Loading...
HomeMy WebLinkAbout10A - Duluth Ave Improvement Project ,. CITY COUNCIL AGENDA REPORT DATE: AGENDA #: PREPARED BY: SUBJECT: NOVEMBER 2,1998 10A SUE MCDERMOTT, ASSISTANT CITY ENGINEER CONSIDER APPROVAL OF CHANGE ORDER NO.1 TO THE DULUTH AVENUE IMPROVEMENT PROJECT #98-16. DISCUSSION: HISTORY During the construction of Duluth Avenue, the Contractor, S.M. Hentges and Sons, encountered three situations that they felt' were cause to request change orders in the original amount of $54,603.84 due to change in conditions or unforeseen circumstances. The items are as follows and will be considered as Change Order No.1: 1. Additional work associated with modifications to a connection to a Metropolitan Council Environmental Services (MCES) manhole as directed by the MCES representative. (Hentges change order reference #4). 2. Removal of a concrete cattle pass that was encountered in Duluth Avenue (Hentges change order reference #5). 3. Additional work associated with utility crossings under an existing telephone duct bank/fiber optic lines which is located along the east side of Duluth Avenue (Hentges change order reference #7). The above requests are dated August 25, 1998. S.M. Hentges and Sons started work on Duluth Avenue on July 6, 1998. As of July 28, 1998, the City had received change order requests and field work orders for approximately $30,000. The total bid for sanitary sewer construction on Duluth Avenue is $39,000. The City Attorney sent the attached letter dated July 30, 1998 regarding change order and contract issues. The attorney and city staff met with the contractor on August 7, 1998 to discuss the city's concerns. Subsequently, the contractor resubmitted change order requests # 4, 5 and 7, which take the place of the initial requests and provide more detailed documentation of the additional work. Engineering staff discussed the change orders with the Council at a work session on October 5, 1998. 16200.&~Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER RECOMMENDA TlONS The Engineering Department staff has provided full-time inspection for the 1998 Improvement projects. Attached are the staffs detailed recommendations for each of the three requests. Based on staff documentation of the construction and review of the Contractor's requests, the following is a summary the recommendations: 1. Payment of $4,400.00 for 10 hours of additional time for work at the MCES manhole (request #4) due to differing conditions. 2. Payment in full of request #5 to remove the concrete cattle pass. 3. Payment of $9,716.00 for additional time required to cross utilities under the telephone duct (request #7). The following table outlines the amount requested and the amount that staff is recommending for approval: Change order request # 4 5 7 TOTAL Amount requested $24,611.34 $3,401.00 $26,591.50 $54,603.84 Staff recommendation $4,400.00 $3,401.00 $9,716.00 $17,517.00 FINANCIAL IMPACT: The original contract was $1,345,425.33. Change Order NO.1 will increase the contract to $1,362,942.33. Funding for this change order is proposed to be from the Trunk Reserve fund due to the fact the extra work was required in conjunction with the utility replacements. ALTERNATIVES: The alternatives are: 1. Approve Change Order NO.1. 2. Deny this item for a specific reason and provide staff with direction. 3. Table this item until some date in the future. RECOMMENDED MOTION: A motion and second approving Change Order No.1 to the Duluth Avenue Reconstruction Project, funded through the Trunk Reserve fund. HENTCOI.DOC CHANGE ORDER CITY OF PRIOR LAKE 16200 EAGLE CREEK AVENUE SE PRIOR LAKE, MN 55372 CHANGE ORDER NO.1 TO: S.M. Hentges & Sons, Inc. P.O. Box 69 Jordan, MN 55352-0069 DATE: November 2,1998 FOR: Project No. 98-16, Duluth Avenue Reconstruction OWNER: City of Prior Lake You are hereby directed to make the following change to your contract dated June 15. 1998. . The change and the work affected thereby is subject to all contract stipulations and covenants. This Change Order will increase the contract sum by: Seventeen-Thousand-Five-Hundred-Seventeen and No/IOO Dollars ($17.517.00) Add the following: Item Descrintion Unit ,Ouantitv Unit Price Amount 1. MCES Manhole Hour 10 $435.00 $ 4,350.00 2. 8" PVC SDR-35 L.F. 25 $2.00 $ 50.00 3. Remove structure L.S. 1 $3,401.00 $ 3,401.00 4. Utility crossings Hour 12.5 $450.00 $ 5,625.00 5. Utility Crossings Hour 3 $365.00 $ 1,095.00 6. Utility Crossings Hour 1.5 $420.00 $ 630.00 7. Remove Sewer Main m 31.1 $20.00 $ 622.00 8. 200mm PVC Sewer m 31.1 $40.00 $ 1,244.00 9. Connect to exist. sewer each 2 $250.00 $ 500.00 Total Additions $17,517.00 G:\PROJECTS\I998\16DULUTHICOI.DOC DATE: November 2, 1998 CHANGE ORDER NO.1 TO: S.M. Hentges & Sons, Inc. P.O. Box 69 Jordan, MN 55352-0069 ....'') FOR: Project No. 98-16, Duluth Avenue Reconstruction OWNER: City of Prior Lake Amount of Original Contract $ 1.345.425.33 Change Order No. 1 $ 17.517.00 Revised Contract Amount $ 1.362.942.33 Contract time is not affected by this change. Approved as to Form: CITY ATTORNEY APPROVALS: Approved: City of Prior Lake Owner Approved: S.M. Hentl:!es & Sons. Inc. By By Mayor Date Date By Title City Manager Date G:\PROJECTS\I 998\16DULUTHICO I.DOC 07/Jl/9~ FRI 08:41 FAX 612 452 5550 CAMPBELL III 002 (18-1&; CAMPBELL KNUTSON Professional Association Attomeys :,.