HomeMy WebLinkAbout5C - Water Tower Change Order
MEETING DATE:
AGENDA #
PREPARED BY:
REVIEWED BY:
AGENDA ITEM:
DISCUSSION:
CITY COUNCIL AGENDA REPORT
May 5, 2003
SC
Makenzie McCormick, Public Works Coordinator
Bud Osmundson, P.E., Public Works Director
CONSIDER APPROVAL OF A RESOLUTION ACCEPTING A CHANGE
ORDER FOR IMPROVMENTS TO THE TOWER STREET WATER
TOWER, CITY PROJECT NO. 03-01
History
On January 6, 2003, the Council accepted bids and awarded contracts for water
tower reconditioning to Classic Protective Coatings and Champion Coatings.
The purpose of this agenda item is to approve the change order for
improvements to the Tower Street Water Tower.
The Tower Street water tower is currently under reconstruction. The
improvements included in this change order are installing a new hatch and
condensate floor at the bottom of the dry riser and replacing the 16" butterfly
valve at the base of the water tower.
When emptying the water out of the tower so crews could begin construction,
City crews found it was difficult to close the existing 16" valve. In fact, the
valve never completely sealed and was leaking water. Because a faulty valve
was found during the construction process, City staff feels now, while the water
tower is out of service, is the best time to replace the valve. Otherwise, if crews
wait until the water tower construction is finished and the tower is back in
service, we will have to empty the water tower at a later date to replace the
existing valve.
The faulty valve was not found during the inspection, because the hired engineer
relies on City staff to empty the water tower, which is done by opening and
closing the 16" valve. The existing valve was working fine when City staff
opened and closed it for the inspection that was completed in April 2000. The
valve was again opened and closed when the tank was emptied in late March
2003 to begin the water tower reconstruction, and that is when it was found the
valve was faulty. City staff recommends replacing the defective valve during
this contract.
City staff requested that the hatch and opening to the valve pit be modified with
the tower construction. The current hatch is difficult to open and very small for
4qQ3~Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
access. A new hatch and larger opening would make access to the valve pit
much easier and safer for City staff. Since a new hatch was requested, the
engineer suggested installing a new condensate floor with the new hatch. During
the initial inspection, the engineer evaluated the condensate floor as structurally
sound and could be rehabilitated by sandblasting and painting. However, since
City staff requested a new hatch, the engineer recommended that the entire
condensate floor be replaced. The new hatch in the floor will create easier
access for City staff to get to the valve pit below, and will be easier to open.
,.
I
!:
l:~1
fi~
l,
Current Circumstances
We requested change order prices for both the condensate floor and 16" butterfly
valve. The contractor for the Tower Street Tower, Classic Protective Coatings,
submitted bid prices which were reviewed by KLM Engineering, the City's
engineer on the water tower reconditioning project. KLM Engineering
compared the change order prices received from our contractor and deemed them
comparable to market value.
Conclusion
The City's contractor submitted the prices of $5,200.00 to install the new
condensate floor, and $5,125.00 to replace the 16" butterfly valve. The prices
include all of materials needed and the work requested. The contractor also
requested an additional 2-3 days to complete the added work.
ISSUES: This added work requested by City staff will extend the life of the water tower.
City staff recommends approving both items in the change order as requested.
FISCAL IMPACT: Sufficient funds are identified in the City's Capital Improvement program to
perform the reconditioning of the two water towers plus the additional cost for
the condensate floor and 16" butterfly valve. The total amount of the two
contracted bids is $997,527. The CIP estimate was $1,140,000. The total cost of
the two change order items is $10,325. At the April 21, 2003 meeting, the City
Council approved a change order to update the City logo on each tower. That
change order totaled $10,150. Because the bids came in lower than the CIP
estimate, there are sufficient funds to cover the additional expenses of this
change order and the logo change order that was approved at the April 21 st
Council meeting. The Wat~r and Sewer Utility (Operating) Fund is the source of
the funding for the two towers since this is a maintenance item of existing capital
equipment.
ALTERNATIVES: The alternatives are as follows:
1. Approve a Resolution accepting the change order bid prices for the new
condensate floor and 16" butterfly valve in the amount not to exceed
$10,325.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason.
4/30/2003
RECOMMENDED Staff recommends alternative number 1.
MOTION:
REVIEWED BY:
, ublic Works Director
4/30/2003
RESOLUTION 03-XX
MOTION BY: SECOND BY:
WHEREAS, City staff requests a new hatch and condensate floor be installed at the bottom of the
dry riser in the Tower Street Tower pursuant to the water tower reconditioning
project that was approved the January 6,2003 Council meeting; and
WHEREAS, City staff requested the 16" butterfly valve be replaced pursuant to the water tower
reconditioning project approved at an earlier Council meeting, because the existing
valve was found to be defective; and
WHEREAS, Classic Protective Coatings submitted a change order bid price of $5,200.00 for the
new hatch and condensate floor; and
WHEREAS, Classic Protective Coatings submitted a change order bid price of $5,125.00 to
replace the 16" butterfly valve; and
WHEREAS, According to the CIP, there are sufficient funds in the Water and Sewer Fund for the
additional work requested.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
1. The recitals set forth above are incorporated as if fully set forth herein.
2. The City Council authorizes the expenditures from the Water and Sewer Utility Fund for the installation
of a new condensate floor and 16" butterfly valve at the Tower Street water tower in an amount not to
exceed $10,325.00.
Passed and adopted this 5th day of May 2003.
YES
NO
Haugen Haugen
Blomberg Blomberg
LeMair LeMair
Petersen Petersen
Zieska Zieska
{Seal} Frank Boyles, City Manager
4/30/2:P~200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER