CITY COUNCIL AGENDA REPORT
AUGUST 7,2006
9B
CRAIG ELDRED, STREET AND UTILITIES SUPERVISOR
CONSIDER APPROVAL OF A RESOLUTION ACCEPTING THE BIDS AND
AUTHORIZING THE EXECUTION OF THE CITY'S STANDARDIZED
CONSTRUCTION CONTRACT FOR THE 2006 STREET OVERLAY
PROJECT
Introduction
The purpose of this agenda item is to accept the bids and authorize the Mayor
and City Manager to execute the City's standard construction contract for
street overlays identified in the 2006-2010 Capital Improvement Program (CIP)
and bituminous improvements to Hastings Avenue north of Dakota Street.
Historv
On June 26, 2006, the City Council approved a resolution accepting plans and
authorizing advertisement for bids for the 2006 Overlay I Hastings Avenue
Improvements. Each year the City Council adopts the CIP which involves
funding for various improvement projects, including street overlays. In addition
to the 2006 overlays, staff has been authorized to install a bituminous surface
on Hastings Avenue north of Dakota Street. This work is being done on
Hastings Avenue to coincide with storm drainage improvements completed last
fall to protect erosion of Hastings Avenue onto private property. This erosion
issue has been raised by property owners in this area in past years.
The following street overlays have been identified by staff for construction in
2006:
Route
Basswood Circle
Basswood Circle
Bay Avenue
Elm Avenue
Walnut Avenue
Willow Beach Street
Hastings Avenue
Description
Elm Avenue to end
Walnut Avenue to Elm Avenue
Willow Beach St. to Willow Beach Trl
170th to Willow Beach Trl
170th to Basswood Circle
Willow Beach Trl to Bay Avenue
North of Dakota Street
Staff utilizes a pavement management system for rating the condition of
streets throughout the City. Staff then uses this system as a tool when
identifying areas for maintenance and repair.
Current Circumstances
A request for bids was advertised with bids being due on July 10, 2006. No
bids were received at that time. Subsequently, staff solicited bids from local
R:\Agenda Reports\Aug 7 2006\street overlays accept bids agenda. doc
www.cityofpriorlake.com
Phone 952.447.4230 / Fax 952.447.4245
contractors. Three sealed bids were received and opened on July 24, 2006,
as outlined below:
Overlay - Various
Bit. Impr. - Hastings
Total Project Cost
Chard Tiling
& Excavating
$ 72,898.20
$ 14.164.00
$ 87,062.20
Northwest
Asphalt
$ 73,523.10
$ 11.117.50
$ 84,640.60
Prior Lake
Blacktop
$ 68,947.17
$ 9.738.90
$ 78,686.07
Prior Lake Blacktop was the lowest responsible bidder and meets the selection
criteria.
Conclusion
Staff is recommending awarding the standardized construction contract to the
lowest bidder, Prior Lake Blacktop. The list of streets provided will conclude
the Willows area and provide an excellent wear surface for 10 to 15 years. In
addition to the overlay work, various bituminous repairs will also be made in
the project area. The improvements on Hastings Avenue would provide for
improvements for proper drainage and allow staff to maintain the area through
all seasons. Continued maintenance of our City streets will reduce the need
for costly reconstruction in the near future, therefore reducing costs overall.
FINANCIAL
IMPACT:
The Overlay portion of this project is included in the 2006 budget. The
Hastings Avenue portion of this project was added after budget preparation for
the year. Staff feels that these additional improvements should be done at this
time to eliminate an ongoing erosion problem. Funding is available for the
project as follows:
Funding Source Amount
Repair & Maint. Service - Bituminous Patching $ 12,000.00
Repair & Maint. Service - Street Overlay $ 50,000.00
Repair & Maint. Supplies $ 6,947.17
Water Quality Fund $ 9.738.90
Total Project Funding $ 78,686.07
It should be noted that the 2006 Streets Budget included $100,000 for street
overlay. $50,000 of the budget was dedicated to the overlay of 150th Street
which is part of the 2005 Reconstruction Project (#05-11).
ALTERNATIVES:
1. Approve a resolution accepting the bids and authorizing the execution of
the City's standardized construction contract for the selected street
overlays and improvements to Hastings Avenue.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason and provide staff with direction.
RECOMMENDED
MOTION:
Alternative # 1.
ReViti
Frank Boyl I C anager Steve Albrecht, Public Works Director/City Engineer
R\Agenda ep s\Aug 7 2006\street overlays accept bids agenda.doc
16200 Eagle Creek Avenue S.E.
Prior lake, MN 55372-1714
RESOLUTION 06-xx
A RESOLUTION ACCEPTING THE BIDS AND AUTHORIZING THE EXECUTION OF THE CITY'S
STANDARDIZED CONSTRUCTION CONTRACT FOR THE 2006 STREET OVERLAY PROJECT
Motion By:
Second By:
WHEREAS, The following street overlays have been identified by staff for construction in 2006:
Route
Basswood Circle
Basswood Circle
Bay Avenue
Elm Avenue
Walnut Avenue
Willow Beach Street
Hastings Avenue
Description
Elm Avenue to end
Walnut Avenue to Elm Avenue
Willow Beach St. to Willow Beach Trl
170th to Willow Beach Trl
170th to Basswood Circle
Willow Beach Trl to Bay Avenue
North of Dakota Street
WHEREAS, The City of Prior Lake is committed to improving the streets within the City by providing
continued maintenance; and
WHEREAS, Improved street conditions provide residents the opportunity of safe travel while
commuting on City streets; and
WHEREAS, Continued maintenance of City streets will reduce the need of costly reconstruction in
the near future; and
WHEREAS, Hastings Avenue (alley) also will be paved to reduce erosion and maintenance to
adjacent business; and
WHEREAS, A total of three bids were received for the identified improvement areas, with the low bid
from Prior Lake Blacktop, as follows:
Overlay - Various
Bit. Impr. - Hastings
Total Project Cost
Chard Tiling &
Excavating
$ 72,898.20
$ 14.164.00
$ 87,062.20
Northwest
Asphalt
$ 73,523.10
$ 11.117.50
$ 84,640.60
Prior Lake
Blacktop
$ 68,947.17
$ 9.738.90
$ 78,686.07
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City Council accepts the bids and authorizes the execution of the City's standard construction
contract for the selected street overlays and improvements to Hastings Avenue as identified in the
Capital Improvement Program and modified by the staff report dated June 26,2006.
R:\Agenda Reports\Aug 7 2006\street overlays accept bids resolution.doc
www.cityofpriorlake.com
Phone 952.447.4230 / Fax 952.447.4245
3. The funding for the project shall come from the 2006 Street Budget as follows: Street Overlays
($50,000), Repair and Maintenance Service ($12,000), Repair and Maintenance Supplies
(6,947.17), and from the Water Quality Fund ($9,738.90) in a total amount not to exceed
$78,686.07.
PASSED AND ADOPTED THIS 7TH DAY OF AUGUST 2006.
YES
NO
I Haugen
I Dornbush
I Erickson
I LeMair
I Millar
Haugen
Dornbush
Erickson
LeMair
Millar
Frank Boyles, City Manager
R:\Agenda Reports\Aug 7 2006\street overlays accept bids resolution.doc