HomeMy WebLinkAbout3H - Downtown Street Improvements Change Order
CONSENT AGENDA:
PREPARED BY:
SUBJECT:
DATE:
INTRODUCTION:
BACKGROUND:
HERITAGE
1891
COMMUNITY
1991
r-gJSOjV
2Q91
3 (h)
BRUCE LONEY, ASSISTANT CITY ENGINEER
CONSIDER APPROVAL OF CHANGE ORDER NO.1,
PROJECT 89-l1, DOWNTOWN STREET IMPROVEMENTS
JULY l6, 1990
During the course of construction for Project
#89-1l, additional work beyond the Contract
was done by the Contractor. A Change Order
for this additional work has been prepared and
enclosed in the Agenda packet for Council
approval.
The contractor, McNamara Contracting Company,
Inc. and his subcontractors, have performed
additional work which was not included in the
original contract. The additional work is
described and itemized costs are shown on the
enclosed memorandum and Change Order form. A
total of ten (10) additional items are
described with the total cost of the Change
Order being $l7,042.25.
Items #1 throu9h #5 and #7 are associated with
underground ut1lity and storm sewer work. In
most cases on these items, the exact scope of
work necessary was not known until the
Contractor had done the excavation work in the
particular area. Item #6 was for the milling
of existing CSAH 21 bituminous pavement and
was deemed necessary so as to provide a smooth
patch on this County highway.
Items #8 through #10 are additional work and
expenses associated with the Main Avenue
Parking Lot and represents the majority of the
Change Order amount. The right-of-way was not
available until this year resulting in a delay
for the Contractor and Item #8 is for these
additional expenses. Item #9 is for a
complete electrical system with electrical
receptacles for Christmas lights; future Town
Center sign lighting, and an irrigation system
circuit. Item #10 is for the irrigation
4629 Dakota S1. S.E., Prior Lake, Minnesota 55372 / Ph. (612) 447-4230 / Fax (612) 447-4245
RECOMMENDATION:
BUDGET IMPACT:
ACTION REQUIRED:
system in the parking lot area which consists
of several trees and shrubs.
The total amount of this Change Order is
$17,042.25 with the original contract amount
being $871,738.65. This represents a 2.0%
increase in the actual contract.
The recommendation is to approve Change Order
#1.
This amount will be paid from the Construction
Fund and has been included with this month's
construction voucher. Project #89-ll is
nearly complete with a current contract amount
including Change Order #1 at $819,928.97 which
is less than the original contract amount of
$871,738.65.
Make a motion as part of the Consent Agenda to
approve Change Order #1 for Project #89-1l
authorizing the Mayor and City Manager to
sign the Change Order.
HERITAGE
1891
COMMUNITY
1991
Q8J!ZJ;. ~/~
2Q9f
CHANGE ORDER
CITY OF PRIOR LAKE
4629 DAKOTA STREET S.E.
PRIOR LAKE, MN. 55372
DATE:
TO:
FOR:
FOR:
July 10, 1990 CHANGE ORDER NO. 1
McNamara Contractinq Company, Inc.
proiect No. 89-ll, Downtown Street Improvements
City of Prior Lake, Minnesota
You are hereby directed to make the following change to your
contract dated June 19, 1989 . The change and
the work affected thereby is subject to all contract stipulations
and covenants. This Change Order will (increase) the contract
sum by Seventeen Thousand Forty Two and ------------- 25/l00
Dollars (l7,042.25 ).
Add the following: See attached memorandum for specific details:
Item 1 - Time delay of crew for field design change $ 349.60
Item 2 - Time and material for replacing existing $l,354.l4
gate valve boxes.
Item 3 - Labor for connecting roof drain $ 74.75
Item 4 - Labor & equipment for connecting roof $ 540.79
drain to storm sewer srstem
Item 5 - Labor & equipment for 1nvestigating $ 334.65
water main leak
Item 6 - Labor & mobilization for milling existing $ 370.88
CSAH 21 bituminous pavement
Item 7 - Labor & equipment to straighten gate valve $ l8l.13
box
Item 8 - Additional expenses incurred by Contractor $ 55l.42
due to one year delay on Main Ave. Parking
Lot
Item 9 - Electrical system on Main Ave. Parking Lot $8,213.39
Item 10- Irrigation system on Main Ave. Parking Lot $5,071.50
NET CHANGE ORDER
$17,042.25
4629 Dakota St. S.E., Prior Lake, Minnesota 55372 / Ph. (612) 447-4230 / Fax (612) 447-4245
Amount of Original Contract
Additions approved to date
Deductions approved to date
Contract amount to date
Amount of this Change Order
Revised Contract Amount
(Nos. )
(Nos. )
(Add) (VlNSln) (NU.1WiaUJfEJ)
~
87l,738.65
0.00
0.00
871.738.65
17.042.25
888.780.90
DATE:
TO:
FOR:
FOR:
December 20, 1989 CHANGE ORDER NO. 1
McNamara Contractinq Company, Inc.
