HomeMy WebLinkAbout6A - 1994 Prior Lake/Spring Lake Improvement Projects Res. 93-87
AGENDA #:
PREPARED BY:
SUBJECT:
DATE:
INTRODUCTION:
STAFF AGENDA REPORT
6A
JOEL RUTHERFORD, WATER RESOURCES COORDINATOR
CONSIDER SUPPORTING AND SPONSORING THE PRIOR -
SPRING LAKES IMPROVEMENT PROJECT AND CONSIDER
ADOPTING RESOLUTION 93-87
OCTOBER 18, 1993
The purpose of this Agenda item is to consider sponsorship of the
Prior - Spring Lakes Improvement Project, which is a six year work
plan being proposed by the Prior Lake/Spring Lake Watershed
District. This project includes an implementation plan which
includes improvements designed to improve water quality in the
lakes, wetlands and other water bodies of the watershed.
As part of this sponsorship, the City would support the Watershed
in their application for a Clean Water Partnership Phase II - Project
Implementation Grant. This Grant, if awarded, would provide
approximately 50% cost share for most of the projects. The
Watershed has indicated the application deadline for this grant is
late October of this year.
If the Council elects to be a sponsor of this project, the City would
be eligible for matching funds to help pay for storm water capital
improvement projects implemented over the next six years. The
Council is being asked to adopt the attached resolution which
authorizes the Watershed District Manager to be the project
representative. The resolution also indicates the estimated cost of
the entire project, as well as the estimated costs to the City if all the
projects are completed.
If a grant is awarded, the Council will be asked over a six-year
period to consider the projects included in the plan for which the
City is the "Lead Local Agency". This consideration would be done
during the normal budget process. If the Council elects to budget
money for these future projects, and the projects are implemented,
the City would receive the funds awarded as part of the grant.
-1-
4629 Dakota St. S.E., Prior Lake, Minnesota 55372 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPWYER
BACKGROUND:
DISCUSSION:
If a grant is not awarded, the City could either choose to look at
alternative funding sources, or reject projects for which funding Is
not available.
Through the EPA's Clean Lakes Program, the Prior Lake/Spring
Lake Watershed District has completed a Implementation Plan for
the Diagnostic/Feasibility Study of Prior and Spring Lakes.
This implementation plan includes several projects, all of which
have the goal of improving water quality in the watershed. Several
of the projects are capital improvement projects which would
benefit Upper and Lower Prior Lakes by helping to reduce
phosphorus levels and other nutrients which have caused
degradation of the lake waters. One project will be used to
inventory water quality basins in the watershed. Other projects
included in the plan are education projects which will show
residents how they can help reduce the amount of nutrients getting
into our water bodies.
The funding for this implementation plan would come from various
agencies and from a grant, if awarded. The watershed district is
asking the city to support and help fund this program.
The implementation plan proposed by the watershed district
includes many projects. The complete study, which is about 2
inches thick, is available for review at City Hall. However, an
Executive Summary for this study has been included with this
report. The Diagnostic/Feasibility study was completed by
Montgomery Watson, the consulting firm hired by the Watershed
District.
To be eligible for a Clean Water Partnership Phase II - Project
Implementation Grant, a study was required which included an
implementation plan. The Watershed District and City staff have
worked together to include projects in this plan which are part of the
City's preliminary stormwater capital improvement program. By
receiving grant funds, these projects could be partially supported
with grant money.
It should be made clear that the resolution, proposal, and any
commitment by the City, at this point, is contingent on a grant being
awarded. The Watershed District has committed to a project
whether a grant is awarded or not. Their project list, however would
most likely be scaled back without the financial support of a grant.
The City has also made a commitment (through the establishment
of a storm water utility fee) to complete projects designed to
improve water quality. The purpose of the proposal submitted by
the watershed is to apply for a grant to help fund the projects
already determined to be important. If the grant is not awarded, it is
understood a different approach is necessary to complete the
projects proposed.
-2-
An award of a grant would be based on the premise that the
completed plan would improve water quality to a degree as
indicated in the study. However, there will be flexibility in the future
as to how those improvements in water quality will be obtained. The
project list and schedule, as included in the application, will be
re-evaluated, and possibly revised, each year. The council will be
given an opportunity to alter some of the projects if higher priority
projects are identified in the future.
