HomeMy WebLinkAbout5J - City Hall & Police Station Landscape Prj.
4646 Dakota Street S.E.
Prior Lake, MN 55372-1714
CITY COUNCIL AGENDA REPORT
MEETING DATE:
AGENDA #:
PREPARED BY:
APRIL 16, 2007
5J
AL FRIEDGES, PARKS AND FLEET SUPERVISOR
AGENDA ITEM:
CONSIDER APPROVAL OF A RESOLUTION AUTHORIZING STAFF TO
PURCHASE AND INSTALL THE NECESSARY MATERIAL FOR THE CITY
HALL AND POLICE STATION LANDSCAPE PROJECT
DISCUSSION:
Introduction
The purpose of this agenda item is to authorize staff to purchase and install
the necessary materials needed to complete the City Hall and the Police
Station landscape project.
Historv
As part of the new City Hall and Police Station building projects, landscaping
was bid as an alternate. This included the purchase and installation of trees,
shrubs, flowers, native plant materials, sod, seed, mulch, compost material
and edging. The low bid for the purchase and installation of these items was
$86,000. This alternate was rejected since we were confident that City staff
could do a better job for less money.
Current Circumstances
By utilizing staff labor to purchase and install the landscape design provided by
Wold Architects and Engineers, a cost savings can be achieved.
Staff estimates a cost of $2,500 to purchase compost material for the
landscape beds and $2,500 for sod, The following quotes depict the cost for
remaining project materials:
Vendor Mn Valley Bachman's Shemin Landscape
Wholesale Nursery Supplv
Sub-total $36,788.56 $33,849.09 $32,826.64
Tax $2,391,26 $2,200.19 $2,133.73
Total $39,179.82 $36,049.28 $34,960,37
By utilizing both full time and seasonal Parks Maintenance employees, staff
estimates that it will take 400 hours to perform the landscape functions.
A rate of $25.00 per hour for full time and $10.00 per hour for seasonal
employees was used to calculate City staff costs The following is a total cost
estimate to have City staff perform the landscape project:
R\Council\Agenda Reports\2007\04 16 07\ch pd landscape project agenda.DOC
www.cityofpriorlake.com
Phone 952.447.9800 / Fax 952.447.4245
$34,960.37
$2,500.00
$2,500,00
$6,000.00
$1,600.00
$47,560.37
ISSUES:
Because the City staff is responsible for the ongoing maintenance of these
City properties, our landscaping work is far more extensive than that of a
private contractor. We will assume, for example, that there is adequate black
dirt to sustain the turf. By the same token the landscape bids are prepared to
maximize shrub and tree well being. If personnel costs exceed the above
estimates, we will report the increase to the City Council.
FINANCIAL
IMPACT:
The funds for the City Hall and Police Station landscape project will be drawn
from the Construction Fund for a total cost not to exceed $39,960.37 (420-
70205-530). The City Hall/Police Station Construction Fund has $40,000
reserved for landscaping.
Staff costs will be drawn from the 2007 Park Maintenance General Fund
Budget.
ALTERNATIVES:
1. Approve a resolution authorizing:
~ The purchase of landscape materials from Shemin Landscape
Supply for $34,960,37.
~ The purchase of compost material for $2,500.00.
~ The purchase of sod for $2,500.00.
~ Funds for staff time spent for $7,600.00.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason and provide staff with direction.
RECOMMENDED
MOTION:
Alternative #1.
;<(;t/I
Steve Albrecht, Public Works Director/City Engineer
---
R\Council\Agenda Reports\2007\04 16 07\ch pd landscape project agenda. DOC
4646 Dakota Street S.E.
Prior Lake, MN 55372-1714
RESOLUTION 07 -xx
A RESOLUTION AUTHORIZING PURCHASE OF MATERIALS AND THE STAFF LABOR
COSTS NECESSARY TO COMPLETE THE CITY HALL AND POLICE STATION
LANDSCAPE PROJECT
Motion By:
Second By:
WHEREAS, The City of Prior Lake is committed to constructing and maintaining City
property in an environmentally responsible and aesthetically pleasing condition;
and
WHEREAS, The alternate bid for the purchase and installation of landscape materials for
City Hall and the Police Station was $86,000; and
WHEREAS, Quotes have been solicited for the landscape materials necessary to perform
the City Hall and Police Station project, as follows:
Vendor MN Valley Bachman's Shemin Landscape
Wholesale Nursery Supply
Sub-total $36,788.56 $33,849.09 $32,826.64
Tax $2,391.26 $2,200.19 $2,133.73
Total $39,179.82 $36,049.28 $34,960.37
WHEREAS, The compost material needed for the planting beds is a cost not to exceed
$2,500; and
WHEREAS, The sod needed for the City Hall and Police Station landscape project is a cost
not to exceed $2,500; and
WHEREAS, The funds for the City Hall and Police Station landscape project will be drawn
from the Construction Fund for a total cost not to exceed $39,960.37 (420-
70205-530); and
WHEREAS, The estimated staff time to complete the City Hall and Police Station landscape
project is a cost of $7,600 and will be drawn from the 2007 General Fund
Budget.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. Staff is directed to place an order with Shemin Landscape Supply for a total amount not to
exceed $34,960.37.
R:\Council\Agenda Reports\2007\04 16 07\ch pd landscape project reso.DOC
www.cityofpriorlake.com
Phone 952.447.9800 / Fax 952.447.4245
3. City staff is authorized to expend up to $2,500.00 for compost material.
4. City staff is authorized to expend up to $2,500.00 for sod.
5. The estimated staff time spent cost to complete the project is $7,600.00
PASSED AND ADOPTED THIS 16TH DAY OF APRIL 2007.
Haugen Hauaen
Erickson Erickson
Hedberg Hedbera
LeMair LeMair
Millar Millar
YES
NO
Frank Boyles, City Manager