~ LelW Tholnas J. Camrbell Roger N. Knut$\1n Thoma~ M. SCO[[ Ellion 5, Koetsch $u.;<"n Lea PlIl.:e (612) 452-5000 Fax (612) 452-5550 Joel J, Jamnik AnJrc:.< McDuwell Puehlt!1 Mmthe\\' K. Hrokl. John F. Kdly ~hmhew J. F"li l\brglll'rir,. M. McCnrmn Ot:l1rgt: T. St~ph~ns"11 .r\'.C,f 1;..'\."11.'-.:01 ill W"lC~-,m"'r1 ... . . Wr.iter's Direct Dial: 234-6226 Writer's Fax! 452-5550 July 30, 1998 Mr. Steven Hentges S.M. Hentges & Sons Inc. P.O. Box 69 Jordan, MN 55352-0069 RE: Contract for 1998 Improvements Dear Mr. Hentges: I regret that you were unable to meet with Greg Ilkka, Sue McDermott, Jeff Evans and me on Tuesday, July 28, 1995 to discuss some serious concerns the City has regarding its conrract with S.M. Hentges & Sons, Inc. for certain sewer, water and road improvements. I was hopeful that if we sat down to meet, we would be able to clarify what appears to be some confusion on the part of your foreman on the Project. Obviously, he has had less experience with contracts than I suspect you have; and he has misinterpreted cel1ain provisions. The City is anxious to move forward with a clear understanding of, among other things, (1) what work is covered by the contract; (2) what work the City will pay for; (3) when change orders are appropriate; and (4) how the cost of additional work is calculated, As I understand it, S.M. Hentges & Sons, Ioc, started work on the Duluth Avenue phase of the project on July 6, 1998. There are two components to this phase of the project; a sewer and water reconstruction component, and a road reconstruction component. Your bid for the sewer portion of the fIrst component was approximately $39,000.00. As of July 28, 1998, the City has received field work orders and change order requests from S.M. Hentges & Sons, Inc. which amount in round numbers to about $30,000.00, or three-fourths as much as you bid for the sewer phase of the Duluth Avenue project. Naturally, you can understand the City's concern. The entire contract for the 1998 Improvements was awarded to your company at a cost of $1,345,425.33. lfthe City's experience thus far on the Duluth A venue portion of the work is any indication of what it can expect throughout the entire project, the [mal cost would be absurd, I did not represent the City at that time, but I am told that there were some difficulties as well with respect to contract administration when your company did the work on the Ridgemont A venlle Suite 317 · Eagandalc Office Center · 1.380 Corporate Center Curve · Eagan, MN 55121 07/31/98 FRI 08:41 FAX 612 452 5550 CAMPBELL !lJe03 S.M. Hentges & Sons. Inc. July 30, 1998 Pal!e 2 of 4 project. My approach to contract disputes may be somewhat different than that of other City Attorneys. I think it is important to .have a mUNal understanding of the contract documents and, at the earliest indication that there may be ongoing problems, to sit down and iron things out before any damage is don.e to the working relationship. It is time to sit down with you and set some ground rules that we all understand. Cities are constrained by the competitive bidding statutes to accept the lowest responsible bid. We both know there are contractors who will bid low in order to get the work and make up (he difference later with a deluge of change orders. I think we would both agree these types of contractors are disreputable and can give the construction industry a bad name. I know that you are not one of these types of contractors; and therefore I am optimistic you will welcome the opportunity to discuss the City's concerns with the City Staff and me at your earliest convenience. With two exceptions, one dealing with a duct and the second dealing with removing a concrete cattle crossing, the City Engineer is denying your foreman's request for cost increases. I am providing you with an explanation for the City's denial of such requests as follows: 1. Chanlre Order Reauest No. L Julv 21. 