Proiect No. 89-11, Downtown street Improvements
City of Prior Lake, Minnesota
Approved as to Form:
Approved
CITY OF PRIOR LAKE
Owner
Respectfully Submitted,
By
Mayor
Date
CITY OF PRIOR LAKE
ENGINEERING DEPARTMENT
By
City Manager
~
Date
Bruce Loney
Project Engi er
Approved McNamara Contractinq Co. Inc.
Contractor
By
Date
TO:
FROM:
SUBJECT:
DATE:
HER/TAGE
189/
COMMUNITY
1991
18J.'5f)~k~
2Q91
LARRY J. ANDERSON, DIRECTOR OF PUBLIC WORKS
BRUCE LONEY, ASSISTANT CITY ENGINEER
PROJECT 89-1l CHANGE ORDER NO. 1
JULY 10, 1990
On the above referenced project, extra work items were required
above the contract scope. The extra work items are listed below
with the associated costs and date when the work was completed.
These costs have been tentatively agreed to by the contractor,
McNamara Contracting Co., Inc.
EXTRA WORK ITEM DESCRIPTION & COST
1.) One hour time delay of subcontractor's storm sewer crew in
making field design change of the 36" corrugated metal pipe
on Duluth Avenue.
ASSOCIATED COST
AMOUNT
July 10, 1989
1 hr. 952 Liehberr backhoe @ $110.00/hr.
1 hr. 380 Komatsu loader @ $85.00/hr.
1 hr. Foreman W/Truck @ $44.00/hr.
1 hr. Pipe layer @ $32.50/hr.
1 hr. Laborer @ $32.50/hr.
$ 110.00
$ 85.00
$ 44.00
$ 32.50
$ 32.50
SUBCONTRACTOR TOTAL......................... . $ 304. 00
GENERAL CONTRACTOR ADMINISTRATION (15%) $ 45.60
NET TOTAL FOR ITEM NO. 1.....................$ 349.60
4629 Dakota St. S.E., Prior Lake, Minnesota 55372 / Ph. (612) 447-4230 / Fax (612) 447-4245
2.) Extra time and material in replacing existing gate valve
boxes which were approximately fifty years old and in a
deteriorated condition. Existing gate valves were repacked
and valve boxes were found to be in need of replacement upon
excavation to repack existing gate valves.
ASSOCIATED COST
July 10, 1989
3 EA - 17" C.J. Valve Box, Top & Cover @
$43.88/EA.
3 EA - 26" C.I.V.B. Ext. @ $44.62/EA
3 EA - 6" Round C.I.V.B. Base @ $35.35/EA
July ll, 1989
3 EA - 17" C.J. Valve Box, Top & Cover @
$43.88/EA.
3 EA - 26" C. I. V . B. Ext. @ $44. 62/EA
3 EA - 6" Round C.I.V.B. Base @ $35.35/EA
July l2, 1989
l&l/2 hr. Foreman W/Truck @ $44.00/hr.
1 EA - 17" C.J. Valve Box, Top & Cover @
$43.88/EA.
1 EA - 26" C.I.V.B. Ext. @ $44.62/EA
1 EA - 6" Round C.I.V.B. Base @ $35.35/EA
July 13, 1989
1/4 hr. Foreman W/Truck @ $44.00/hr.
1 EA - 17" C.J. Valve Box, Top & Cover @
$43.88/EA.
1 EA - 26" C.I.V.B. Ext. @ $44.62/EA
1 EA - 6" Round C.I.V.B. Base @ $35.35/EA
July 24, 1989
1 EA - 6" Gate Valve Box W/Cover @ $109.71
AMOUNT
$ 131. 64
$ 133.86
$ 106.05
$ 131.64
$ l33.86
$ 106.05
$
$
$
$
$
$
$
$
$
66.00
43.88
44.62
35.35
11. 00
43.88
44.62
35.35
109.71
SUBCONTRACTOR TOTAL.........................$1,177.51
GENERAL CONTRACTOR ADMINISTRATION (15%) $ 176.63
NET TOTAL FOR ITEM NO. 2....................$1,354.14
3.) Connection of 8" PVC SDR 35 roof drain from st. Michael's
Church to new 27" RCP storm sewer. Roof drain was previously
connected to old storm sewer system and was detected upon
placement of 27" storm sewer mainline and was not shown on
the plans.
ASSOCIATED COST
July 11, 1989
1 hr. Pipe1ayer @ $32.50/hr.
1 hr. Laborer @ $32.50/hr.
AMOUNT
$ 32.50
$ 32.50
SUBCONTRACTOR TOTAL..........................$ 65.00
GENERAL CONTRACTOR ADMINISTRATION (15%) $ 9.75
NET TOTAL FOR ITEM NO. 3.....................$ 74.75
4. )
Connection of roof drain of st. Michael's parsonage to
27" RCP storm sewer. Roof drain was previously connected
old storm sewer srstem and was detected upon placement of
storm sewer mainl1ne and was not shown on the plans.
new
to
27"
ASSOCIATED COST
AMOUNT
July 17, 1989
3 hr. JD 510 Backhoe @ $69.00/hr.
