HomeMy WebLinkAbout05(E) - Resolution Approving a Work Order for Well 10 Design and Construction Administration (2027-03) Report ITEM: 5E CITY COUNCIL AGENDA REPORT MEETING DATE: October 27, 2026 PREPARED BY: Christine Watson, Public Works Supervisor – Administration Phil Ryan, Public Works Supervisor – Utilities PRESENTED BY: Nick Monserud, Public Works Director/City Engineer AGENDA ITEM: Resolution Approving a Work Order for Well 10 Design and Construction Administration (2027-03) RECOMMENDED ACTION: Adopt a resolution approving a work order for Well 10 design and construction administration. BACKGROUND: The City currently operates seven municipal wells for the production of potable water for the Prior Lake community. One of those wells - Well 6 - pumps directly to the Shakopee Mdewakanton Sioux Community (SMSC) water treatment plant where it is combined with SMSC water and made available for distribution to both the SMSC and Prior Lake communities. Prior Lake purchases roughly 300 million gallons of water from the SMSC treatment plant each year to supplement the production from our own treatment plant. The average water demand in the City of Prior Lake over the past five years is 900 million gallons per year. In 2023, water demand exceeded one billion gallons for the first and only time to date. Another municipal well (Well 10) is proposed to be constructed in Prior Lake to accommodate the increased demand that future development will bring as well as maximize the production capacity of the City’s existing water treatment plant located near the intersection of Itasca Avenue SE and Summer Street SE. This new well will be located just ½ mile to the south within the Wilderness Ponds Park property on the southwest corner of Blind Lake Trl SE and Fish Point Rd SE, near Fire Station 1. The need for Well 10 is recommended in both the City’s Comprehensive Plan as well as the Water System Study recently completed by Bolton & Menk, Inc. for the Orderly Annexation Area. AE2S, a member of the City’s consultant pool, has provided a proposal in the amount of $398,300 to provide complete design, bidding administration and construction administration services related to the construction of Well 10 and the associated well house. Full details of their proposal are included in the work order attached herein. Staff recommend approving this work order so the preliminary data-gathering and design work for Well 10 can begin as soon as possible to accommodate the construction of the well and well house in 2028. FINANCIAL IMPACT: The City’s Trunk Fund includes $2,000,000 in 2028 to accommodate the construction of Well 10 and the associated well house. The $398,300 cost of the work order is included in this $2,000,000 estimated project cost. Once AE2S has completed the design phase of the project, an updated project cost will be provided. City of Prior Lake | 4646 Dakota Street SE | Prior Lake MN 55372 Item 5E Page | 2 ALTERNATIVES: 1. Motion and second as part of the consent agenda to adopt a resolution approving a work order for Well 10 design and construction administration. 2. Motion and second to remove this item from the consent agenda for further discussion. ATTACHMENTS: 1. Resolution 2. Work Order with Proposal 4646 Dakota Street SE Prior Lake, MN 55372 RESOLUTION 26- A RESOLUTION APPROVING A WORK ORDER FOR WELL 10 DESIGN AND CONSTRUCTION ADMINISTRATION (2027-03) Motion By: Second By: WHEREAS, the City of Prior Lake currently operates seven municipal wells for the production of potable water for the Prior Lake community; and WHEREAS, one of those wells (Well 6) pumps directly to the Shakopee Mdewakanton Sioux Community (SMSC) treatment plant where it is combined with SMSC water and made available for distribution to both the SMSC and Prior Lake communities; and WHEREAS, Prior Lake purchases roughly 300 million gallons of water from the SMSC treatment plant each year to supplement the production from our own treatment plant, with average annual demand in the city currently at 900 million gallons per year; and WHEREAS, another municpal well (Well 10) is proposed to be constructed in Prior Lake to accommodate the increased demand that future development will bring to the City and to maximize the production capacity of the City’s existing water treatment plant; and WHEREAS, AE2S, a member of the City’s consultant pool, has provided a proposal in the amount of $398,300 to provide complete design, bidding administration and construction administration services related to the construction of Well 10 and the associated well house; and WHEREAS, staff recommend approving this work order so the preliminary data-gathering and design work for Well 10 can begin as soon as possible to accommodate construction of the well and well house in 2028. NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA as follows: 1. The recitals set forth above are incorporated herein. 