A summary of projects the City is being asked to help sponsor is
listed below. Attached to this report is Exhibit 1 which summarizes
the project costs.
Slgnage and Street Sweeping Coordination is part of the Public
Information/Education program. Because the City already has a
street sweeping program, the main expenditures for this item would
be to stencil certain catch basin areas with "Drains to Prior Lake",
or something similar, to alert residents that anything entering the
storm sewer, including grass clippings, etc., will end up in the lake.
The cost for this project is from in-kind service of 82 hours.
Water Quality Basin 1 Improvement is the impoundment structure
proposed at Holly Circle and Cates Street. The City received a
grant from the Minnesota Board of Water and Soil Resources
(BWSR) for half the cost of this project, up to a certain amount.
However, when the bids were 2 1/2 times the engineer's estimate,
the project was canceled. If the PUSLWD receives their grant, and
the City receives an extension for the BWSR grant, it may be
possible to construct the structure with almost 100% grant money. It
may require reducing the scope of the project slightly to lower the
construction costs, an option already suggested as a way to get the
project completed.
Water Quality Basin 4 Improvement is to convert a pond near
Beach Street from a dry pond to a wet pond. This project was
included in the plan with the assumption that a valve was never
installed, and therefore the pond would remain dry if not improved.
However, a valve was installed, so this project may involve
improvement by enlarging the capacity of the pond, to provide
additional storage of sediment, or a different project may be
substituted later.
A Water Quality Basin Inventory has been scheduled to be
included in the Comprehensive Storm Sewer plan which should be
completed this winter.
The lake-wide Aquatic Macrophyte Management Plan is
necessary to facilitate a long-term comprehensive aquatic
macrophyte management plan, including the control of Eurasian
Water Milfoil.
-3-
An Aquascaplng plan is a promotion to educate lake shore owners
of the benefits proper shoreline landscaping can have on water
quality in the lakes.
Monitoring of Spring and Prior Lakes has been proposed for 1996
and 1999, to determine the effectiveness of the projects in the
implementation plan.
A Ferric Chloride System is proposed for installation along County
Ditch 13 at the outlet of an existing sediment basin. The precipitant,
iron in this case, causes flocculation, which precipitates phosphorus
and solids to the sediments. By increasing the rate of precipitation
of soluble phosphorus, less is available for algae growth in the lake.
In summary, the request for sponsorship by the PUSLWD is a very
reasonable proposal, which allows the city and watershed district
an opportunity to work together on many issues both are committed
to. The City has already begun planning for many of the projects
included in the proposed implementation plan. The PUSLWD has
taken a step further, however, by rating the projects, and including
them in a comprehensive study, with projected costs and benefits.
If the city commits to being a sponsor, any grants that ~ be
awarded will help the city pay for some projects originally assumed
to be paid entirely out of the city's budget. If a grant is not awarded,
a different approach would be necessary.
The City will be the lead local agency, responsible for completing a
few of the projects listed above. In those cases, if the city chose to
construct a project other than those indicated in the proposal, that
would be an option the grant would allow. However, to receive the
grant it would need to be shown that the benefits of the new project
are the same or better than the benefits from the project rejected.
The resolution included in this report will support the Watershed's
Project, and agree to identify the Executive Director of the
Watershed District as the Project representative. It commits
financial support, in an amount not to exceed $74,134, and staff
labor, not to exceed 82 hours. These dollars would come from the
storm water utility fee, spread out over the next 6 years. Again,
these commitments are all contingent on receiving grant funds.
The Lake Advisory Committee was given a presentation by Paul
Nelson of Montgomery Watson at their meeting on September 15,
1993. They unanimously support the proposed sponsorship, and
staff labor as outlined in the Watershed District's proposal.
-4-
BUDGET IMPACT:
Over the six year duration of the project, funds from the Storm
Water utility fee, which in 1993 will generate approximately
$103,000, would be used for this project. If fully implemented the
total cost to the City would be about $76,104 or $12,700 per year.