1998. YOUR DESCIUr .liON OF WORK PERFORMED: Additional work associated with stubbing the sewer east and north of M.H. #7. The work to the east was slowed by the unknown telephone duct bank that we had to work around. . . AMOUNT REQUEstED: $5,741.50 CITY REsPONSE: S.M. Hentges & Sons, Inc. should be compensated for the additional work incurred as a result of encountering a duct which was larger than indicated on the City's plans and specifications. The City Engineer will recorrunend that the City Council approve Change Order No.1 in the amount of $1,090.00 for labor. An additiona131.1m of200IlUl1 PVC sewer pipe and 2 connections to existing manholes wlll be paid at the contract unit price for the corresponding items. The City is not compensating Hentges for the requested $2,635.00 for equipment because the equipment was already on the site. 2. Chane:e Order Reauest No.2. Julv 2L 1998. YOUR DESCR&r uON OF WORK PERFORMED: Additional work associated with repairing 6 II watennain. AMOUNT REQUESTED: $207.50 CITY RESPONSE: Your company broke the pipe and the City is not paying to repair it, On July 13, 1998, sanitary. sewer M.H. #7 was installed per the plans and all existing underground pipes within a 10-15~ radius were exposed to make proper cormection to the existing pipes. While exposing the existing 6" watermain pipe to the north of M.H. #7, a small leak appeared on the pipe due to the construction activities that day. The City provided S.M. Hentges & Sons, Inc. with a 6" steel band to repair the damaged pipe. The foreman installed the 6" x 12" steel band over the leak by hjmself. Jeff Evans observed the work and advises me that the entire installation took approximately 10 minutes. , ,,.t' --'"'c -- 07/31/98 FRI 08:41 FAX 612 452 5550 CAMPBELL ~004 S.M. Hentges & Sons, Inc. July 30, 1998 Pae-e 3 of 4 3. Field Work Order No.1733, dated Ju1v 16. 1998. YOUR DESCRIPTION OF WORK PERFORMED: Change in conditions; .M.H. #6 has to be relocated, water table 3' to 4' higher than shown on boring detail. ES11MATED AMOUNT REQUESTED: $9,501.00 CITY REsPONSE: Paragraph 13.2 of the Special Provisions of the Contract provides: The Contractor is advised to determine to his own satisfaction the exact soils and groundwater conditions prior to submitting his bid. In wet trenches. the Contractor shall dewater the trench by an acceptable mechod and use proper granular bedding. Any dewatering required shall be incidental to pipe installation unless a specific bid item is provided. Your bid included the following written statement: "We have examined the site of the work and are acquainted with all conditions affecting the construction of the work." Pursuant to paragraph 13.2 of the Special Provisions, S.M. Hentges & Sons, Inc. is not entitled to a cost adjustment for rhis work. Further, paragraph 17.2 of the General Conditions concerning subsurface conditions provides in relevant parr that "[a)ny claim of the Contractor for adjustment hereunder shall not be allowed unless the required written notice has been provided... " . 4. Field Work Order No. 1734, Julv 15. 1998. YOUR DESCRIPTION OF WORK PERFORMED: Laying PVC out of #6 to #5, 1-2 truckloads of 1 1/2" per pipe, (change in conditions). EsTIMATED AMOUNT REQUESTED: $6,955.50 CITY RESPONSE: Same as response to No.3 above. 5. Field Work Order No. 1735. Julv 20. 1998. YOUR DESCRir .liON OF WORK PERFORMED: Change in conditions. laying 200uu.u pve, water table 3>> -4' above invert. EsTIMATED AMOUNT REQUESTED: $4,000,00 CITY REsPONSE: Same as response to No.3 above. In addition, paragraph G.4 Foundation Materials of Section 4000, Sanitary Sewer. Specific Reouirements (page 40005-1 of the specifications) states: Any dewatering required for this work shall also be considered incidental to sanitary sewer construction with no additional compensation provided. Pipe foundation material will be paid at the contract unit price per the bid. 07/31/98 FRI 08:42 FAX 612 452 5550 CAMPBELL 19j uU.o S.M. Hentges & Sons, Inc. July 30, 1998 PaQ'c 4 of 4 6. Field Work Order No. 1738. July 22. 1998. YOUR DESCRIPTION OF WORK PERFORMED: Remove Ex.isting Culvert to set M.H. #2. EsTIMATED AMOUNT REQUESTED: $3,300.00 CITY REsPONSE: Although the City Engineer will recommend a change order for the box culven removal. the City's inspector. Jeff Evans, was on-site and recorded the extra time it took to remove the structure as 2 hours for full crew and 2 hours plus the Cat w/hammer. In addition, 410ads of debris were hauled off-site, not the 6 indicated on the field work order. Since you have not provided us with the rates for the equipment, we will discuss the costs at our upcoming meeting. 7. Field Work Order No. 1739. Julv 24. 1998. YOUR DESCRJt" uON OF WORK PERFORMED; Dewater sanitary sewer line. ESTIMATED AMOUNT REQUESTED: None provided. CITY RESPONSE: See No.3, 4 and 5 above. Finally, I would like to call your attention to paragraph 16 of the Contract, which reads in part: "Additional Work performed without authorization of a Change Order will nOl entitle Contracror to an increase in the Contract Price or an extension of the Contract Time." Your foreman has used Section 17, General Conditions of the Contract as the basis for most of the Change Orders and Field Work Orders requested. Apparently, your foreman is of the opinion that conditions at the sire differ materially from what is indicated in the plans and specifications. If that is the case, perhaps the Contract should be rescinded, the plans and specifications revised, and the Project re-bid. Please advise Assistant City Engineer, Sue