2. The City Council approves a work order with with AE2S in the amount of $398,300 for the Well 10 design and construction administration. 3. The cost of this work order will be paid from the Trunk Water Fund. th Passed and adopted by the Prior Lake City Council this 27 day of October 2026. VOTE Briggs Braid Churchill Lake Hellier Aye ☐ ☐ ☐ ☐ ☐ Nay ☐ ☐ ☐ ☐ ☐ Abstain ☐ ☐ ☐ ☐ ☐ Absent ☐ ☐ ☐ ☐ ☐ ______________________________ Jason Wedel, City Manager C:\\Users\\hsimon\\AppData\\Local\\Temp\\Report Attachment - 20261027 Approve WO - Well 10 - RESO_679001\\Report Attachment - 20261027 Approve WO - Well 10 - RESO.docx 2 Public Works Consultant Pool Work Order Well 10 (2027-03) AE2S This work order (“Work Order”) is issued on this 27th day of October, 2026 by the City of Prior Lake (“City”) pursuant to the Public Works Consultant Pool – Master Agreement dated May 8, 2020 and as amended March 17, 2025 (“Contract”) between the City and Advanced Engineering and Environmental Services, LLC (AE2S) (“Consultant”). Based on the mutual promises and covenants set forth herein, the sufficiency of which are hereby acknowledged, the City and Consultant agree as follows: 1.Scope of Work Order. Consultant agrees to provide, perform and complete all the services requested by the City in this Work Order and attached Exhibit 1 (“Work”), which Work shall be subject to the terms and conditions of this Work Order and the Contract. 2.Term of Work Order. All Work requested by this Work Order shall be completed by December 31, 2028. 3.Compensation for Work Order. City agrees to pay the Consultant an amount not to exceed $398,300 as full and complete payment for the Work requested by this Work Order. 4.Consultant Representative. Consultant has designated Douglas Klamerus, PE to manage the Work Order subject to the supervision of Consultant’s representative. ISSUED BY CITY OF PRIOR LAKE ___________________________________ Mayor ___________________________________ City Manager RECEIVED AND ACCEPTED BY AE2S _____________________________________ Signature ____________________________________ Title Exhibit 1 – Scope of Work September 21, 2026 Mr. Nick Monserud, PE Public Works Director / City Engineer City of Prior Lake 17073 Adelmann St. SE Prior Lake, MN 55372 Re: Proposal for Well and Wellhouse No. 10 City of Prior Lake, MN Dear Mr. Monserud: Thank you for the opportunity to submit this proposal to provide professional engineering services related to the new Well and Wellhouse No. 10. Consultant is recommending the following general scope of services and associated fee proposal based upon the information provided to AE2S during our site visit on June 12, 2026. Project Understanding The City of Prior Lake (City) owns and operates seven (7) municipal water supply wells, with one of those wells (Well No. 6) only providing water during emergency peaks. The City has requested that AE2S provide scope for the design of a new municipal water supply Well No. 10 to serve continued growth in the City. The proposed well will be connected to existing raw water transmission lines and be routed to the water treatment plant. The proposed well location is in a neighborhood park at the intersection of Fish Pointe Rd SE and Blind Lake Trail SE. An observation well is located adjacent to the site and provides an understanding of the local geology and a history of static groundwater levels. The Jordan Aquifer will be investigated as the preferred source by the City. A design pumping rate of 1,200 gpm is desired by the City. Data Request Items Phil Ryan, Public Works Supervisor- Utilities provided follow up information to the June meeting with a Water System Study for the Orderly Annexation area which was completed by another consultant. In addition, water levels for the observation well at the proposed site of Well No. 10 were also provided. It is assumed that City staff will provide additional data requested by AE2S during the project in a timely manner to meet the