HomeMy WebLinkAbout6B - Forest Circle & Forest Oaks
AGENDA NUMBER:
PREPARED BY:
SUBJECT:
DATE:
INTRODUCTION:
BACKGROUND:
DISCUSSION:
6B
BRUCE LONEY, ASSISTANT CITY ENGINEER
CONSIDER APPROVAL OF RESOLUTION 93-53
APPROVING PLANS AND SPECIFICATIONS AND
ORDERING BIDS FOR FOREST CIRCLE AND FOREST
OAKS FIRST ADDmON IMPROVEMENTS AND HOLY
CROSS LUTIIERAN CHURCH SEWER EXTENSION
JULY 6,1993
The purpose of this item is to consider the approval of the plans
and specifications for Project #93-13, Forest Circle and Forest
Oaks First Addition improvements, and Project #93-06, Pike Lake
Trail sanitary sewer extension to serve the Holy Cross Lutheran
Church. If plans are approved by the Council, then adoption of
Resolution #93-53 is in order to authorize the Advertisement for
Bids on the projects.
On May 17, 1993, the Council adopted Resolution #93-29 ordering
the preparation of plans and specifications for Project #93-13,
Forest Oaks and Forest Oaks 1st Addition improvements. On June
21, 1993, the City Council passed a motion authorizing the plan
preparation for the Pike Lake Trail sanitary sewer extension by the
City's consultant, Maier Stewart & Associates, Inc. Both projects
have been designed by Maier Stewart with plans and specifications
to be presented to the Council at the July 6, 1993 meeting.
The Feasibility Project Cost Estimate for Project #93-13 was
$110,000.00 including 30% indirect project costs. Since the
feasibility study, the developer requested that the grading of the
street and two lots be included in the project and assessed on the
property. This addition was done and incorporated within the
signed Developer's Agreement. Cost of the project will be assessed
to the benefitting properites with the developer of Forest Oaks First
Addition being assessed for all the project except for $2,000.00 for
each of the three existing residential homes off of Forest Circle.
The initial construction estimate to extend sanitary sewer on Pike
Lake Trail from CSAH 42 to the south end of the Holy Cross
Lutheran Church parcel is $40,000.00. Cost of the project will be
paid for by a combination of Trunk Reserve funds and sanitary
sewer lateral fees from the Holy Cross Lutheran church building
project. The sewer line will be constructed in such a way to allow
4629 Dakota 51. 5.E., Prior Lake, Minnesota 55372 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPlDYER
traffic on Pike Lake Trail as this road is the only access for several
residents.
An acceptable bid opening for Project #93-13 and #93-06 would be
at 10:00 A.M. on August 2, 1993. The bid opening results will be
presented to the Council at the August 2, 1993 Council Meeting.
RECOMMENDATION: Approval of Resolution #93-53 would be appropriate subject to
Council direction.
ALTERNATIVES: The alternatives are as follows:
1. Approve the Plans and Specifications and approve
Resolution #93-53 ordering an Advertisement for Bid with
a bid opening for August 2, 193 at 10:00 A.M.
FINANCIAL IMPACT:
2. Table this item for a specific reason.
3. Deny the project at this time.
The cost of Project #93-13 will be recovered through Special
Assessments. The cost of Project #93-06 will be paid for with the
Trunk Reserve Funds and the sewer lateral fees collected by the
Holy Cross Lutheran Church building project.
ACTION REQUIRED:
Make a motion to approve Resolution #93-53.
AGEN6B.WRT
'RSll353"
RESOLUTION 93-53
RESOLUTION APPROVING PLANS AND SPECIFICATIONS
AND ORDERING ADVERTISEMENT FOR BIDS ON
FOREST CIRCLE AND FOREST OAKS FIRST ADDITION
IMPROVEMENT (PROJECT 93-13) AND ON PIKE LAKE TRAIL
SANITARY SEWER EXTENSION IMPROVEMENT (PROJECT 93-06)
MOTION BY:
WHEREAS,
SECONDED BY:
pursuant to Resolution 93-29 which the City Council approved on May 17,
1993, and pursuant to a motion which the City Council approved on June
21, 1993, the City Engineer has prepared plans and specifications for the
improvement of Forest Circle from Fish Point Road to end terminus and
within Forest Oaks First Addition by the construction of grading, sanitary
sewer, watermain, storm sewer, aggregate base, concrete curb and gutter,
bituminous surfacing and appurtenant work; and for the improvement on
Pike Lake Trail from CSAH 42 to approximately 700 feet south by the
construction of sanitary sewer and appurtenant work; .
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA, that
I. Such plans and specifications, a copy of which is attached hereto and
made a part of hereof, are hereby approved.
2. The City Manager shall prepare and cause to be inserted in the official
paper and in the Construction Bulletin an advertisement for bids upon the
making of such improvement under such approved plans and
specifications. The advertisement shall be published not less than 21 days
prior to bid opening, shall specify the work to be done, shall state that bids
will be opened, and that all bids will be received by the City until 10:00
A.M. on August 2, 1993, at which time they will be publicly opened in the
Council Chambers of City Hall by the City Engineer.
No bids will be considered unless sealed and filed with the City Manager
and accompanied by a cash deposit, cashier's check, bid bond, or certified
check payable to the City of Prior Lake for five (5) percent of the amount
of such bid.
4629 Dakota 51. 5.E., Prior Lake, Minnesota 55372 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPlDYER
3. The City reserves the right to reject any and all bids for any reason as
determined solely by the City.
Passed and adopted this _ th day of
, 1993.
YES
NO
Andren
Fitzgerald
Kedrowski
Scott
White
Andren
Fitzgerald
Kedrowski
Scott
White
Frank Boyles
City Manager
City of Prior Lake
{ Seal}