McDermott, when you are available to meet with me and City Staff. I suggest the meeting should be at your earliest convenience. As a ma~ter of courtesy, I think: it is appropriate to advise you that I will be briefing the City Council on these problems. Very truly yours, CAMPBELL KNUTSON Professional Association By: \~ tu.. Pau- I Suesan Lea Pace Prior Lake City Attorney cc: Mayor and. City Council Frank Boyles. City Manager Greg Ilkka, City Engineer Sue McDennott, Asst. City Engineer CHANGE ORDER REQUEST REFERENCE #4 DATE OF REQUEST: 8/25/98 PURPOSE: Connection of sanitary sewer pipe at existing M.C.E.S. manhole. AMOUNT REQUESTED BY CONTRACTOR: $24,611.24 AMOUNT RECOMMENDED BY STAFF: $4,565.00 FACTS: * The direction of the existing stub was not shown correctly on the plan. * The invert elevation of the stub is correctly shown on the plan. * M.C.E.S. inspector, Dan Smitz, was on-site during the work. * The contractor proceeded with the work without contacting engineer or inspector on site. Connected to in-place stub as shown on plan. * Contractor assumed he was to punch a new hole into the manhole & M.C.E.S. inspector said "NO", so contractor proceeded to install pipe in existing direction. * The Change Order includes quantities already in contract which were paid in Pay Estimate #1. * Hentges' foreman discussed in field with Jeff (City inspector) that existing angle would be used to set manhole #6 & adjust the grade of the pipe between manhole 6 and manhole 5. * On 7/16/98, Hentges crew started at 7:00 A.M., by 1 :45 P.M. the manhole was excavated & plug pulled from stub at 2:30 P.M., contractor put PVC into bell & proceeded with pipe. At 5:30 P.M. set MH6. Total of 10 hours, change order request shows 13 for the foreman and 12 for the laborers. City Inspector reports are included. * July 15, 1998, the contractor did not work near the M.C.E.S. manhole. They were working elsewhere. They are claiming $6,396.27 for July 15. * July 16, 1998, contractor was working under contract setting manhole. Already paid the following bid items for this work: 10m of 8" PVC at $40 = $ 400 +MH ($1750 ea.) =$1750 + extra depth 1.6m @ $350 = $ 560 + connect to exist. MH = $ 350 $3060 * July 17, 1998, started at MH6 & laid 12m of pipe. Crew left at 2:30 P.M. (not in C.O. #4) * July 20, 1998, 7:00 A.M. - 2:30 P.M. = 7 hours. Change order states 9.5 16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 G:\PROJECTS\I998\CHGOR#4.DOC AN EQUAL OPPORTUNITY EMPLOYER hours for foreman and 8 hours for laborers. 20m pipe were installed (paid in Pay Estimate # 1) . , * Dewatering is incidental per the contract specifications. The contractor is claiming $5,082 for well points plus $2,350 for pumps and generators plus additional quantities for rock. * Groundwater: 1 1/2 feet over pipe (proposed). Pipe would be in groundwater even without the revision (see attached plan). The bid contained separate items for pipe at 2-foot depth increments. The contractor bid each item at the same rate ($40/m) regardless of depth. CONTRACT PROVISION: G:\PROJECTS\I998\CHGOR#4.DOC GROUNDWATER ISSUES: 1. Bid states "We have examined the site of the work & are acquainted with all conditions affecting the construction of the work." 2. Page GC-9, Paragraph 17. We received a letter dated July 21, 1998 from Hentges claiming a change in conditions from what is in the plans. Paragraph 17 of the General Conditions states "17.1 The Contractor shall promptly, and before such conditions are disturbed except in the event of an emergency, notify the Owner by written notice of: 17.1.1 Subsurface or latent physical conditions at the site differing materially from those indicated in the Contract Documents, or..." 3. Page SP-6, paragraph 13.2 "the Contractor is advised to determine to his own satisfaction the exact soils and ground water conditions prior to submitting his bid. In wet trenches, the Contractor shall dewater the trench by an acceptable method and use proper granular bedding. Any dewatering required shall be incidental to pipe installation unless a specific bid item is provided." 4. Dewatering page 4000-14, fourth paragraph: "The Contractor shall install and operate a dewatering system of wells or points to maintain pipe trenches free of water whenever necessary or as directed by the Engineer to meet the intent of these specifications. Unless otherwise specified in the Plans, Specifications, or Specific Requirements, such work shall be considered incidental with no additional compensation provided therefore." 5. Page 4000-15 "If examination by the engineer reveals the need for placement of foundation aggregates was caused by the COrlllactor's manipulation of the soils in the presence of excessive moisture or lack of proper dewatering, the cost of the corrective measures shall be borne by the Contractor." 6. The Geotechnical Report prepared by Braun Intertec, which is included in the contract documents, states "Seasonal and annual fluctuations of the groundwater level should be anticipated." MANHOLE ISSUES: 1. 4000-7 "There shall be an inspection of the existing sanitary sewer, storm sewer and water main utilities prior to the start of construction. The Contractor shall notify the Engineer 24 hours in advance to aid in accomplishing this inspection. All deficiencies in these existing systems prior to beginning construction must be immediately brought to the attention of the Engineer. " 2. Page GC-3, paragraph 4.3 "Any discrepancies found between the drawings and specifications and site conditions or any inconsistencies or ambiguities in the drawings or specifications shall be immediately reported to the Engineer, in writing, who shall promptly correct such inconsistencies or ambiguities in writing. Work done by the Contractor after discovery of such discrepancies, inconsistencies or ambiguities shall be done at the Contractor's risk." RECOMMENDATION: Recommend payment of 1 0 hours of crew time, 10 hours of equipment time and 25 LF of 8"PVC pipe as outlined in the request for July 16, 1998, due to additional time required because of reversal of connections as shown on the plans. The bid contains unit prices for all of the items associated with connection to the MCES manhole. The Contractor is required by the specifications to contact the Engineer when discrepancies are discovered. The Contractor constructed the connections differently than shown by the plan based on discussions with the MCES inspector. The Contractor is claiming additional compensation for days that were not spent on this manhole. The contract is clear regarding groundwater and dewatering. The Bid included items for different depths of pipe placement, the Contractor chose to bid the same unit price regardless of depth. G:\PROJECTS\I998\CHGOR#4.DOC 1. Foreman, 10 hrs @ $55.00/hr.........$ 550.00 2. Laborers (2),20 hrs @ $35.00/hr......$ 700.00 3. 400 B'hoe, 10 hrs @ $175.00/hr......$1,750.00 4. 943 Loader, 10 hrs @ $135.00/hr....$1,350.00 5. 8" PVC SDR-35, 25 If @ $2.00/lf...$ 50.00 TOTAL $4,400.00 G:\PROJECTS\I998\CHGOR#4.DOC 1'; CITY OF PRIOR LAKE DAILY REPORT CUENT CONlRACTOR (PRIME/SUB) TatP. RANGE c,{;' A~ P AGE OF PROJECT Cfg ~/6 CUL..VIt-+ DAlE 7-/6 - '1 f[; s ~ T W D' s ~ #1, /I eNTl:; e7 SUPERINlENDENT JOHN W1 W1ND(J - <' CLOUD CO~ ~(Z./pc... PRECIPITATION 0 COtAIENTS: 7'f}() A-Lc-t - ~1}JJ:JINC; ("ii> .6< /4eJ co. tw /I ~ r;? 0., Sg 7 7.'10 fTl1ffetJf!..7 '7""0';1 or (5-{. >10~W1 t-V1c..vrYeeD To Co~f7-ooT v-/J 76~ y &'E pv'} LN. 0JZ.oC/JIP iv.JfT&fZ.- /'5 I ,#}lJv& Y'1Zof'. r,PE A/6't!:"P f20c.J::., 'pe;"-7J:?_ C5/C.. 7f1o, 'fj1J _ 1/et.-.-f'6D .5c.,," ~'Cf. 7#(!)Or eG.. "Ii Duc.T ~ d-N':4 )ftt; /8c(;e>~ hll.(p Nu~ 14t1g-. C~. 04 >/TC ~ t7:~A-""" (.D N__ . ;::;'1.1 J,r: '3 rO~ ANc, ~C> TO "7_f.A./6~r. w/C,L (/fe e;rvl? /!.t../~I'I""'el)lr /,?,yD >~. ~/-/ f? @ 4.V.)ulr ~14J.DG To c-o/// ~ ?40 /~ tf) PC/I..L.c.r> P l-vq Pf!.o""1 ~ f c:.,.L .If . - f/} -p sruf.3 ~ - - I . C~_~H , ,\, -V~~J 1'-." 1,) ex ,...u, u,er.co 9:'/5 cr:~tJ ~61771J~ up R;f":,JL-- ~N '7 Pclvr1iJ ~;<</? !smt2.:re-rJ ) L.oTj op jZ.OoK ~ / '7 ~ eN ~ 4/1JiN4 44'~' 4-: rD ~:5o . ~ T 14 e,c... (2/1''' C, t2oc., K- ;:::0 /l- JU H - ,.v.~ l.t./ t:. ~ 5;::' e I ~ JI' .) r?11? r~.~ ~-I PVc.... , (,., _ (.A-~ -.;.../ ?o ~,.~" I"/. ) ....... .-: z~~o ~ vr -'0 t!l..t- C. f'Vc.- J, Ii- f'o . f7i?LC- . DIP . t etPtivW 4'01.,.:- (j7 r eXI>1 z.," p'c f? 5 emN~ utl-/ 7fJd/ /Nv A'/t:. ~ ~_ tf-"(;Z ........ IF b (:.78: '8 So, ) 0/D C) 1= ,-:;I'l..t'J-P.~ 1-o.e.>""-= /.4-3/t:' Lcf'} flDi-G t)P6^J ro(L Nlt:;ifr (/~6tf) /f-PPi3 z..er /f T" <5,1lA-N vvllt1T Iov/?-J ~PIA~I!- (T5~P) ~ - t : so t:-t;r7 7// if 110m: C e..E! iA/ :: /~J&-Jo,A,y ~- ,:?,I'~~ __4!:. 1- IJ~ /I"""" 44f1P 7: dO TO 7.' t7 0 /-OP~T6~ (~ T'or ~~N) - --" INSPECTlON TIME JOB NUMBER MILEAGE TOTAL HOURS I z.- //. INSPECTOR ~~~~ -~ White - Office Yellow - Inspector .Jo; c ~ MI;i~ ~ ~ I -:-1 \~ I r-~-_-l_.:'" 200 mm DIP g I -C 1_.1 -J~ 8 I' :"':~l ":: ,.",,'I~ I~ t.}>' I:.^I,:) I 2jo ~ "'~t! ~~ '" .ro._ "1 ... ';:)U mm)r.~c; SHJriM ~ -- , ~ fS!A ~ II ~. 'q'SJ ~I "'" l~~ ~ ~ I 00 "~' --\ " r; N ~~~~S:~~r~ ~ , g ~ CURB STOP CONNECTlONj 3 Cl (lYPICAL) . 3 ~ B~'f' l:u rT1 ~~~ r ~ r 16377 ~ I~ {.~-~;':' T'~ . I 00 o + O'J o ...... c.n ;:: co ~~!~ ~ '" '" ~IV ---- fr /1 Ii: 1:3 1& 1 ~ Il QI ~I ~I 31 16361 '86.( FINI~ED CL GRADe I ., ~' '\ ~ .,. \'! '85.( 184.( EXISTING CL ,RADE \\ "", ..,;1,.- \.. 79.V==- (1lC1l ltlltl gr2~ NN ~. ).!Jl (l)Z -.. ~~~ !i;__ N N co __ t'i~ ___-- "r, ga~ __ -- ~ ;. :r u cxS _ _ --_________ "<; ::; >-N _ ~ 11- -~-~ II /I II II II II /I " PI top 460 mm X 725 mm AF C~ R =P STORM I I PROVIDE MINIMUM (~S17 TO 0518) II 0.46 m SEPARAl ~ Ii nJ P.O"O'''.WJM~ :: ~~ ~0.46 m SEF'AR'~~ - - ------+-- -II~ - ---.f-- II I U ----I II II " II II I -II IIIN~~'" ;:::~~~ 111~~~:i :g I III NN~ ..:1 ~A.JU ~III' :(1)(1), ~~~~~ti: ;:!: xxx~ l/l LULULU_ CllNNECT TO EXIST 200 mm DIP OF OP ~83.C ---J- ~82.C PROP 300 mm RCI' ;;TORM (0515 TO 0516) \0 :81.0 ~80. C- - 78.0 O'>"<:t ON 1'01") roC() NN 0+540 " ",," 0'- .,.