HomeMy WebLinkAbout05(B) - Resolution Authorizing a Change Order and Final Payment for the Lords Lift Station Rehabilitation (2025-07) Report
ITEM: 5B
CITY COUNCIL AGENDA REPORT
MEETING DATE: February 10, 2026
PREPARED BY: Christine Watson, Public Works Supervisor – Administration
Phil Ryan, Public Works Supervisor – Utilities
PRESENTED BY: Nick Monserud, Public Works Director/City Engineer
AGENDA ITEM: Resolution Authorizing a Change Order and Final Payment for the
Lords Lift Station Rehabilitation (2025-07)
RECOMMENDED ACTION:
Adopt a resolution authorizing a change order and final payment for the Lords lift station
rehabilitation (2025-07).
BACKGROUND:
On April 22, 2025 the City Council awarded a contract in the amount of $244,401 to Krueger
Excavating, Inc. for the Lords lift station rehabilitation. All work has now been completed in
accordance with the contract.
The project required a change order in the amount of $117,675 to address the following additions
to the scope of the project:
• A new transformer and concrete pad to upgrade the power supply from 240V to 480V
(three phase). This is consistent with what is at other lift stations throughout the city. This
added $27,830 to the project.
• During construction, it was noted that the pump bases were worn and chipped and needed
replacement. This added $10,194 to the project.
• During the design phase of the project, as-built drawings incorrectly showed the force main
to be in the green space of the residence at 4285 Lords St NE, but after initial excavation
it was found that the force main was actually located under the driveway. The replacement
of this sewer force main resulted in needing to replace the homeowner’s concrete
driveway as well. Relocating the force main and replacing the driveway added $79,651 to
the project.
The final payment amount is $139,395.05, which includes the $117,675 change order. With this
payment, the total amount paid to Krueger Excavating, Inc. is $362,076.
The contractor delivered a quality project and has addressed all outstanding work items. WSB
LLC, the city’s engineering consultant on this project, has provided the attached letter
recommending approval of the change order and final pay voucher.
FINANCIAL IMPACT:
The Sewer Utility Fund included $709,000 for lift station rehabilitation in 2025. The total project
cost for equipment, installation, SCADA integration, and all engineering and consultant services
is $478,846 which is 32.6% above the estimated total project cost of $361,171 due to the change
City of Prior Lake | 4646 Dakota Street SE | Prior Lake MN 55372
Item 5B
Page | 2
order additions noted above. The remainder of the budgeted $709,000 will be used on the 150th
Street lift station rehabilitation, which is nearing completion as well.
ALTERNATIVES:
1. Motion and second as part of the consent agenda to adopt a resolution authorizing a
change order and final payment for the Lords lift station rehabilitation (2025-07).
2. Motion and second to remove this item from the consent agenda for further discussion.
ATTACHMENTS:
1. Resolution
2. Change Order
3. Recommendation Letter and Pay App
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 26-
A RESOLUTION AUTHORIZING A CHANGE ORDER AND FINAL PAYMENT FOR THE
LORDS LIFT STATION REHABILITATION (2025-07)
Motion By: Second By:
WHEREAS, on April 22, 2025 the City Council adopted Resolution 25-054 which
authorized the city to award a construction contract to Krueger Excavating,
Inc. for the Lords lift station rehabilitation; and
WHEREAS, the contract outlined the improvements Krueger Excavating, Inc. was
responsible for installing; and
WHEREAS, the scope of the project changed after construction began, adding $117,675 to
the contract through a change order for the following work:
A new transformer and concrete pad to upgrade the power supply from 240
delta to 480 three phase. This is consistent with what is at other lift stations
throughout the city. This added $27,830 to the project.
During construction, it was noted that the pump bases were worn and
chipped and needed replacement. This added $10,194 to the project.
During the design phase of the project, as-built drawings incorrectly
showed the force main to be in the green space of the residence at 4285
Lords St NE, but after initial excavation it was found that the force main
was actually located under the driveway. The replacement of this sewer
force main resulted in needing to replace the homeowner’s concrete
driveway as well. Relocating the force main and replacing the driveway
added $79,651 to the project; and
WHEREAS, these improvements and all other contract responsibilities are now complete to
the satisfaction of the city; and
WHEREAS, the city’s consulting engineer, WSB LLC, has reviewed the improvements and
has written a recommendation letter and provided all close out documentation
to support final payment in the amount of $139,395.05 for this project.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City Council hereby accepts the improvements for the Lords lift station rehabilitation
project.