Many of these programs and projects were proposed to be
implemented and paid for through the funds generated by the storm
water utility fee. Upon completion of the City's local comprehensive
Storm Water Management Plan, a thorough study on the programs
and funding alternatives will be presented to the Council.
ALTERNATIVES:
The alternatives are as follows:
1. Adopt Resolution 93-87
2. Do not adopt Resolution 93-87
RECOMMENDATION: Adopt Resolution 93-87
ACTION REQUIRED: The action required is for the City Council to adopt Resolution
93-87.
LACAG1.WRT
-5-
Exhibit 1 . Summ~ of Costs
PROJECT CITY'S TOTAL PROJECT OTHER AGENCIES
DESCRIPTION COST COST PARTICIPATING
SignagelStreet $1,970.00 $1,970.00
Sweeping Coordination
Other Public 0.00 $64,200.00 Scott County En.
InformationlEducation PUSLWD
Water Quality Basin $30,000.00 $60,000.00 Grant
1 Improvement
Water Quality Basin $3,885.00 $7,770.00 Grant
4 Improvement
Water Quality Basin $4,475.00 $17,900.00 PUSLWD
Inventory Grant
Aquatic Macrophyte $3,804.00 $25,220.00 PUSLWD
Management Plan MnDNR
Grant
Aquascaping $1,250.00 $5,000.00 PUSLWD
Grant
Monitoring $8,520.00 $68,170.00 PUSLWD
Grant
Ferric Chloride $0.00 $38,200.00 PUSLWD
System (installation) Grant
Ferric Chloride $22,200.00 $44,400.00 PUSLWD
System (0 & M for 6 years)
Fertilizer $0.00 $28,000.00 Scott County Ext.
Management Incentives Grant
Conservation Tillage $0.00 $28,000.00 Scott County Ext.
Equipment Grant
Aeration System $0.00 $212,190.00 PUSLWD
Grant
Wetland Restorations $0.00 $117,690.00 PUSLWD
Grant
Other Projects $0.00 $55,360.00 PUSLWD
Scott County En.
Scott County SWCD
Grant
TOTAL $76,104.00 $774,070.00
-6-
RESOLUTION 93-87
RESOLUTION IDENTIFYING PROJECf REPRESENTATIVE
AND AUTHORIZING A PHASE II APPUCATION
BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA, that the Oty of
Prior Lake hereby designates William Dilks, Executive Director, Prior Lake-Spring Lake
Watershed District as the Project Representative for the Prior-Sprin, Lakes Improvement Project
and proposed Clean Water Partnership Phase II - Project Implementation Grant
The Project Representative shall have the authority to represent the City of Prior Lake in all matters
that do not specifically require action by the Prior-Spring Lakes Improvement Project sponsors.
The Minnesota Pollution Control Agency (MPCA) shall direct Clean Water Parttlership
Application correspondence to the Project Representative and shall consider correspondence from
and actions taken by the Project Representative to be that of the Prior-Spring Lakes Improvement
Project sponsors, including the City of Prior Lake.
BE IT FURTHER RESOLVED by the City of Prior Lake that the Project Representative designated
above is hereby authorized to submit to the MPCA a Clean Water Partnership Phase II - Project
Implementation Grant Application for the Prior-Spring Lakes Improvement Project.
BE IT FURTHER RESOLVED by the City of Prior Lake that the total project cost of the Prior-Spring
Lakes Improvement Project is expected to be $774,070. In addition, the City of Prior Lake shall
provide up to $51,934 in grant matching funds, and other costs. for the six year duration of the
project The City of Prior Lake also agrees to provide up to 82 hours of staff labor valued at
$1,970, and 50%. up to $3,700 per year, of the annual operations and maintenance cost of the ferric
chloride addition system for the six year project duration. The total cost to the City for the six year
project would be a maximum of $76,104.
BE IT FURTHER RESOLVED by the City of Prior Lake that on a yearly basis, the projects included in
the proposed plan for which the City is the "Lead Local agency", will be evaluated to determine if
the project will be delayed or if alternative projects should be implemented. Any alternative
projects would be required to meet or exceed the benefits obtained from the projects included in the
original plan.
Passed and adopted this 18.th day or October, 1993.
YES
NO
Andren
Fitzgerald
Kedrowski
Scott
White
Andren
Fitzgerald
Kedrowski
Scott
White
Frank Boyles
City Manager
{ Seal }
-7-
4629 Dakota St. S.E., Prior Lake, Minnesota 55372 / Ph. (612) 4474230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLDYER
(
. .
EXECUTIVE SUMMARY
This report presents the results and recommended Implementation Plan (or the
DiaenosticIFeasibility Study on Prior and Sprinl Lakes. The project was a joint effort and
was funded by the Prior LakelSprinl Lake Watershed District CPSlSLWD) and EPA throuch
a 5&J, cost share in the Clean Lakes PrOI1'am. The State o( Minnesota's Pollution Control
~eney (PCA) provided technical review and project man8iement.
DIAGNOSTIC STUDY
The DialDostic Study included a 12-month water quality monitorinl prOl1'am and
subsequent data and land use assessments which characterized the sources o( water quality
problems on the lakes. The Feasibility Study evaluates the various alternatives (or water
quality improvement and develops the Implementation Plan (or the project.
Spring, Upper Prior, and Lower Prior Lakes are important recreational resources. Sprinl
Lake is a (ocal point for the planned Regional Park which will include a swimminl beach.
Upper and Lower Prior Lakes are connected, have public access and swimming beaches.
Algal blooms are the primary problems restricting desired uses of Spring and Upper Prior
Lakes. These blooms are excessive during the growing season with chlorophyll-A
concentrations averaging 45 ~ and 35 J1g/l for Spring and Upper Prior Lakes, respectively.
Blooms of this magnitude place both lakes in the worst 33% of lakes in the Central
Hardwoods Region. Lower Prior Lake has much better water quality and is in the best 33%
of lakes in the Central Hardwoods Region.
Primary productivity (algal growth) in Upper Prior and Lower Prior Lakes is clearly limited
by the availability of phosphorus. Primary productivity in Spring Lake is not always
phosphorus-limited. This is due to extremely high phosphorus concentrations in Spring
Lake, makinl it overly abundant. Even thouch Sprinl Lake is not always phosphorus-
limited, phosphorus is still the primary pollutant targeted for reductions (or several reasons:
. Phosphorus levels can be reduced to the point where it again'becomes limiting.
. It is generally easier to reduce phosphorus than other nutrients.
ES-l
(
· The aleal apedes dominatinr SPrinl Lake are blue-rreens which caD fix their
own nitroeen.
. Reducin&, nitro&,en without equal or creater reduction. of phosphorus could live a
rreater competitive advantare to blue-rreen alese.
. Primary produc:tivity in Upper Prior Lake, which receives 55% of ita phosphorus
budget from Sp~ Lake, is clearly phosphorus-limited.
The direct watershed area to Spring Lake encompass88 13,250 acres. This lar&,e watershed
lives Sprin&, Lake a relatively short hydraulic residence time of 1.3 years. The western
portion of the direct watershed to Spring Lake is dominated by 8.&'riculturalland uses. These
uses consist primarily of row crops. Approximately 23% of the direct watershed to Sprini
Lake is hiihly erodible soils. Streams from these watersheds contribute 41% of the total
phosphorus load to Spring Lake. Because of the large amount of highly erodible land and the
hieh phosphorus loading to Spring Lake, these subwatersheds were classified as hiih priority
for implementation of qricultural Best MaDaiement Practices (BMPs).
Internal phosphorus loading is sienificant in Spring Lake. Internal loading is estimated to
contnbute 33% of the total phosphorus load in Spring Lake. Internal loadin&, causes the
buildup of soluble reactive phosphorus within Spring Lake. This form of phosphorus is the
most readily available form for algal uptake. Approximately 60% of the phosphorus in
Sprini Lake is soluble. Manqement of soluble phosphorus and internal loading in Spring
Lake will be important for improving Upper Prior Lake as well as Spring Lake.