project’s timeline. EXHIBIT 1 City of Prior Lake Well & Wellhouse No 10 Proposal Page 2 of 8 Project Approach – New Well and Wellhouse No. 10 Well No. 10 will include scope for the design, bidding and construction administration of the new well. A second phase of the project includes scope for design, bidding and construction administration for the new wellhouse. Specific features of the new wellhouse include: - Architectural style of the building will be a maintenance-free exterior with metal roof and gutters - Natural gas generator - Submersible well - Fiber will be connected to the site, and security features will include a scan reader and security cameras - Additional design details will be discussed at a pre-design kickoff meeting In addition, AE2S has discussed backflow prevention requirements included in the Well Code with Minnesota Department of Health staff to verify what will be required at existing wells to bring the water system into compliance with the well code. Per David Weum with MDH, all wells that are connected to a common raw water transmission line shall have backflow at the wellhead. However, MDH appears to be open to phasing-in these requirements over the course of a couple of years. Communication with MDH is ongoing. For the purposes of this proposal, backflow prevention has been included in the design phase of the wellhouse at all wells connected to the raw transmission line. If MDH does formally allow these improvements to be phased over time, the scope of work can be decreased under this contract. AE2S’ scope does not include budget to design for control of the new well. It is understood that the City’s integrator will design the controls, and coordinate with the Contractor and the City for proper start-up and integration services. Scope of Work Phase One – Well Drilling - Design Phase Services: o Coordinate site survey requirements with Owner. Conduct site survey park parcel. o Discuss the project with the Minnesota Department of Health (MDH) and the Minnesota Department of Natural Resources (DNR). o Meet at the well site with Minnesota Department of Health (MDH) personnel for preliminary approval of well set-back distances. City of Prior Lake Well & Wellhouse No 10 Proposal Page 3 of 8 o Prepare a preliminary well construction application for approval and submit it to the DNR. o Meet with the DNR to discuss the project. (1 meeting – 1 hour) o Prepare a preliminary set of drawings. o Prepare a preliminary list of specifications for the project. Specification format will meet the approval of the City and will include Prior Lake standard general conditions and contract forms. o Prepare preliminary opinion of probable construction cost. o Review preliminary documents with City personnel and make changes as required. o Prepare final construction drawings and specifications based upon draft comments from the City. o Update the preliminary opinion of probable cost to reflect any modifications made during final design. o Review final construction documents with City personnel and make changes as required. o Submit two (2) copies of the final bidding documents and wellhead protection information to the MDH for review. Respond to questions and comments from the MDH and receive approval for the drawings and specifications. o Submit two (2) copies of the final bidding documents to the City and one copy in electronic format (PDF). - Bidding Phase Services: o Print construction drawings and specifications (Bidding Documents). o Distribute Bidding Documents to prospective bidders. o Maintain plan holders list. o Respond to bidder questions. o Issue addenda to bidding documents, if required. o Attend bid opening and prepare bid tabulation sheets. o Evaluate bids and prepare recommendation letter. - Construction Phase Services: o Issue contract document clarification as required. o Provide construction observation on behalf of the City. o Organize, coordinate, lead, and attend preconstruction conference. Provide and distribute meeting minutes. o Assist the City in procuring testing services as defined in the Contract Documents. o Review Contractor submittals (shop drawings) for products and equipment. o Process contract change order requests, if required. o Review contractor-submitted construction progress schedules. o Process contractors pay requests. o Provide periodic construction observation by design team members during construction of the well, test pumping