-1") .,.-1") nLD 1"')1") COCXJ NN ~_-D....L.. ~ Q n L{)C() 1'-0) 1")1") roC() NN 1"')1") roC() NN n 4- "-fin. _ ,....,. c.....c...- ~~0;'_~~.r~~::~.\ .O;*-",~,,~..<..ij"! Change Order Request AUG 3 1 1998 p.o. Box 69 Jordan, MN 55352-0069 Phone: (612) 492-5700 Fax: (612) 492-5705 :",:. Change Order Reference 4 Date of Request 8/25/98 TO: Sue McDermott, P.E. City Hall 16200 Eagle Creek Ave. S.E. Prior Lake, MN 55372-1714 Job No.' 98-317 Job Description 98-14,98-15,98-16 Job Location DESCRIPTION OF WORK PERFORMED: Changes due to M.C.E.S. changing the connection to their structure. (See 5MB letter dated 7/21/98) See attached field work orders for specific information along with John's detailed description of what happened. ACTUAL COSTS: A. July 15, 1998 1. Foreman, 2. Laborers (2), 3. 400 B'hoe, 4. 943 loader, 5. 1-1/2" rock, 6. Common excav. 7. 8" PVC SDR-35, 8. Generators (2), 9. Pumps ( 3) , 8.5 hrs @ $55.00/hr.... 16 hrs @ $35.00/hr..... 8 hrs @ $175.00/hr..... 8 hrs @ $135.00/hr..... 103.93 t @ $8.11 W/15%. 52 cys @ $6.50/cy...... 54 lf @ $2.00/lf....... 8 hrs @ $350.00/8 hrs.. 24 hrs @ $300.00/8 hrs. $ 467.40 $ 560.00 $1,400.00 $1,080.00 $ 842.87 $ 338.00 $ 108.00 $ 700.00 S 900.00 Subtotal $6,396.27 An Equal Opportunity Employer B. July 16, 1998 1. Foreman, 13 hrs @ $55.00/hr.... . $ 715.00 2. Laborers (2) , 24 hrs @ $35. OO/hr. . . . . $ 840.00 3. 400 B'hoe, 12.5 hrs @ $175. 00 /hr. . $2,187.50 4. 943 loader, 12.5 hrs @ $135. OO/hr. . $1,687.50 5. 1-1/2" rock, 175.45 t @ $8.11 W/15%. $1,422.90 6. Common excav. 88 cys @ $6.50/cy.....~ $ 572.00 7. 8" PVC SDR-35, 25 If @ $2.00/lf....... $ 50.00 8. 48" M.H. sect. , 12' @ $90.00/lf.... .... .sJ,..080.00 Subtotal $8,554.90 C. July 20, 1998 1. Foreman, 9.5 hrs @ $55.00/hr..... $ 522.50 2. Laborers (2) , 16 hrs @ $35.00/hr..... $ 560.00 3. 400 B'hoe, 8.5 hrs @ $175.00/hr.. $1,487.50 4. 943 loader, 8.5 hrs @ $135.00/hr.. $1,147.50 5. 1-1/2" rock, 12.66 t @ $8.11 W/15%.. $ 102.67 6. 8" PVC SDR-35, 4 If @ $2.00/lf. ...... $ 8.00 7. 3 pumps S 750.00 Subtotal $4,578.17 D. Well-point charge for dewatering requirements I.Invoice from Blake Drilling............... $4,620.00 2. SMH 10% O. H. . . . . . . . . . . . . . . . . . . . . . . . . . . . .. S 462 . 00 Subtotal $5,082.00 TOTAL $24,611.34 ,.1',' '"'^ }( ~ f "t:L /tl Of\l fhu.V'scJ.Cc..'j 7-lb~B, 7>-to..r-rt.J dl8fJl",~ o..rolJ-V\d metro S~~~V' L'~ @ A-fr(J~. q:oo Do...V\ S W1 itz.. +r'-'fIf'1 (Y) e.T'('D CO\..Ul\~ \ ~~ 0....,,:1 i-o i (/\ 3fe c:-( COr') '" -e d ; "..," w... tw.d ... )< I' 0 S e J +h '" Tr:. r:. ""-"I c/ --ff, . 7' Sf....b -r t., "- -l hc..d · z s b CLd: -A.-II" ..,- J, e. L '" He. _ of -t ~ '" T €" G W <>"5 he o.d : '" ':l cr,"'o l' 7'1' of -f. IV he 01\ ""th"- 't clro..f'+Io-J The f (0.... S -H-. ""t ~ r -e V e r s~ d +- h -e 2. (...... '" e e.--r" " ." ." : ... ..., 0 1- ~ -e MQ..y\ ),,0/.... " n e.,..... ..... ,"s ~ It.' StJ.rv h... ~~c..d,"nlJ +W"'r ls ft1 H #- " Loco.. -{ ,'6", I 01..'" d T 1.. 'f! '-..e .e.. ..., "'-5 ..... he...- -r 'l-h e 't '/-'h 0 ---11!- 1- IA-"C<. 5" 'f--l,.""- 4 /1 Se... oJ" """--. 1 !;"}!plo..Jn-e,[ "1-0 D...."I. ~..,. ih order for """- '1-0 (!CA:T m-/t#,- ,'.., :t 0/.... '^ '0 co... -f J 'u .., I ~ ~ 5 -to b re4... k. 0 '"'- -r 1 ...L) .... . \ L..,.. t:A. Y'a CA. VI d r '" ~ TE d i e ~'1 ~rY)J )d b'j dol",Ct SO [ k,eH......./d ~.:S to hO"~+D o...d.d. ~ pC2..ice ~..r::: , I r pi foc <> rh -e 12.... r! (') + --r h € -+ -e. ~ .b e u.. "-3 e. i t- /.u 0",- td. I, c... "-e he e Y1 ) v... + '5;d..e.. +h e. vn.~1I'l hb l-e . D~", .) r e p { V Y l.(.., Ct. ~ I f C1 <..LV'" noT q , b )01"'1 t- 0 r e. <<. k -r i-, e. ::5 e. "'- ( c... '" <> lA "l d. -+ t--. <> ftD IIi1I1 A 1-1 d 7- _I \\, ." I YOlA.Y' ;)olV\..] 7--0 ,0'" U\ "'<-- T" "-' /"...:1-s -rh-er-e. C(...o Ie J do", '1 C.eve "-f .t I I c.o~""s :::L 71 n 01'-- ~..,\ CJ p1io...... +0 b 1..- ~. re.~" C.I LA- -r ~ -he c.;+'1 t~o-r~ or nOI, '!.A.'r MH" (1)1:4.11\ S~jt"Z.), ~~ W~ 1-,... v -c 30' ,,-f d ,- <; -J",V\<- -c. be.T..... eon. rn H"H b "'-'" d IE" -x/ 5 T. ~ 3 · 0 (j 0]" pic. K:s - (' -J "- e '1 r-<>k · q J 0 rf Fr I '" ...1(" i-f w " ~ Lve" i" v....;i L. , PIC(.", ~e o-f '3.I~"l", iVl lOb.{, "'-'<. \.uo.....\d ho..>>~ 6-ee.... u..~ ~.5' iA,;"o...-e (2,..;~1 /JI\.verr (Af't.~.) LOf...c~.:"'/on 0 -F fP)ff~ WCt.~ 7ft?_S' ~c. /2- t1-f Plo...", Lo(;.a...