallery
18.7 0 -2 -1 -2 13.7
Panama and TH 13
Iron Enhanced Filtration
Bench
22.6 -0.5 -1 -0.5 -2 18.6
Boudins Park
Biofiltration Basin 0.3 -1 -0.5 -1 -0.5 -2.7
Eagle Creek Avenue
Iron Enhanced Filtration
Basin
17.7 0 -1 -0.5 -1 15.2
Rutledge Street
V2B1 Treatment Structure 1 1.3 0 -0.5 0 0 0.8
Willows Park
Underground Infiltration
Gallery
2.4 0 -1 -0.5 -2 -1.1
V2B1 Treatment Structure 1 6.3 0 -0.5 0 0 5.8
Best Management Practice Decision Matrix for TP Reduction
Sand Point Park
Location
Best Management
Practice
Volume Control
Credit1
cf)
Area of New and
Reconstructed
Impervious Surface
Offset2
ac)
Area of Net New
Impervious
Surface Offset 3
ac)
Estimated Cost4
Lakefront Park
Iron Enhanced Infiltration
Basin
28,701 15.81 7.91 $ 372,200
Underground Filtration
Gallery
32,966 18.16 9.08 $ 559,610
Panama and TH 13
Iron Enhanced Filtration
Bench
113,247 62.40 31.20 $ 857,560
Boudins Park
Biofiltration Basin 9,032 4.98 2.49 $ 107,400
Eagle Creek Avenue
Iron Enhanced Filtration
Basin
24,627 13.57 6.78 $ 306,880
Rutledge Street
V2B1 Treatment Structure 152 0.08 0.04 $ 59,500
Willows Park
Underground Infiltration
Gallery
18,113 9.98 4.99 $ 426,070
Sand Point Park
V2B1 Treatment Structure 152 0.08 0.04 $ 59,500
1
2
3
4
Best Management Practice Decision Matrix for Volume Control Credit
Impervious offset for a project where 0.5 inches of runoff from all new and reconstructed impervious surfaces
must be captured.
Impervious offset for a project where 1.0 inches of runoff from the net increase in impervious area must be
captured and treated.
Volume Conversion Factor applied based on BMP type and PLSLWD Table D.3.1
Pre-feasibility level cost estimate based on subwatershed assessment assumptions.
Prior Lake Subwatershed Assessment Report
April 22, 2022
Page 5
Site summaries are included below.
Lakefront Park Figure 5, as attached.
o Analysis showed that a significant amount of phosphorus reduction is achieved
via constructed basins and Little Prior Lake. However, additional treatment
options include an iron enhanced infiltration basin downstream of Little Prior Lake
or an active underground filter system used to treat Little Prior Lake stormwater
via a pump system.
The iron enhanced infiltration basin would likely result in significant
tree/habitat loss. Access to the area, for construction and long-term
maintenance, would be challenging due to steep slopes and trees.
Phosphorus reduction to Prior Lake is average. The basin has a large
volume credit potential because of the possible BMP footprint.
The Lakefront Park Master Plan indicates several locations that may be
suitable for the construction of an underground filtration chamber system:
under the expanded parking lot or near the potential amphitheater
location. Although pumping water from Little Prior Lake to Lakefront Park
may add cost, there is a significant amount of pollutant removal and
volume credit potential. The BMP was modeled to pump 2-feet of water
from Little Prior Lake through the filtration gallery (modeled as
StormTech MC-3500 chamber) annually. The lake water was assumed
to have a phosphorus concentration of 0.3 milligrams per liter. The
project will necessitate permits for pumping out of a public waterbody.
Pump and force main installation may present construction challenges
and long-term maintenance costs.
Panama Avenue and Trunk Highway 13 Figure 6, as attached.
o Based on City input and a site analysis, enhancing the existing pond near
Panama Avenue and Trunk Highway 13 with an iron enhanced filter bench was
considered. The improvement could result in a significant pollutant reduction and
volume credit. From historic aerials, it appears that the pond was constructed
between 1957 and 1992. XPSWMM modeling indicates that there are potential
flooding issues in the area.
Boudins Park Figure 7, as attached.
o Boudins Park receives thirty-four acres of runoff with eleven acres of impervious
area. An existing basin and underground treatment chamber provides 10,100
cubic feet of water quality volume. To sufficiently treat all of the impervious area
to NPDES and City standards, 39,749 cubic feet of water quality volume must be
provided. The direct drainage to the existing filtration basin is fully treated as well
as a portion of the drainage from the west. To fully treat the western drainage
area, 29,649 cubic feet of additional water quality volume must be provided. The
site lacks the area to construct a sufficiently sized basin. As such, limited
pollutant reduction benefits and volume control credits would be gleaned from
constructing a BMP in the area. The City may wish to investigate the functionality
of the existing underground treatment chamber to determine if an updated
chamber design would better treat the area.