operations, alignment test, well video, and substantial and final completion inspections, for a total of 40 hours. City of Prior Lake Well & Wellhouse No 10 Proposal Page 4 of 8 o Provide Substantial Completion inspection and punch list for Contractor and issue Certificate of Substantial Completion when appropriate. o Provide Final Completion inspection for Contractor and issue Certificate of Final Completion when appropriate. o Review final submittal from Contractor with respect to conformance with the contract documents. o Process final pay requests and project close-outs. o Provide record drawings based upon Contractor’s mark-up and field observation. Phase Two – Wellhouse Design and Construction - Design Phase Services: o Preliminary Design: ▪ Coordinate and conduct a project team kick-off meeting attended by City and engineer. ▪ Prepare site plans based on City’s drawings and GIS data and site survey. ▪ Request soil borings for wellhouse and transmission main sites. ▪ Civil preliminary design will consist of: • Initial utility coordination • Preliminary drainage design • Prepare one (1) preliminary site layout for the wellhouse ▪ Electrical preliminary design will consist of: • Concept site plans • One-line diagrams • Specification Section Table of Contents ▪ Architectural preliminary design will consist of 3 renderings of the wellhouse and coordination with the City on preferred options. ▪ Prepare a preliminary set of drawings (30%). ▪ Prepare preliminary opinion of probable construction cost. ▪ Review preliminary documents with City personnel and make changes as required. - Final Design Services: o Civil, process, mechanical, electrical, structural and architectural design. o Prepare final construction drawings and specifications. o Prepare an opinion of probable construction cost. o Review 60% and 90% construction documents with City personnel and make changes as required. o Watershed district and MDH permit preparation & coordination. o Respond to questions and comments from the MDH and receive approval for the drawings and specifications. City of Prior Lake Well & Wellhouse No 10 Proposal Page 5 of 8 - Bidding Phase Services: o Print 2 copies of construction drawings and specifications for City (Bidding Documents). o Maintain plan holders list. o Respond to bidder questions. o Issue addenda to bidding documents, as required. o Attend bid opening and prepare bid tabulation sheets. o Evaluate bids and prepare recommendation letter. - Construction Phase Services o Construction Administration ▪ Issue contract document clarification as required. ▪ Act as Prior Lake’s liaison with contractor. ▪ Organize, coordinate, lead, and attend preconstruction conference and progress meetings, as needed. Provide and distribute meeting minutes. ▪ Assist the City in procuring testing services as defined in the Contract Documents. ▪ Assist the City in procuring construction staking services. ▪ Review Contractor submittals (shop drawings) for products and equipment. ▪ Process contract change order requests, if required. ▪ Review Contractor-submitted construction progress schedules. ▪ Process Contractor partial pay requests and submit to CLIENT. ▪ Provide Substantial Completion inspection and punch list for Contractor and issue Certificate of Substantial Completion, when appropriate. ▪ Review final submittal from Contractor with respect to conformance with the contract documents. ▪ Process final pay requests and project close-outs. ▪ Provide record drawings based upon Contractor’s mark-up and field observation. o Construction Observation – Provide construction observation for Wellhouse. ▪ Construction Observation is assumed to be part-time observation with trips to site for critical point construction activities and milestones. On-site representation will be provided during the following activities: • Underground Construction. o Assumed to be three 8-hour days. • Cast-in-Place Concrete. o Assumed to be three 8-hour days. City of Prior Lake Well & Wellhouse No 10 Proposal Page 6 of 8 • Substantial and Final Completion Punchlist Walkthrough. • Weekly Project Check-Ins through substantial completion. o Assumed to be 4-hours each visit. o Assumed to be a 9-month construction period. • It is assumed that 208 total hours will be spent on-site for construction observation. ▪ AE2S shall not at any time supervise, direct, control, or have authority over any contractor’s work, nor shall AE2S have authority