-! jlPY1()o +h-l!. Y COVVlp-e.1II. ~-I r.J by .ftrf"-/'~) c- V\-Qt.v I r fA J e I -rA...., l:;" q~ f i "'-~ ",-, i y.. tk" ..,.... -f,..r +... b r~ L,J . "" f-o f" ~ I\. ~ n~p. CL1f\. CHANGE ORDER REQUEST REFERENCE #5 DATE OF REQUEST: 8/25/98 PURPOSE: Remove cattle pass. AMOUNT REQUESTED BY CONTRACTOR: $3,401.00 AMOUNT RECOMMENDED BY STAFF: $3,401.00 FACTS: * Unforeseen condition. * The structure had to be removed to install utilities & lower road grade. RECOMMEND: * Pay the entire amount requested of $3,401.00 16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 G:\PROJECTS\I998\CHGORIIS.DOC AN EQUAL OPPORTUNITY EMPLOYER p.o. Box 69 Jordan, MN 55352-0069 Phone: (612) 492-57GJ Fax: (612) 492-5705 Change Order Request Change Order Reference 5 Date of Request 8/25/98 TO: Sue McDermott, P.E. City Hall 16200 Eagle Creek Ave. S.E. Prior Lake, MN 55372-1714 Job No. Job Description Job Location 98-317 98-14,98-15,98-16 DESCRIPTION OF WORK PERFORMED: Removal of existing box culvert. See attached field work orders for specific information. ACTUAL COSTS: Labor. . . . . . . . . . . . . . . . . . . . . . . . Equipment. . . . . . . . . . . . . . . . . . . . Material. . . . . . . . . . . . . . . . . . . . . Dump charges................. $ 750.00 $2,560.00 $ 91. 00 S 0 _ 00. TOTAL $3,401. 00 . An Equal Opportunity Employer REFERENCE #7 CHANGE ORDER REQUEST DATE OF REQUEST: 8/25/98 PURPOSE: Large telephone duct. Contractor claims delay, extra work. AMOUNT REQUESTED BY CONTRACTOR: $26,591.50 AMOUNT RECOMMENDED BY STAFF: $9,716.00 FACTS: * Telephone line shown on plans. * Average time to install service was 2.5 hours. If it took 2.5 hours over & above this it would mean 4.5 hours per service. They were installing 4 services per day. They did not work 18 hours per day. If they mean it took 2.5 hours to install a service and average time to install is 2.0 when there is normal gas/telephone, only 1/2 hour additional time was required. Recommend 11 services x 0.5 x $450 = $2,475.00 * (C) Jeff Evens (City Inspector) & John Mazurkiewicz (Hentges' foreman) agreed on-site to 2 hours, not 4 hours (attached field work order 1711). Recommend 2 x $450 = $900 * (D) Sanitary Sewer Stub to East: John's crew started at 7:00am at MH 7 heading east. Scott Rice arrived on site at 7:15am. At 9:15am all utilities were exposed. Scott Rice delivered the pole to use to hold the duct at 11: 15am and duct banded to the pole at 11 :30am. Lunch 11 :30 - 12:30. At 1:10pm the connection was made to the existing sewer pipe and backfilling commenced. An additional 5 hours additional time was required due to the telephone duct. Recommend 5 x $450 = $2,250 Sanitary Sewer Stub to North: The telephone duct did not affect the placement of pipe to the north. The crew started at 1 :OOpm and connected to the existing at 3:00pm. Recommend payment of this work through quantities already in the contract (12.5 meters of 200mm PVC and 1 each connect to existing sanitary sewer pipe). * (E) Foreman not on-site 2 hours x $365 = $730 * (F) No extra time - no delay per Jeffs notes. Other work being done while phone company shoring duct. * (G) On Tuesday, July 28, 1998, one of S.M. Hentges sewer crews (Marty/Mark's Crew) worked a total of three hours laying one 20' section of 6" DIP watermai~ under a 2" PVC cable TV crossing, a 16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 G:\PROJECTS\I998\CHGOR#7.DOC AN EQUAL OPPORTUNITY EMPLOYER Scott-Rice Telephone duct, and a 6" gas main on Pleasant Street east of MH7. Their time is documented in City's inspection report as follows: (1 :00 - 2:00 P.M.) sewer crew exposed 2" PVC cable TV crossing and telephone duct. A representative from Scott-Rice was on-site to assist banding the duct to a wooden pole. (2:00 - 2:20 P.M.) sewer crew removed existing hydrant at the N.E. comer of Duluth Avenue and Pleasant Street and exposed a 6" gas main. (2:20 - 3:30 P.M.) sewer crew undermined 2" PVC cable TV, telephone duct, and 6" gas main and laid one 20' section of 6" DIP watermain underneath while removing existing 6" CIP (cast iron pipe) water. (3:30 - 4:00 P.M.) Scott-Rice representative assisted planking and banding telephone duct. Sewer crew backfilled trench. In my opinion an additional 1 hour of time was utilized undermining the Scott-Rice Telephone duct. Recommend 1 x $420 = $420 * (H) On Monday, August 10, 1998, one of S.M. Hentges sewer crews (MartyIMark's), less the foreman, worked from 7:00 A.M. to 2:45 P.M. laying 15 meters of 460mm x 725mm Arch RCP from station 0+043.5 to 0+028.5 and setting DS 17, excluding 1/2 hour for lunch. Working conditions for the backhoe were very tight with the 6.1 meter easement, the deck directly outside the easement at 16411 Duluth Avenue, the depth of the Arch RCP at this location, and the overhead power lines. In addition, setting DS 17 was tight with the telephone duct to the east, the NSP power pole to the north, and the gas main to the west. Work progressed very slowly under these conditions. In City Inspector's opinion an additional 1 hour of time was utilized dealing with the Scott-Rice Telephone duct. Recommend 1 x $365 = $365 * (I) On Tuesday, August 18, 1998, Mark's sewer crew worked a total of 1/2 hour tunneling under the Scott-Rice Telephone duct with 300mm HDPE storm sewer between DSIO and DS9. The backhoe was able to expose both sides of the duct. Mark instructed the crew to hand dig and tunnel under the duct rather than having to expose and band it to a wood pole in