Loading...
HomeMy WebLinkAbout26-096 Receiving Quotes and Awarding a Contract for SCADA Fiber Installation 4646 Dakota Street SE Prior Lake, MN 55372 RESOLUTION 26-096 A RESOLUTION RECEIVING QUOTES AND AWARDING A CONTRACT FOR SCADA FIBER INSTALLATION Motion By: Braid Second By: Hellier WHEREAS, the CIP includes $500,000 per year from 2025 - 2029 for SCADA upgrades at all of the City’s wells, lift stations, water storage towers, and the treatment plant; and WHEREAS, one of the critical steps to updating our SCADA infrastructure is to get fiber connections to each location; and WHEREAS, the city is part of the Scott County fiber network and is therefore required to use the vendor designated by the County, Electrical Production Services (EPS), for any expansion of the network; and WHEREAS, staff solicted quotes from EPS to install fiber at three locations – the north water tower, the south water tower, and the Summit booster station. Location Quote North Tower $24,755 South Tower $13,328 Summit Booster Station $24,326 Total $62,409 and WHEREAS, staff recommend awarding a contract to EPS in the amount of $62,409 WHEREAS, funding is available in the 2026 CIP to cover this expenditure (604-49450.00-55580.00). NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA as follows: 1. The recitals set forth above are incorporated herein. 2. The City Council authorizes a contract with Electrical Production Services in the amount of $62,409 for SCADA fiber installation. 3. Funding will come from the 2026 CIP (604-49450.00-55580.00). M:\2- City Clerk\City Council\Resolutions\2026\26-096 Receiving Quotes and Awarding a Contract for SCADA Fiber Installation.docx 2 Passed and adopted by the Prior Lake City Council this 14th day of July 2026. VOTE Briggs Braid Churchill Lake Hellier Aye ☒ ☒ ☒ ☒ ☒ Nay ☐ ☐ ☐ ☐ ☐ Abstain ☐ ☐ ☐ ☐ ☐ Absent ☐ ☐ ☐ ☐ ☐ ______________________________ Jason Wedel, City Manager