Eagle Creek Avenue Figure 8, as attached.
o The City owned parcel adjacent to Eagle Creek Avenue, upstream of Lower Prior
Lake and north of Quincy Street, was identified in the site analysis because of
the ability to capture drainage from a large untreated impervious area (thirty-
seven acre drainage area of which eighteen acres are impervious) that currently
Prior Lake Subwatershed Assessment Report
April 22, 2022
Page 6
discharges through the Eagle Creek storm sewer directly into Upper Prior Lake.
The key elements of an effective BMP involve diverting the flow from the existing
storm sewer along Eagle Creek Avenue into an iron enhanced filtration basin
above the ordinary high water level of Upper and Lower Prior Lakes. Under these
assumptions, P8 modeling confirmed that treatment of the impervious could
significantly reduce pollutant loads to Prior Lake. Moderate volume control credits
could be achieved, limited by the proposed basin size. A pretreatment structure
e.g., SAFL Baffle and sump) would be recommended for retention and periodical
removal of the bulk of the sediment in order to reduce the long-term maintenance
costs of efforts associated with the filtration area. Because Eagle Creek Avenue
is a county road, coordination with the County would be required. Utilities may
need to be relocated or avoided.
Rutledge Street Figure 9, as attached.
o The storm sewer on Rutledge Street contributes untreated stormwater directly to
Lower Prior Lake. Although a filtration basin would provide the most pollutant
reduction, the slopes adjacent to the roadway are very steep and prohibitive to
basin construction. A V2B1 or similar treatment structure may be installed along
the trunkline storm sewer. A V2B1 or similar structure primarily focuses on
removal of total suspended solids. Some particulate phosphorus will also be
removed associated with large particles. A treatment structure would provide a
minimal amount of volume control credits.
Willows Park Figure 10, as attached.
o Willows Park was identified in the site analysis as a potential location for a BMP
based on the adjacent untreated impervious area and favorable conditions for
infiltration. Further analysis of an underground chamber system (modeled as
StormTech MC-3500 chamber) proved that the overall benefit to Prior Lake
would be small as there are three BMPs, a wetland, and a channel prior to
discharging to the lake. However, the volume credit potential offered by the BMP
is moderate.
Sand Point Park Figure 11, as attached.
o A significant amount of untreated impervious area enters Prior Lake south of
Sand Point Park. A diversion pipe was recently installed from Birchwood Avenue
to Sandpoint Beach, treating a portion of the drainage area, but P8 modeling
shows that there would be additional benefits to treating more of the area. A BMP
cannot be located within the park itself due to elevation and access constraints.
To treat the stormwater, a V2B1 treatment structure or similar could be installed
within the right of way at the intersection of Birchwood Avenue and Shady Beach
Trail. A V2B1 or similar structure primarily focuses on removal of total suspended
solids. Some particulate phosphorus will also be removed associated with large
particles. A treatment structure would provide a minimal amount of volume
control credits.
During the analysis, several additional best management practice options were discussed and
considered. It is important to note that quantification of credits for these improvements would be
difficult, but each may present water quality benefits.
Investigate the condition of the channel that flows from the wetland complex near
Priorwood Street and Five Hawks Drive to Upper Prior Lake. Install stabilization
measures if conditions warrant it.
Treat Little Prior Lake with annual or routine alum dosage.
Prior Lake Subwatershed Assessment Report
April 22, 2022
Page 7
Emmons and Olivier Resources, Inc. completed a retrofit feasibility study for Prior Lake Spring
Lake Watershed District in 2021. The City could consider partnering with the watershed district to
construct four curbside rain gardens and up to three iron-enhanced sand filter benches alongside
existing stormwater ponds adjacent to Trunk Highway 13. Combined, the retrofit projects are
estimated to remove 7.1 pounds of phosphorus per year.
RECOMMENDATION
Based on the analysis, one BMP stands out as most effective for total phosphorus reduction as
well as achievable volume control credits with reasonable secondary factors: the addition of an
iron enhanced filter bench to the existing pond near Panama Avenue and Trunk Highway 13.
Construction of an underground filtration gallery in Lakefront Park or an iron enhanced filtration
basin adjacent to Eagle Creek Avenue should also be considered for the significant total
phosphorus removal and volume control credit potential.
MUSHTOWNRDSEDULUTHAVESECREEKSIDECIRSEFIVE
HAWKS AVE SEV ILLA G EL A K E D
R
S E W ILL O W W O O D S
T S E H E R I T A G
E L N SET O W E R S
T S E P ONDVIEW
TRL SEMAPLEWOOD ST
SEANNA
TRL
SE23
Scott
County
GIS
16
27
12
83
42
44
17 82 18 78 14 21 This product is for informational purposes and is not
suitable for legal, engineering, or surveying purposes. This product has been produced by the City of Prior
Lake for the sole purpose of geographic reference. No warranty is made by the City
of Prior
Lake regarding specific accuracy or completeness.0 0.04
0.
09 0.1 0.2
Miles Water Quality Credit
Pond Project Council
Page 1 of 2
Public Works Consultant Pool Work Order
Water Quality Credit Pond Project
WSB & ASSOCIATES, INCORPORATED, dba WSB
This work order (“Work Order”) is issued on this 20th day of March, 2023 by the City of Prior
Lake (“City”) pursuant to the Public Works Consultant Pool – Master Agreement dated April
20, 2020 (“Contract”) between the City and WSB & Associates, Incorporated, dba WSB
Consultant”).
Based on the mutual promises and covenants set forth herein, the sufficiency of which are
hereby acknowledged, the City and Consultant agree as follows:
1.Scope of Work Order. Consultant agrees to provide, perform and complete all the services
requested by the City in this Work Order and attached Exhibit 1 (“Work”), which Work shall
be subject to the terms and conditions of this Work Order and the Contract.
2.Term of Work Order. All Work requested by this Work Order shall be completed by
December 31, 2024.
3.Compensation for Work Order. City agrees to pay the Consultant an hourly, not-to-
exceed sum of $69,400.00 as full and complete payment for the Work requested by this
Work Order.
4.Consultant Representative. Consultant has designated Jake Newhall to manage the Work
Order subject to the supervision of Consultant’s representative.
ISSUED BY CITY OF PRIOR LAKE
Mayor
City Manager
RECEIVED AND ACCEPTED BY WSB &
ASSOCIATES, INC.
Signature
Title
Page 2 of 2
Exhibit 1 – Scope of Work Order
G:\Group Data\WATER RESOURCES\WR Proposal Folder\Prior Lake\LTR PROP-p young_Panama&13_010623.docx
701 XENIA AVENUE
S | SUITE
300 | MINNEAPOLIS, MN |
55416 | 763.541.4800 |
WSBENG.COM January 6,
2023 Pete Young Water
Resources Engineer City of Prior Lake 4646 Dakota Street SE Prior Lake, MN
55372 Re: Proposal to Provide
Final Design and Construction Pond
Water Quality Retrofits
at Panama Avenue and Highway 13 City of Prior Lake, MN Dear Mr. Young: Attached for
your review and approval is our proposed scope of services, fee, and schedule
for providing professional engineering services to complete the final design and construction for the BMP retrofits to the
pond located at Panama Avenue and Highway 13. The goal of this project is
to improve water quality treatment provided upstream of Lower Prior Lake
consistent with the recently completed Prior Lake Subwatershed Assessment. Water quality benefits (credits) from this project
will be used to offset past and
future watershed permitting needs for City projects where stormwater management cannot be feasibly achieved. We are excited to continue
to work with you on this project. If you are in agreement with
this proposal, please sign where indicated below and return one copy. The necessary contract documents will then
be provided. WSB will start work upon receipt of a signed contract.
Please
do
not hesitate to
contact Jake at 612-
990-
3576 with
any questions. Sincerely, WSB Jake
Newhall,
PE
Director
Mr. Pete Young
January 6, 2023
Page 2
SCOPE OF ENGINEERING SERVICES
FOR
POND WATER QUALITY RETROFITS AT PANAMA AVENUE AND HIGHWAY 13
FINAL DESIGN & CONSTRUCTION
FOR THE CITY OF PRIOR LAKE
SCOPE OF ENGINEERING SERVICES
This work plan consists of the final design and construction tasks for the Pond Retrofit Project at
Panama Avenue and Highway 13 in the City of Prior Lake. The following are the tasks that will be
included:
Task 1 – Project Management ($6,800)
Project management will be performed throughout the course of the project. The following
subtasks are included as part of Project Management:
1.1 Attend project update meetings with City staff to discuss draft plans, final plans, cost
estimates, bidding, and other project variables. This will include developing agendas,
preparing handouts and graphics, and attending meetings.
