RESOLUTION 26-017 A RESOLUTION AUTHORIZING A CHANGE ORDER AND FINAL PAYMENT FOR THE LORDS LIFT STATION REHABILITATION (2025-07) Motion By: Hellier Second By: Churchill
WHEREAS, on April 22, 2025 the City Council adopted Resolution 25-054 which authorized the city to award a construction contract to Krueger Excavating, Inc. for the Lords lift station rehabilitation; and WHEREAS, the contract outlined the improvements Krueger Excavating, Inc. was responsible for installing; and WHEREAS, the scope of the project changed after construction began, adding $117,675 to the contract through a change order for the following work:
• A new transformer and concrete pad to upgrade the power supply from 240
delta to 480 three phase. This is consistent with what is at other lift stations throughout the city. This added $27,830 to the project.
• During construction, it was noted that the pump bases were worn and chipped and needed replacement. This added $10,194 to the project.
• During the design phase of the project, as-built drawings incorrectly
showed the force main to be in the green space of the residence at 4285 Lords St NE, but after initial excavation it was found that the force main
was actually located under the driveway. The replacement of this sewer force main resulted in needing to replace the homeowner’s concrete driveway as well. Relocating the force main and replacing the driveway added $79,651 to the project; and WHEREAS, these improvements and all other contract responsibilities are now complete to the satisfaction of the city; and WHEREAS, the city’s consulting engineer, WSB LLC, has reviewed the improvements and
has written a recommendation letter and provided all close out documentation to support final payment in the amount of $139,395.05 for this project. NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA as follows:
1. The recitals set forth above are incorporated herein. 2. The City Council hereby accepts the improvements for the Lords lift station rehabilitation project. 3. Final payment will be made to Krueger Excavating, Inc. in the amount of $139,395.05.
M:\2- City Clerk\City Council\Resolutions\2026\26-017 Authorizing a Change Order and Final Payment for the Lords Lift Station.docx 2
Passed and adopted by the Prior Lake City Council this 10th day of February 2026. VOTE Briggs Braid Churchill Lake Hellier