3. Final payment will be made to Krueger Excavating, Inc. in the amount of $139,395.05.
th
Passed and adopted by the Prior Lake City Council this 10 day of February 2026.
VOTE Briggs Braid Churchill Lake Hellier
Aye
☐ ☐ ☐ ☐ ☐
Nay
☐ ☐ ☐ ☐ ☐
Abstain
☐ ☐ ☐ ☐ ☐
Absent
☐ ☐ ☐ ☐ ☐
______________________________
Jason Wedel, City Manager
C:\\Users\\hsimon\\AppData\\Local\\Temp\\Report Attachment - 20260210 Approve CO and final payment Lords LS - RESO_675688\\Report Attachment - 20260210
Approve CO and final payment Lords LS -.docx 2
LORDS STREET LIFT STATION IMPROVEMENTS
CITY OF PRIOR LAKE
WSB PROJECT NO.: 027183-000
OWNER:
City of Prior Lake
4646 Dakota St SE,
Prior Lake, MN 55372
THE CONTRACT IS MODIFIED AS FOLLOWS UPON EXECUTION OF THIS CHANGE ORDER:
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE: $244,401.00 ORIGINAL CONTRACT TIME: NONE
PREVIOUS CHANGE ORDERS: $0.00 NET CHANGE FROM PREVIOUS CHANGE ORDERS: NONE
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: $244,401.00 CONTRACT TIME PRIOR TO THIS CHANGE ORDER: NONE
NET INCREASE/DECREASE OF THIS CHANGE ORDER:$117,675.00 NET INCREASE OF CHANGE ORDER: NONE
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $362,076.00 CONTRACT TIME WITH APPROVED CHANGE ORDERS:NONE
RECOMMENDED BY: APPROVED BY:
STEVE NELSON, PE, PROJECT MANAGER
WSB
ENGINEER
APPROVED BY:
PRIOR LAKE
DATE
PRIOR LAKE
DATE
Krueger Excavating
7616 180th St E,
Prior Lake, MN 55372
CONTRACTOR
CHANGE ORDER NO. 1
JANUARY 22, 2026
CONTRACTOR SIGNATURE
Krueger Excavating
ATTACHMENTS: SUMMARY OF WORK AND COSTS ASSOCIATED COR #15 - #22.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CONTRACTOR:
DESCRIPTION: THIS CHANGE ORDER INCLUDES ALL ADDITIONAL WORK AND COSTS ASSOCIATED WITH THE FORCEMAIN RELOCATION, RETAINING
WALL, CURB REPLACEMENTS, SEEDING AND GRADING WORK, AND REMOVAL AND REPLACEMENT OF PUMP BASES AS LAID OUT IN THE
ATTACHED DOCUMENTATION WITH DEDUCTIONS FOR THE UNUSED CONSTRUCTION AND TRAFFIC CONTROL ALLOWANCE ($10,000 EACH).
M:\027183-000\Admin\Construction Admin\Pay Apps Lords St LS\CORs & COs\Change Order Summary SheetCO 1
M:\027183-000\Admin\Construction Admin\Pay Apps Lords St LS\Final Pay App (Cover Letter).docx
17
8
E
9
T
H
S
T
R
E
E
T
|
SU
I
T
E
2
0
0
|
SA
I
N
T
P
A
U
L
,
M
N
|
55
1
0
1
|
65
1
.
2
8
6
.
8
4
5
0
|
WS
B
E
N
G
.
C
O
M
January 26, 2026
Mr. Phil Ryan
Public Works Supervisor
City of Prior Lake, MN
4646 Dakota St SE,
Prior Lake, MN 55372
Re: Final Application for Payment No. 2
Lords Street Lift Station Rehabiliation
City of Prior Lake, MN
WSB Project No. 027183-000
Dear Mr. Ryan:
Please find attached Final Application for Payment No. 2 from Krueger Excavating for the
construction of the Lords Street Lift Station Rehabilitation. We reviewed this application and find it
acceptable for payment. Therefore, we recommend making a payment of $139,395.05 to Krueger
Excavating, Inc. If you are in agreement, please sign the application and process it for payment.
Sincerely,
WSB
Steve Nelson
snelson@wsbeng.com
(612) 258-8152
2