1.2 Attend watershed meetings to discuss water quality benefits and credit/debit
balances and allocations. This will include developing agendas, preparing handouts
and graphics, and attending meetings.
1.3 Work with project team and the City to coordinate project deliverables, schedule, and
budget.
Deliverables: Two (2) meetings with City staff to review draft plans and final plans. Two (2)
meetings with the watershed to discuss proposed and final water quality benefits.
Task 2 – Collect Background Info ($6,200)
This task consists of collecting background data and relevant design information for the project.
The following are the subtasks that will be included as part of the evaluation:
2.1 Collect background information including: easement information, storm sewer sizes
and elevations, soils information, utility information, existing hydrologic modeling for
the area, groundwater information, permitting requirements, and other relevant
information.
2.2 Topographic survey and bathymetric survey of the pond area will be performed by
WSB. This will include surveying property lines, storm sewer, outlet structure, trees,
and other items within the anticipated construction limits.
It is important to note that this task does not include geotechnical analysis as it is not anticipated
to be needed. If it is determined that a geotechnical investigation is needed this can be provided
as an additional service.
Deliverables: Topographic Survey Information.
Task 3 –Permit Coordination ($4,500)
This task consists of coordinating and obtaining the required permits for the project. It is
anticipated that a Prior Lake Spring Lake Watershed Permit will be needed in addition to the
Mr. Pete Young
January 6, 2023
Page 3
water quality benefit coordination. It is anticipated that US Army Corps of Engineers permitting
will be required based on experience with similar projects. In addition, WSB will coordinate the
necessary Wetland Conservation Act (WCA) no-loss and exemption application.
3.1 Wetland Delineation and Report.
3.2 US Army Corps of Engineers permitting.
3.3 WCA permitting.
Deliverables: Agency Coordination Meeting, necessary permitting documentation for the US
Army Corps of Engineers and WCA. This task does not include any necessary permit application
fees; these will be passed on to the City if applicable. Wetland delineation is not anticipated to be
needed.
Task 4 – Water Quality Modeling ($9,800)
WSB will complete water quality and H&H modeling to help develop and inform the most effective
final design components for the pond retrofit project. Existing P8 and XPSWMM will be utilized to
complete these analyses. A cost benefit analysis will be completed to help determine the optimal
design from a total phosphorus standpoint and while also considering construction and ongoing
maintenance costs.
Task 5 – Construction Documents ($24,600)
This task consists of completing construction plans, specifications, and bidding documents for the
Pond Retrofit Project at Panama Avenue and Highway 13. Plans are anticipated to include cover
sheet, grading plan, erosion control/restoration, storm sewer plan, and details. An updated cost
estimate will be developed to verify consistency between the proposed improvements and the
City project budget.
This scope assumes answering questions during the bid process to help facilitate the
understanding of construction expectations.
5.1 Prepare draft construction plans, specification, and updated cost estimate.
5.2 Finalize construction plans, specification, and bidding documents based on feedback
from City staff.
Deliverables: Final Plans, Specifications, and Bid Documents.
Task 6 – Construction Management ($17,500)
Construction management will be performed throughout the course of the construction schedule
for the Pond Retrofit Project at Panama Avenue and Highway 13. This will include attending the
pre-construction meeting as well as weekly progress meetings throughout the project, and other
necessary construction coordination.
This task will include part-time observation (approximately 15-20 hours per week). This will
include inspection of all critical construction components as well as regular check -ins with the
contractor and the City. WSB will also perform the necessary construction staking and survey
work. This includes any necessary survey for record drawings.
6.1 Attend weekly construction meetings.
6.2 Part-time construction observation.
6.3 Review and approve pay vouchers.
6.4 Construction staking and record drawings.
Mr. Pete Young
January 6, 2023
Page 4
Deliverables: Construction Meetings, Construction Observation, Construction Staking, Record
Drawings.
TOTAL ESTIMATED ENGINEERING FEE
The cost to provide the scope of services outlined in this proposal will be billed hourly, based on
our current hourly rates. We are proposing to complete the Pond Retrofit Project at Panama
Avenue and Highway 13 for an hourly not-to-exceed fee of $69,400.
TIME SCHEDULE
Based on the current project schedule, WSB proposes to complete the construction documents
by September of 2023 to allow for bidding in the fall and construction in the winter of 2023.