HomeMy WebLinkAbout05(F) - Resolution Receiving Bids and Awarding the Contract for the Downtown Parking Lot Reconstruction Project (2025-13) Report ITEM: 5F CITY COUNCIL AGENDA REPORT MEETING DATE: August 12, 2025 PREPARED BY: Stephanie Thulien, Project Engineer- Stormwater PRESENTED BY: Nick Monserud, Public Works Director/City Engineer AGENDA ITEM: Resolution Receiving Bids and Awarding the Contract for the Downtown Parking Lot Reconstruction Project (2025-13) RECOMMENDED ACTION: Adopt a resolution receiving bids and awarding the contract for the Downtown Parking Lot Reconstruction Project (2025-13). BACKGROUND: The 2025 Facilities CIP (F440) includes $300,000 for the rehabilitation of the public parking areas surrounding the Library and Club Prior, as shown below: This proposed project includes the following improvements: • full-depth reclamation of existing pavement and repaving • spot curb and gutter repair • inspection and repair of catch basins as needed • new pavement markings (striping) City of Prior Lake | 4646 Dakota Street SE | Prior Lake MN 55372 Item 5F Page | 2 A work order with WSB LLC was approved by the City Council on May 13, 2025 to provide engineering services for this project. These services include administering the bidding process. The following bids were received and read publicly on July 29, 2025: Contractor Bid Prior Lake Blacktop, Inc. $242,260.78 Northwest $259,990.41 Bituminous Roadways, Inc. $263,315.50 Asphalt Specialties Company $280,190.50 GMH Asphalt Corperation $319,989.55 Urban Companies $370,605.25 The low bidder is Prior Lake Blacktop, Inc. with a bid of $242,260.78. This is 7.95% higher than the engineer’s estimate of $224,408 due to higher-than-expected material costs. WSB has provided the attached recommendation letter to award the contract to Prior Lake Blacktop, Inc. FINANCIAL IMPACT: The total project cost estimate is $341,103.18 which includes construction and overhead costs. The project will be funded using $300,000 from the 2025 Facilities CIP. The remaining $41,103.18 will be funded by the Streets Operating Budget and Stormwater Utility Fund. ALTERNATIVES: 1. Motion and second as part of the consent agenda to adopt a resolution receiving bids and awarding a contract for the Downtown Parking Lot Reconstruction Project (2025- 13). 2. Motion and second to remove this item from the consent agenda for further discussion. ATTACHMENTS: 1. Resolution 2. Recommendation Letter 4646 Dakota Street SE Prior Lake, MN 55372 RESOLUTION 25- A RESOLUTION RECEIVING BIDS AND AWARDING THE CONTRACT FOR THE DOWNTOWN PARKING LOT RECONSTRUCTION PROJECT (2025-13) Motion By: Second By: WHEREAS, pursuant to Resolution 25-061, adopted on May 13, 2025, the city received plans and specifications for the Downtown Parking Lot Reconstruction Project (2025-13); and WHEREAS, bids were requested on July 8, 2025 and publicly opened on July 29, 2025 at 10:00 a.m.; and WHEREAS, the following bids were received, opened, and tabulated according to law: Contractor Bid Prior Lake Blacktop, Inc. $242,260.78 Northwest $259,990.41 Bituminous Roadways, Inc. $263,315.50 Asphalt Specialties Company $280,190.50 GMH Asphalt Corperation $319,989.55 Urban Companies $370,605.25 and WHEREAS, the city’s consulting engineer, WSB LLC, has provided a recommendation letter to award the contract to the lowest responsible bidder, Prior Lake Blacktop, Inc. in the amount of $242,260.78. NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA as follows: 1. The recitals set forth above are incorporated herein. 2. The bids and tabulation worksheet, a copy of which is attached hereto and incorporated by reference herein, are hereby received. 3. The Mayor and City Manager are hereby authorized to execute a contract with Prior Lake Blacktop Inc. in the amount of $242,260.78. 4. The total cost estimate for this project is $341,103.18 (including overhead) and will be funded from the 2025 CIP, Streets Operating Budget, and Stormwater Utility Fund. th Passed and adopted by the Prior Lake City Council this 12 day of August 2025. VOTE Briggs Braid Churchill Lake Hellier Aye ☐ ☐ ☐ ☐ ☐ Nay ☐ ☐ ☐ ☐ ☐ Abstain ☐ ☐ ☐ ☐ ☐ Absent ☐ ☐ ☐ ☐ ☐ ______________________________ Jason Wedel, City Manager C:\\Users\\hsimon\\AppData\\Local\\Temp\\Report Attachment - 20250812 Receive Bids Award Contract Downtown Parking _673397\\Report Attachment - 20250812 Receive Bids Award Contract Downtown P.docx 2 17 8 E A S T 9 T H S T R E E T | S U I T E 2 0 0 | S T . P A U L , M N | 5 5 1 0 1 | 6 5 1 . 2 8 6 . 8 4 5 0 | W S B E N G . C O M July 29, 2025 Honorable Mayor and City Council City of Prior Lake 4646 Dakota Street SE Prior Lake, MN 55372-1714 Re: Downtown Parking Lot Reconstruction Project City Project No. 2025-13 City of Prior Lake WSB Project No. 030614-000 Dear Mayor and Council Members: Bids were received for the above-referenced project on Tuesday, July 29, 2025, and were opened and read aloud. Six bids were received. The bids were checked for mathematical accuracy. Please find enclosed the bid summary indicating the low bid as submitted by Prior Lake Blacktop, Inc., Prior Lake, Minnesota in the amount of $242,260.78. The Engineer’s Estimate was $224,408.00. We recommend that the City Council consider these bids and award a contract for the base bid in the amount of $242,260.78 to Prior Lake Blacktop, Inc. based on the results of the bids received. Sincerely, WSB Emily Brown, PE Project Manager Attachments cc: jsc