order to save time. He was of the opinion that S.M. Hentges was not getting any additional compensation for time utilized undermining the telephone duct, as City Inspector heard him tell his crew. In Inspector's opinion, an additional 1/2 hour of time was utilized undermining the Scott-Rice Telephone duct. Recommend 0.5 x $420 = $210 RECOMMENDATIONS: Reduce the request based on documentation by City inspectors outlined above. G:\PROJECTS\I998\CHGOR#7.DOC Approve a change order in the amount of $7,350.00 and the following additional quantities paid at the contract unit prices: SCHEDULE NO.9 (98-16 SANITARY SEWER) UNIT TOTAL ITEM # DESCRIPTION UNIT OTY PRICE PRICE 1 Remove sewer main 31.1 m 20.00 622.00 12 200mm PVC sewer 31.1 m 40.00 1,244.00 13 Connect to exist.sewer 2 ea. 250.00 500.00 TOTAL $2,366.00 RECOMMENDED TOTAL FOR CHANGE ORDER #7: $9,716.00 G:\PROJECTS\I998\CHGOR#7.DOC p.o. Box 69 Jordan, MN 55352-0069 Phone: (612) 492-5700 Fax: (612) 492-5705 Change Order Request Change Order Date of Reference Request 7 8/25/98 TO: Sue McDermott, P.E. City Hall 16200 Eagle Creek Ave. S.E. Prior Lake, MN 55372-1714 Job No. 98-317 Job Description 98-14,98-15,98-16 Job Location DESCRIPTION OF WORK PERFORMED: Additional work associated with crossing the existing telephone duct bank/fiber optic lines. Please not that casing pipe used for the copper is not being charged as an extra. All time is above and beyond bid unit prices. ACTUAL COSTS: A. John's crew 1. 400 Blhoe 2. Loader 3. Laborers 4. Top man 5. Foreman Total crew (2) $175.00/hr $100.00/hr $ 70.00/hr $ 50.00/hr S s~_OOiliI: $450.00/hr Martyls/Mark's 1. 330 B'hoe 2. Loader 3. Laborers (2) 4. Top man 5. Foreman Total crew rate Crew $150.00/hr $ 95.00/hr $ 70.00/hr $ 50.00/hr ,S 5S _ 00 LID: $420.00/hr rate B. 11 services required 2.5 hrs of additional work, above and beyond the bid item for services. 1. 11 services X 2.5 X $450.00.......... $12,375.00 c: C. The service for 16541 and Valley Sign required 4 hours of additional work, above and beyond the bid item for services. 1. 1 service X 4 X $450.00............... $ 1,800.00 An Equal Opportunity Employer D. Additional work associated with stubbing the utilities East and North of M.H. #7. The work going to the east was slowed by the unknown telephone duct bank/fiber optic lines along with additional existing utilities that we had to work around. Since these stubs were not part of the bid quantities, you will have to add this length increasing the bid quantity and subtract it from this total or simply pay it as a change order. 1. Sanitary sewer stub toward the East a. Foreman, 9 hrs @ $55.00/hr. ..... b. Laborers (2) ,17 hrs @ $35.00/hr.. '" c. 400 Blhoe, 8.5 hrs @ $175.00/hr... d. 943 loader, 8.5 hrs @ $135.00/hr... f. Material W/I0%.... . . . . . . . . . . . . . . . . . SUBTOTAL 1. Sanitary sewer stub toward the North a. Foreman, 3.5 hrs @ $55.00/hr.... b. Laborers(2),7 hrs @ $35.00/hr...... c. Top man, 3.5 hrs @ $50.00/hr.... d. 400 Blhoe, 3.5 hrs @ $175.00/hr... e. 943 loader, 3.5 hrs @ $135.00/hr... f. Material W/IO%..................... SUBTOTAL TOTAL E. 8" watermain East of manhole #1 1. 3.5 hrs X $450.00/hr................. F. 6" watermain East of manhole #4 1. 2 hrs X $450.00/hr..... .............. G. 6" watermain East of manhole #7 1. 4 hrs @ $420.00/hr..... ..... ......... H. 725mm Rep span East of DS #17 1. 4 hrs @ $420.00/hr..... ...... .... .... I. 300mm HDPE East of DS #10 1. 2 hrs @ $420.00/hr...... .... ......... TOTAL $ 495.00 $ 595.00 $1,487.50 $1,147.00 S 233.00 $3,958.00 $ 192.50 $ 245.00 $ 175.00 $ 612.50 $ 472.50 S 86.00 $1,783.50 $5,741.50 $1,575.00 $ 900.00 $1,680.00 $1,680.00 S 840.0Q $26,591. 50 11': P.O. Box 69 Jordan, MN 55352 (612) 492-5700 FIELD WORK ORDER (FOR EXTRA WORK, TIME & MATERIAL WORK, AND BACKCHARGES) Date ~)...L/1) e..t;rl.e..... \.L B-1 2 - q ~ Bill to () ~ + }' J-F .p I' r 0 r I .('1,.-1 COP Address Project No. Of ~, 3. 1 ., Project Name 1) LA. \ I I --\.-"-' Au...e. Location of Work Performed Lb 5"41 I') fA I L.J ~ A-IJ ..p Nature of Work Performed. (J rf>W ~ ","vfJ (') ('} t~~r S~tI"l} "l...Y" EMPLOYEE ~ h Jrj fY1 ~ 'ZJ.Af Itj't.tu~ /(,,11'\ St~ (\ V\ "" ) &1\1 M ~ l('., f2.u.d.c> 10 ~ f)CA..tt'\ sc. "W\.J +z- LABORERS & SUPERVISIO~ TRADE I fJ-lhouRS M T W T F fiu:uvt~ ~ ~/ 1- i-J.tJCJ' 'f- ~hor (t 2.._0 I "2.~O 12_0 LAB~"SGa TOT A L S S TOT AL I HOURS RA TE EMPLOYEE EQUIP. NO. Do '-L-C.. ltJ 14' ~ 1&-",. 56 -u 7 ~ ../ EQUIPMENT DESCRIPTION I M OJ Lf 5. C,4- T TlA-t . S TOTAL HOURS 2..._0 - ,1 ~-"l-tOURS W T )CI I I 'KI I I I I I I T F S I I 'Z.. ~O I I I I I I I I I I I I I 1)01/\ .:a--J-o"5 (1lJO /~&Ir: r"l I I "lb EQUIPMENT SUB TOTAL DESCRIPTION MATERIAL & OTHER CHARGES I QUANTITY UNIT COST MATERIAL SUB TOTAL REQUESTED BY (SIGNATURE) ~RKO DER R~Rro BY ~ ~? LABOR SUB TOTAL EQUIPMENT SUB TOTAL PROFIT AT _% & O.H, AT % TOTAL BILLED WHITE - TO CUSTOMER YELLOW - MPLS. ACCOUNTING PINK - FIELD OFFICE 1 7 t l' TOTAL RATE I TOTAL TOTAL