HomeMy WebLinkAbout23-078 Work Order for the 2023 Lift Station Rehabilitation Project
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 23-78
APPROVAL OF WORK ORDER FOR THE 2023 LIFT STATION REHABILITATION PROJECT
Motion By: Braid Second By: Lake
WHEREAS, the City operates 41 sanitary sewer lift stations which are generally
recommended for rehabilitation every 15-20 years; and
WHEREAS, the Estate lift station is 50 years old and was last rehabilitated in 2002; and
WHEREAS, the Lords lift station is 47 years old and was last rehabilitated in 2003; and
WHEREAS, the 150th Street lift station is 50 years old and was last rehabilitated in 2003;
and
WHEREAS, a significant amount of work is needed at these sites to upgrade the pumps
and components in order to continue providing the level of service that is
necessary in our system; and
WHEREAS, WSB (a member of the City’s consultant pool) has provided a scope and
estimate for the design and construction administration for the 2023 lift station
rehabilitation project; and
WHEREAS, funding has been budgeted in the Sewer Utility Fund to cover the anticipated
expenditure of this project.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City Council approves a work order with WSB in an amount not to exceed $113,323 for
the design and construction administration of the 2023 lift station rehabilitation project.
3. The Sewer Utility Fund includes funding for this project.
Passed and adopted by the Prior Lake City Council this day of May 15, 2023.
VOTE Briggs Braid Burkart Churchill Lake
Aye ☒ ☒ ☒ ☒ ☒
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☐ ☐ ☐
______________________________
Jason Wedel, City Manager