CITY COUNCIL AGENDA REPORT
MEETING DATE:
AGENDA #:
PREPARED BY:
AGENDA ITEM:
JUNE 1, 1998
9B
GREG ILKKA, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
CONSIDER APPROVAL OF CONTRACTOR'S CLAIM FOR LOST
OVERHEAD ON PIKE LAKE TRAIL DUE TO THE ELIMINATION OF A
RETAINING WALL.
DISCUSSION:
HISTORY
The City Council approved elimination of a retaining wall from the contract
for construction of Pike Lake Trail for a total contract reduction of ,
$78,142.00 pending receipt of documentation for their overhead.
Attached is a letter from McNamara Contracting, Inc. on this subject. This
change accommodated a developer's request for access to Pike Lake
Trail by providing a graded slope in lieu of the retaining wall.
CURRENT CIRCUMSTANCES
The Contractor allocated $5,510 of overhead to the retaining wall on a
$953,641.85 contract. As part of the change to the contract the
Contractor indicated he needed to recover this full amount. Recovery of
the full amount of overhead was questioned by the Council and the
Contractor was asked to provide documentation to support the claim.
The enclosed letter outlines the request for compensation. As stated, the
Contractor included a 3% overhead factor on the contract. This would
amount to $28,609.25 for the whole contract. Of this amount he allocated
$5,510 to the retaining wall. The $5,510 represents almost 20% of his
overhead on the entire project. He is now requesting recovery of only
$2,344.26, but is claiming additional costs associated with the Change
Order.
Because McNamara assumed he would recover his full overhead amount
when he submitted his costs initially, he did not mark up the new unit
price on the remaining retaining wall work. He is now requesting this
compensation, which by MnDOT specification is allowable at 15%. The
request is for $1086.
162~~ Creek Ave. S.L Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
Further, because he has incurred additional costs on the Change Order
beyond first anticipated he is requesting reimbursement of those costs as
well in the amount of $2,400.
ISSUES
In highway construction, contractors allocate portions of their overhead to
their major work items and not to every line item. In the bidding process
the Contractor allocated $5,510 of overhead for the entire contract to the
retaining wall. This amount has nothing to do with the amount of
overhead it costs to actually build the retaining wall but is merely part of
his 3% overhead factor which he distributed to the major work items on
the contract. Because of the elimination of the retaining wall he has no
way to recover this overhead.
The Contractor's original request for overhead recovery was $5,510.
Because he feels he was treating the City fairly, but is not receiving the
same treatment in return, he now feels he must claim reimbursement for '
additional costs incurred which were not initially anticipated for a total of
$5,830.26.
CONCLUSION
The Contractor initially requested 100% overhead recovery, but is now
requesting recovery of only $2,344.26. However, the Contractor did not
originally put a mark-up on his sub-contractor's prices and he has incurred
additional costs he did not originally anticipate. He is now requesting
reimbursement of these costs as well. The Contractor's total request is
$5,830.26. The Contractor's claim has now become more involved than
the original request to recover his overhead. In order to resolve this issue
once and for all, staff recommends approval of the original request for
$5,510. We believe the contractor would accept this offer as settlement
of the entire claim.
FISCAL IMPACT:
If approved, the change in contract cost would be an additional $5,510.
This would still represent a total contract deduction of $72,632,00.
AL TERNA TIVES:
There are three alternatives for the City Council to consider:
1. Approve the contractor's claim for reimbursement of lost overhead and
increased costs due to elimination of a retaining wall on Pike Lake Trail in
the amount of $5,510 and direct staff to prepare a change order for
signature by the Mayor and City Manager.
PLTCOI4.DOC
2. Approve a portion of the contractor's claim for reimbursement of lost
overhead and increased costs due to elimination of a retaining wall on
Pike Lake Trail and direct staff to prepare a change order for signature by
the Mayor and City Manager.
3. Deny this item and provide staff with direction.
RECOMMENDED
MOTION:
Motion and second to approve the contractor's claim for reimbursement of
lost overhead and increased costs due to elimination of a retaining wall on
Pike Lake Trail in the amount of $5,510 and direct staff to prepare a
change order for signature by the Mayor and City Manager.
REVIEWED BY:
PLTC014.DOC
: ASPHALT CONSTRUCTION
May 18, 1998
R~n1"'C'"
~~lJ'.,. .
HAY 20 1998
Mr. Greg llkka, P.E.
Public Works Director/City Engineer
16200 Eagle Creek Avenue S.E.
Prior Lake, MN 55372-1714
Re: Pike Lake Trail, Project No. 97-17
Dear Greg:
This letter serves as McNamara Contracting, lnc's claim for reimbursement for overhead and
profits. This claim is a result of a revised construction plan as described in Change Order #1 on
the above referenced project.
The revisionsjncludedin Change Order #1 have caused the following:
1. Reduced the recovery of overhead costs incurred by McNamara
in the original bidding of the project. McNamara includes a 3.0%
overhead factor in each project bid. This is based upon McNamara's
history of bidding costs. Such costs include estimator and office
staff time to review plans, project site, bid documents, office
equipment, and plan costs. The following is our lost overhead:
Change Order #1 - Deductions 93,210.00
Additions (approved) 15.068.00
78,142.00 x 3%
$ 2,344.26
2. No markup has been included on the items to be paid to Rosti
Construction. The prime contractor normally marks-up sub-
contractor prices. This enables the Prime Contractor to
recover costs incurred on behalf of the subcontractor such
as bonding, scheduling, supervising, and processing payments.
The markup also is to include a profit margin. Change Order # 1
approved prices from Rosti Without any markup for McNamara.
McNamara believes it should be compensated for these items
atour normal 15% markup rate: 7,240.00 x 15%
1,086.00
500l16Oth Street West · Rosemount, Minnesota 55068-1304
Office (612) 322-5940 · Fax (612) 322-5944 · Plant (612) 322-5946
3. McNamara has incurred substantial additional overhead costs
due to Change Order # 1. Extra time has been spent by the job
superintendent, project manager, estimator, and office personnel
in the fOIm of additional site meetings, revised quantity and
price reviews, project scheduling, project supervision, and
contract documents processing. McNamara estimates this cost
to be 40 hours x $60.00
2.400.00
Total claim for reimbursement for overhead and profits
$ 5,830.26
Our original request for reimbursement for overhead costs was for $5,510.00. That amount was
requestedgased upon our belief the city realized that McNamara had and 'will incur substantial
costs due to Change Order # 1.
Please review the above justification and present it to the City Council at your earliest .
opportunity.
Sincerely,
~tj:IA
Controller
McNamara Contracting, Inc.