Upper Prior Lake has a relatively small lake volume. This lives the lake a short hydraulic
residence time of 0.2 years and means that controlling external phosphorus sources are
particularly important for improving the lake. Prior Lake receives 55% of its phosphorus
from Spring Lake. Thirty-five percent of the remaining phosphorus load comes from the
direct drainage area to Upper Prior Lake. Much of the shoreline is hiehly developed. Lawn
maintenance to the water's edge is a common practice. In addition, city areas south of the
.lake are heavily developed. Few opportunities exist for stormwater system retrofits or for
new stormwater .quality basins. Public education will be important for urban areas
surrounding Upper Prior Lake.
ES-2
\
The water quality of Lower Prior Lake i. fairly cood. However, there are .icniticant
development pt'e8sures, particularly alone the north shore of the lake. Wise development
will be important in maint.Ainine the quality of Lower Prior Lake.
FEASmILITY STUDY
In the Feasibility Study, a number of alternatives were evaluated to reach phosphorus
concentration eoals. These alternatives ranee trom administrative alternatives such as
fertilizer management education programs to structural alternatives such as wetland
restoration. Each option was evaluated for potential water quality benefits, estimated initial
and long-term (operation and maintenance) costs, and technical feasibility. The most
technically sound and cost-eft"ective options were incorporated into the Implementation Plan
for improving the lakes.
Special consideration was given to alternatives that address problems and reduce pollutant
loadings at their source, and to alternatives that have the potential to reduce runoff as well
as phosphorus. The Feasibility Study also identifies numerous existing water qualit1
initiatives by the PUSL WD and other local agencies. The Implementation Plan was
designed to complement these exis~ initiatives, particularly land development regulations.
Parts of the PUSL WD are currently experiencing rapid urban development. Areas without
sewer are being developed as single family lO-acre lots. The Implementation Plan improves
regulation of this transition through revised wet pond design criteria, by developing methods
for ensuring maintenance of water quality facilities, and by public education efforts. The
final plan includes the following elements:
. A public information/education program which will focus on fertilizer
management, yard waste management, septic system maintenance, enlisting
public support, and improving non-point source pollution prevention practices by
local landowners.
. Amendments to the District's 509 Plan including revisions to water quality pond
design criteria, clarificiltion of responsibilities for m~taining storm water
facilities, and amendments to protect landlocked basins.
ES-3
t
. A fertilizer wnAnAlement incentive proeram to encoUl8le .,ncultural operaton
in the priority watersheds to utilize soil tests and manare aericultural nutrients
that will achieve profitable crop production and reduce nutrient runoff.
. Promotion of no-till farminc throu.ch the purchase of a no-till drill for use by
farmers in the priority watershed.
. Promotion of aquascapinr as a means of establishing residential shoreline
buffers.
. Modifications to existing storm water basins to improve phosphorus
sedimentation and reduce phosphorus loadinr to the lakes.
. The restoration of four priority wetland areas to reduce the phosphorus load to
Spring Lake, provide flood storage, and wildlife habitat.
. A feme chloride chemical feed system to reduce the inflow of dissolved
phosphorus from County Ditch 13 to Sp~ Lake.
. Aeration of Sp~ Lake to reduce internal cyclinC of phosphorus.
. Development of lake-wide aquatic macrophyte management plans to facilitate
long-term comprehensive aquatic macrophyte management following treatment
of Eurasian water milfoil.
. Improvements to a northern pike spawning area on Lower Prior Lake.
The estimated cost of implementing the plan over the six-year project duration is $774,070.
Implementation of the plan will reduce phosphorus loading to Spring Lake, Upper Prior
Lake, and Lower Prior Lake by 40%, 30%. and 20%, respectively. These reductions will
significantly reduce the frequency and severity of aleal blooms. A reduction in algal blooms
. will also decrease the volume of OTganiC matter which contributes to sediment oxygen
demand. Reducing algal blooms will also increase water clarity. The improved conditions
will be sufficient to change Sprin, Lake from non-supportinr to partially supporting
swimming. Water clarity in Upper Prior Lake will increase by an estimated 0.8 feet.
ES-4
\
One consequence or improvm, water clarity may be an increase in the lI'owth or aquatic
macrophytes (weeds). lnC1'8ased li~ht penetration may allow weed Jrowth into deeper
waters. This should be viewed as improvin~ the biolo,ical health and diversity of the lakes.
This chan~e will also be addressed as part of the aquatic macrophyte ftlAn411lement plans.
ES-5