HomeMy WebLinkAbout5K - Hawk Ridge Rd Sidewalk Construction
MEETING DATE:
AGENDA #:
PREPARED BY:
AGENDA ITEM:
DISCUSSION:
June 18, 2007
5K
LARRY POPPLER, ASSISTANT CITY ENGINEER
CONSIDER APPROVAL OF A RESOLUTION ACCEPTING QUOTES AND
AWARDING THE CITY'S STANDARDIZED CONTRACT TO S.M. HENTGES FOR
SIDEWALK CONSTRUCTION ON HAWK RIDGE ROAD (CITY PROJECT #06-15)
Introduction
The purpose of this agenda item is to accept quotes and award the City's
Standardized Construction Contract for the sidewalk construction on Hawk Ridge
Road.
Historv
On March 20, 2006 the City Council adopted Resolution 06-039 approving the
preliminary plat of "NORTHWOOD MEADOWS" subject to added conditions. One
of the conditions was that staff and developer review the feasibility of extending
sidewalk along Hawk Ridge Road to Northwood Road with the developer paying the
costs. Based on that condition, an Engineer's Estimate of $21,120.00 was
established on July 19, 2006 and included in the Development Contract.
On August 7, 2006 the City Council approved the Development Contract for the
development of land known as "NORTHWOOD MEADOWS". The Development
Contract required the developer to furnish the City with a sidewalk escrow of
$26,400.00 for the future construction of a sidewalk on Hawk Ridge Road. This
escrow was based on 125% of the estimated cost.
A neighborhood informational meeting was held on January 17, 2007 to provide
affected property owners an opportunity to view the plans and discuss the project
with City Staff. Contrary to the original determination, Staff informed the property
owners that they recommended constructing the sidewalk on the north side of Hawk
Ridge Road due to steep driveway grades on the south side and the inability to
meet design standards. Three of four property owners on the north side of the road
were present to comment on this recommendation. Staff proceeded with plans and
specifications for the project based on their recommendation and the property
owner's comments.
Current Circumstances
The plans and specifications were distributed to contractors and Staff has received
quotes in accordance with the City's Purchasing Policy from three companies for
the Hawk Ridge sidewalk project in the Northwood Meadows development ("Hawk
Ridge Sidewalk Project".) The quotes received are shown below:
Bid Price
$38,980.07
$43.473.95
$46,945.00
www.cityofpriorlake.com
Phone 952.447.9800 / Fax 952.447.4245
The quotes received were each analyzed and tabulated. City Staff is
recommending that S.M. Hentges perform the construction for the Hawk Ridge
Sidewalk Project. S.M. Hentges has performed work for the City of Prior Lake in
the past. Most recently they have constructed the streets and utilities for the Prior
Lake Downtown Project and the Ring Road Project. S.M, Hentges is currently
constructing the County Road 82 project. With crews in the area, they were able to
provide a favorable quote. The Engineers Estimate for this project is $45,698,00,
ISSUES:
The majority of the issues raised at the informational meeting were incorporated
into the design of the project or otherwise answered. Not all those present
supported the project regardless of location.
CONCLUSION
The staff recommends the City Council award the contract to S.M. Hentges and
Sons Inc. When the City solicits for quotes, there is always a provision in the
solicitation documents specifying the City Council reserves the right to reject all
quotes. The City Council has in the past, rejected quotes on projects where the
quotes exceeded the estimate or were otherwise unfavorable for the City.
FINANCIAL
IMPACT:
As stated above, as part of the Development Contract the City required the
Developer to escrowed $26,400.00 for this sidewalk project. These funds will be
utilized to construct the sidewalk. This figure was calculated as 125% of the
original estimate.
The original estimate included basic sidewalk construction assuming general
sidewalk placement. Due to changes in the design, additional driveway repair,
hydrant relocation, catch basin relocation, mailbox relocation, sprinkler system
repair and additional concrete work, the bids have exceeded the escrowed amount
by $12,580.07. Since this is a sidewalk project that promotes pedestrian travel to
the park system, It is recommended that the additional funding come from the
Capital Park Fund.
I Total Project Cost I Developer Escrow Capital Park Fund
$38,980.07 $26,400.00 $12,580.07
ALTERNATIVES: The alternatives are as follows:
1. Approve a resolution accepting quotes and authorizing the Mayor and City
Manager to execute the City's Standardized Construction Contract with S.M.
Hentges for construction of the Hawk Ridge Sidewalk.
2. Table the Resolution for a specific reason.
3. Deny the Resolution.
RECOMMENDED Alternative # 1
MOTION:
A RESOLUTION ACCEPTING QUOTES AND AUTHORIZING THE MAYOR AND CITY MANAGER
TO EXECUTE THE CITY'S STANDARDIZED CONSTRUCTION CONTRACT FOR THE HAWK
RIDGE ROAD SIDEWALK PROJECT (CITY PROJECT #06-15) AS PART OF THE "NORTHWOOD
MEADOWS" FINAL PLAT APPROVAL
Motion By:
Second By:
WHEREAS, Council adopted Resolution 06-039 approving the preliminary plat of "NORTHWOOD
MEADOWS" subject to added conditions. One of the conditions was that the staff and
the Developer review the feasibility of extending a sidewalk along Hawk Ridge Road,
and;
WHEREAS, This sidewalk connection will link Northwood Road sidewalk to the community park
dedicated with the "NORTHWOOD MEADOWS" final plat, and;
WHEREAS, A total of (3) three quotes (provided in the chart below) were received for the identified
improvements, with the low bid from S.M. Hentges and Sons Inc. at a cost of
$38,980.07, and;
Bid Price
$38,980.07
$43.473.95
$46,945.00
WHEREAS, S.M. Hentges has satisfactorily completed work for the City of Prior Lake, and
WHEREAS, The Developer has escrowed $26,400.00 for the sidewalk improvements on Hawk
Ridge Road with the August 7,2006 approval of the Development Contract and final
plat for "NORTHWOOD MEADOWS".
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and City Manager are hereby authorized to execute the City's Standardized
Construction Contract for the identified Hawk Ridge Road Sidewalk Project with S.M. Hentges and
Sons Inc. for a cost not to exceed $38,980.07.
3. Funding for this project shall be drawn from the escrow provided by the developer for
"NORTHWOOD MEADOWS" in the amount of $26,400.00 and the Capital Park Fund. Account
#225-45201-501 in the amount of $12,580.07.
PASSED AND ADOPTED THIS 18TH DAY OF JUNE 2007.