HomeMy WebLinkAbout05(K) - Resolution Approving Final Payment for Fire Station 1 Bathroom Remodel Report
ITEM: 5K
CITY COUNCIL AGENDA REPORT
MEETING DATE: July 28, 2026
PREPARED BY: Christine Watson, Public Works Supervisor – Administration
Josh Eppen, Facilities Manager
PRESENTED BY: Nick Monserud, Public Works Director/City Engineer
AGENDA ITEM: Resolution Authorizing Final Payment for the Fire Station 1
Bathroom Remodel Project (2025-11)
RECOMMENDED ACTION:
Adopt a resolution authorizing final payment for the Fire Station 1 bathroom remodel project
(2025-11).
BACKGROUND:
On August 26, 2025 the City Council awarded a contract in the amount of $199,800 to Dering
Pierson Group (Dering) for the Fire Station 1 bathroom remodel project.
All work has now been completed in accordance with the contract. The final payment amount to
Dering is $10,340.82. With this payment, the total amount paid to Dering is $206,816.33, which
is 3.5% above the original contract amount of $199,800. This overage is due to the following
changes to the contract:
• Addition of a backflow prevention check valve to the steam shower
• Reconfiguration of the women’s shower fixture and valve controls
• Addition of blocking in the walls of all shower compartments
Dering delivered a quality project and has addressed all outstanding work items. CNH Architects,
the city’s architectural consultant on this project, has provided the attached letter recommending
final payment be made at this time.
FINANCIAL IMPACT:
The total project cost for the Fire Station 1 bathroom remodel project is $244,816.33 which
includes the $38,000 for the consultant work order. The majority of the fuding for the project
($225,000) came from money that was carried over from the 2024 CIP, and the remaining portion
for the consultant fees were paid from the operating budget (Engineering Professional Services
101-43050.00-53100.80).
ALTERNATIVES:
1. Motion and second as part of the consent agenda to adopt a resolution authorizing final
payment for the Fire Station 1 bathroom remodel project (2025-11).
2. Motion and second to remove this item from the consent agenda for further discussion.
ATTACHMENTS:
1. Resolution
2. Letter of Recommendation & Pay Voucher
City of Prior Lake | 4646 Dakota Street SE | Prior Lake MN 55372
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 26-
A RESOLUTION AUTHORIZING FINAL PAYMENT FOR THE FIRE STATION 1
BATHROOM REMODEL PROJECT (2025-11)
Motion By: Second By:
WHEREAS, on August 26, 2025 the City Council awarded a construction contract in the
amount of $199,800 for the Fire Station 1 bathroom remodel project; and
WHEREAS, the contract outlined the improvements Dering Pierson Group was responsible
for installing; and
WHEREAS, these improvements and all other contract responsibilities are now complete to
the satisfaction of the city; and
WHEREAS, the city’s architectural consultant, CNH Architects, has reviewed the
improvements and has written a recommendation letter and provided all close
out documentation to support final payment for this project.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City Council hereby accepts the improvements for the Fire Station 1 bathroom remodel
project.
3. Final payment will be made to Dering Pierson Group in the amount of $10,340.82.
th
Passed and adopted by the Prior Lake City Council this 28 day of July 2026.
VOTE Briggs Braid Churchill Lake Hellier
Aye
☐ ☐ ☐ ☐ ☐
Nay
☐ ☐ ☐ ☐ ☐
Abstain
☐ ☐ ☐ ☐ ☐
Absent
☐ ☐ ☐ ☐ ☐
______________________________
Jason Wedel, City Manager
7300 WEST 147TH STREET | SUITE 504 | APPLE VALLEY, MN 55124 | 952.431.4433
YOUR SUCCESS IS OUR INSPIRATION. CNH ARCHITECTS 1
MEMORANDUM
PROJECT: Prior Lake Fire Station #1 Remodel
CNH No: 24049
DATE: 07/15/26
TO: City of Prior Lake -Mayor and City Council
SUBJECT: Recommendation for final payment
This is a notification of our recommendation for the release of $10,340.82 in final payment/retainage
monies to the Dering Pierson Group of Rogers Minnesota for construction work and management of the
Prior Lake Fire Station #1 Remodel project based on construction documents prepared by CNH
architects and dated 07/18/2025.
