HomeMy WebLinkAbout09(B)- Waters Edge Marina Temporary Dock Extension PresentationWaters Edge Marina
Temporary Dock Extension
Prior Lake City Council
April 17, 2023
1
Located in Boudins Bay
DNR permit for a permanent floating dock
100’ wide at the end of a 343’ x 44’ dock
50 slips
2
General Location Map
2
CC approved a motion authorizing a temporary 48’ extension to the Waters Edge Marina dock
2022 boating season only
Due to low water levels (900.2’ at the time) the slips closest to the shoreline did not have adequate depth
Extension allowed the docks to be pushed further in the bay
48’ approved; property owners only extended the dock 36’ in 2022
3
May 2, 2022 Request
3
Property owners requested approval of permanent 48’ dock extension, or
Extend temporary authorization for 48’ dock extension in 2023
Both requests were denied
CC indicated the temporary dock extension request for 2023 was premature until spring lake levels were known
4
November 7, 2022 Request
4
Request to extend temporary authorization for 48’ dock extension in 2023
No additional slips are requested
Prior Lake water elevation (903.9’ OHW)
897.79’ as of 11/22/22
899.11’ as of 4/6/23 (+1.32’ since Nov. 22)
899.92 as of 4/17/23 (+0.81’ since 4/6/23)
5
April 17, 2023 Request
5
If approved, the resolution states,
In future years, the Prior Lake Community Development Director is authorized to administratively approve this temporary 48-foot extension for individual boating seasons in the event
the elevation of Prior Lake is 901 feet or less as of October 15th of the prior year
6
Resolution
6