HomeMy WebLinkAbout03-69 RESOLUTION 03-69
;IDER APPROVAL OF A RESOLUTION ACCEPTING A CHANGE ORDER
g TO THE TOWER STREET TOWER, CITY PROJECT NO. 03-01
MOTION BY:LEMAIR SECOND BY: BLOMBERG
WHEREAS, City staff requested a new hatch and condensate floor be installed in the Tower
Street Tower pursuant to the water tower reconditioning project approved at an
earlier Council meeting; and
WHEREAS, City staff requested the 16" butterfly valve be replaced pursuant to the water tower
reconditioning project approved at an earlier Council meeting, because the existing
valve was found to be defective; and
WHEREAS, Classic Protective Coatings submitted a change order bid price of $5,200.00 for the
new condensate floor; and
WHEREAS, Classic Protective Coatings submitted a change order bid price of $5,125.00 to
replace the 16" butterfly valve; and
WHEREAS, According to the CIP, there are sufficient funds in the Water and Sewer Fund for the
additional work requested.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
1. The recitals set forth above are incorporated as if fully set forth herein.
2. The City Council authorizes the expenditures from the Water and Sewer Utility Fund for the installation
of a new condensate floor and 16" butterfly valve at the Tower Street water tower in an amount not to
exceed $10,325.00.
Passed and adopted this 5th day of May 2003.
YES NO
Haugen · Absent Haugen Absent
Blomberg X Blomberg
LeMair X LeMair
Petersen X Petersen
Zieska X Zieska
{Seal} Frank Boyles,~ty ~anager
16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245