Submitted By:
Jon Vandervelde, PA
CNH Architects, Ltd.
cc: File
Josh Eppen, City of Prior lake
Quinn Hutson, CNH architects
Invoice22401 Industrial Blvd
Rogers, MN 55374
Phone: 612-213-2210
Fax: Date Invoice #
Feb 25,
2026
2756
Bill To Ship To
City of Prior Lake
4646 Dakota Street SE
Prior Lake, MN 55372
Prior Lake Fire Station 1
16776 Fish Point Road Prior
Lake, MN 55372
P.O. No.Terms Due Date Job
30 Days Mar 27, 2026 25035-Prior Lake Fire Station 1 RR Remod
Description Qty Unit Price Amount
Retainage (10,340.82)
Tax 0.00
Total $10,340.82
Tax No.80-0696128
RECEIVED
By CNH Architects on April 22, 2026
$10,340.82
04/22/2026
Dering Pierson Group
22401 Industrial Blvd
Rogers, MN 55374
612-213-2210
City of Prior Lake
APPLICATION AND CERTIFICATE FOR PAYMENT
Job No.: 25035
Job: Prior Lake Fire Station 1 RR Remod
Application No: 3.0
Application Date: Jan 1, 2026
Period To: Jan 31, 2026
CONTRACT
A B C D E F G H I
Work CompletedItem
#Description of Work Scheduled
Value From Previous
Application(s)This Period
Materials
Presently
Stored
Total Completed
and Stored To Date %Balance to
Finish
Retainage
(If Variable
Rate)
01 General Conditions 33,211.40 31,500.00 1,711.40 0.00 33,211.40 100 0.00 1,660.57
02 Demolition Labor 5,600.00 5,600.00 0.00 0.00 5,600.00 100 0.00 280.00
03 Masonry 5,000.00 5,000.00 0.00 0.00 5,000.00 100 0.00 250.00
04 Carpentry Labor 3,735.00 3,000.00 735.00 0.00 3,735.00 100 0.00 186.75
05 Glazing 9,644.00 0.00 9,644.00 0.00 9,644.00 100 0.00 482.20
06 Drywall 5,871.24 5,871.24 0.00 0.00 5,871.24 100 0.00 293.56
07 Tiling 41,733.00 41,733.00 0.00 0.00 41,733.00 100 0.00 2,086.65
08 Ceilings 5,300.00 5,300.00 0.00 0.00 5,300.00 100 0.00 265.00
09 Flooring 250.00 250.00 0.00 0.00 250.00 100 0.00 12.50
10 Painting 2,000.00 500.00 1,500.00 0.00 2,000.00 100 0.00 100.00
11 Bath Partitions 9,677.89 9,677.89 0.00 0.00 9,677.89 100 0.00 483.89
12 Bath Accessories 820.00 820.00 0.00 0.00 820.00 100 0.00 41.00
13 Countertops 750.00 750.00 0.00 0.00 750.00 100 0.00 37.50
14 Plumbing 51,000.00 47,000.00 4,000.00 0.00 51,000.00 100 0.00 2,550.00
15 Electrical 15,122.00 15,122.00 0.00 0.00 15,122.00 100 0.00 756.10
16 OH&P 10,085.47 9,500.00 585.47 0.00 10,085.47 100 0.00 504.27
199,800.00 181,624.13 18,175.87 0.00 199,800.00 100 0.00 9,990.00
ADDITIONS TO CONTRACT
CO-01 Sink Station Panel Add 0.00 0.00 0.00 0.00 0.00 0.00 0.00
CO-02 SI-01 Changes 3,468.54 0.00 3,468.54 0.00 3,468.54 100 0.00 173.43
CO-03 SI-02 Changes 3,547.79 709.56 2,838.23 0.00 3,547.79 100 0.00 177.39
7,016.33 709.56 6,306.77 0.00 7,016.33 100 0.00 350.82
Grand TOTAL:206,816.33 182,333.69 24,482.64 0.00 206,816.33 100 0.00 10,340.82