over or be responsible for the means, methods, techniques, sequences, or procedures of construction selected or used by any contractor, or the safety precautions and programs incident thereto, for security or safety at a project site, nor for any failure of a contractor to comply with laws and regulations applicable to such contractor’s furnishing and performing of its work. AE2S neither guarantees the performance of any contractor nor assumes responsibility for any contractor’s failure to furnish and perform its work in accordance with the contract between CLIENT and such contractor. AE2S shall not be responsible for the acts or omissions of any contractor, subcontractor, or supplier, or of any of their agents or employees or of any other persons (except AE2S’s own employees) at a project site or otherwise furnishing or performing any construction work; or for any decision made regarding the construction contract requirements, or any application, interpretation, or clarification of the construction contract other than those made by AE2S. Phase Three – Wellhouse Backflow Prevention - Design Phase Services: o Preliminary Design: ▪ Coordinate and conduct a project team kick-off meeting attended by City and engineer. ▪ Prepare site plans based on wellhouse pictures gathered during preliminary site visits. An additional visit to verify dimensions will be conducted. • It is assumed backflow prevention will be required to be added at all existing wells and wellhouses. o Three (3) wellhouses and seven (7) wells. ▪ Prepare a preliminary set of drawings (30%). ▪ Prepare preliminary opinion of probable construction cost. City of Prior Lake Well & Wellhouse No 10 Proposal Page 7 of 8 ▪ Review preliminary documents with City personnel and make changes as required. o Final Design: ▪ Prepare final drawings and specifications. ▪ Prepare opinion of probable cost. ▪ Review 90% drawings with City personnel. ▪ MDH permit preparation & coordination. ▪ Respond to questions and comments from the MDH and receive approval for the drawings and specifications. - Bidding Phase Services: o It is assumed that wellhouse backflow prevention will be bid as part of the new wellhouse package but can be bid as separate projects (not included in scope). o No additional bidding services will be required. o Alternatively, if MDH allows phased construction after Well No.10 is online, this scope can be removed from the project or bid separately at a schedule determined by the City of Prior Lake - Construction Phase Services: o It is assumed that Construction Observation will occur under the new wellhouse construction services. o No additional construction services will be required. Schedule The schedule shown below assumes AE2S receives the City’s authorization to proceed by October 2026. Well No. 10 - City Authorizes Proposal: October 2026 - Surveying: October 2026 - Meetings with MDH & DNR for Preliminary Well Approval November 2026 - Preliminary Design Phase Well Deliverable: January 2027 - Final Design Phase Deliverable: February 2027 - City Authorizes Advertisement for Bid: February/March 2027 - Bid Opening: April 2027 - City Authorizes Contract Award: April 2027 - Construction: May – July 2027 Wellhouse No. 10 - Preliminary Design Phase Wellhouse Deliverable: July 2027 City of Prior Lake Well & Wellhouse No 10 Proposal Page 8 of 8 - Final Design Phase Deliverable: August 2027 - City Authorizes Advertisement for Bid: August 2027 - Bid Opening: September 2027 - City Authorizes Contract Award: September 2027 - Construction: October 2027 – June 2028 Fee Proposal Estimate AE2S will complete the proposed scope of services outlined above for an hourly, not-to-exceed, fee of $398,300. This fee is summarized in the table below. Phase/Task Number Phase/Task Phase Description Estimated Fee 1 Phase One Well No. 10 1 Design - $48,200 2 Bidding - $8,400 3 Construction - $17,400 2 Phase Two Wellhouse No. 10 1 Design - $164,200 2 Bidding - $11,400 3 Construction - $135,800 3 Phase Three Backflow Prevention $15,600 Total Estimated Fee $398,300 We appreciate the opportunity to assist the City of Prior Lake with this work and look forward to collaborating with you on this effort. If you have any questions or comments regarding our proposed services or if you need additional information, please do not hesitate to contact me at 651-448-3632 Sincerely, AE2S Douglas Klamerus, PE (MN) Laura Wehr, PE CFM Project Manager Operations Manager