3 hr. Foreman W/Truck @ $44.00/hr.
3 hr. Laborer @ $32.50/hr.
1/2 hr. Compactor @ $67.50/hr.
$ 207.00
$ 132.00
$ 97.50
$ 33.75
SUBCONTRACTOR TOTAL....... . . . . . . . . . . . . . . . . . . . $ 470. 25
GENERAL CONTRACTOR ADMINISTRATION (15%) $ 70.54
NET TOTAL FOR ITEM NO. 4.....................$ 540.79
5.) Underground utility subcontractor's crew time for
investigating possible watermain leak on Arcadia Avenue.
Also crew time for working watermain gate valves so that
the water could be shut off to permit the replacement of an
existing fire hydrant on Arcadia Avenue.
ASSOCIATED COST
AMOUNT
July
20, 1989
2 hr. JD 510 Backhoe @ $69.00/hr.
2 hr. Foreman W/Truck @ $44.00/hr.
2 hr. Laborer @ $32.50/hr.
$ 138.00
$ 88.00
$ 65.00
SUBCONTRACTOR TOTAL..... . . . . . . . . . . . . . . . . . . . . . $ 291. 00
GENERAL CONTRACTOR ADMINISTRATION (15%) $ 43.65
NET TOTAL FOR ITEM NO.5..................... $ 334.65
6.) Mobilization and time for milling of bituminous pavement on
CSAH 21 by Arcadia Avenue. New concrete curb and gutter was
placed on the south side of CSAH 21 closing Arcadia Avenue
from CSAH 21. After the curb was placed, the bituminous
pavement needed to be patched and milling of the existing
pavement was necessary to obtain a smooth surface.
ASSOCIATED COST
AMOUNT
September 14, 1989
1&1/2 hr. mobilization of milling equipment
@ $90.00/hr.
1&1/2 hr. milling equip. time @ $125.00
GENERAL CONTRACTOR ADMINISTRATION (15%)
$ 135.00
$ l87.50
$ 48.38
NET TOTAL FOR ITEM NO. 6.....................$ 370.88
7.) At Bass street and West Avenue, a gate valve box had to be
straightened so as to allow a gate valve key to be placed.
ASSOCIATED COST
September 14, 1989
1 hr. John Deere Backhoe @ $60.00/hr.
3 hr. Laborer @ $32.50/hr.
GENERAL CONTRACTOR ADMINISTRATION (15%)
AMOUNT
$ 60.00
$ 97.50
$ 23.63
NET TOTAL FOR ITEM NO. 7.....................$ 181.13
8.) Additional expenses incurred by the Contractor due to the one
year delay in obtaining the right of way for the Main Avenue
Parking Lot.
ASSOCIATED COST
AMOUNT
May - June, 1990
Man Hours (316 Hr. @ $.92/Hr. Increase $
Equipment Hours 245 Hrs. @ 5 gal/Hr.=1225 gal.
1225 gallon @ $.04/gal Increase (Bituminous) $
Utility Price Increases for Plant $
Asphalt Price Increase $ll.30 ton @lO.60/ton $
$
GENERAL CONTRACTOR ADMINISTRATION (l5%) $
290.72
49.00
20.00
l19.78
479.50
71. 92
NET TOTAL FOR ITEM NO.8.......... .. .. . .. .. .. $ 551. 42
9. )
Complete electrical
for the Main Avenue
connection for the
Parking Lot.
system for the lightin9 and power outlets
Parking Lot. Addit10nal circuit and
irrigation system on the Main Avenue
ASSOCIATED COST
AMOUNT
May - June, 1990
Original quote for electrical system
Additional circuit for irrigation system
Electrical connection for irrigation system
GENERAL CONTRACTOR ADMINISTRATION (15%)
$6,542.00
$ 457.74
$ 142.34
7,142.08
$1,071. 31
NET TOTAL FOR ITEM NO. 9....................$8,213.39
10.)Complete irrigation system for the Main Avenue Parking Lot
area including all labor and materials and warrantr against
defective workmanship for two years after installat1on.
ASSOCIATED COST
AMOUNT
May - June, 1990
Original quote for irrigation system
GENERAL CONTRACTOR ADMINISTRATION (15%)
$4,410.00
$661.50
NET TOTAL FOR ITEM NO. 10...................$5,071.50
TOTAL TO DATE
ITEM NUMBER ITEM TOTAL
1 $ 349.60
2 $l,354.14
3 $ 74.75
4 $ 540.79
5 $ 334.65
6 $ 370.88
7 $ 181.13
8 $ 551.42
9 $8,213.39
10 $5,071. 50
TOTAL ITEMS l-10 $17,042.25
The contract amount for Project NO. 89-ll is $87l,738.65. This
change order to date would increase the contract amount by
$l7,042.25 or 2.0% of the initial contract amount. Remaining
work items on this job includes only punchlist items which are
mainly restoration items.