HomeMy WebLinkAbout9A - 2000 Improvement Projects T T .. DATE: AGENDA #: PREPARED BY: REVIEWED BY: SUBJECT: AUGUST 16, 1999 9A SUE MCDERMOTT, ASSISTANT CITY ENGINEER GREG ILKKA, PUBLIC WORKS DIRECTOR/CITY ENGINEER CONSIDER APPROVAL OF RESOLUTION 99-XX, ACCEPTING FEASffiILITY REPORT AND SCHEDULING A PUBLIC HEARING TO CONSIDER 2000 IMPROVEMENT PROJECTS DISCUSSION: HISTORY At the May 17, 1999, City Council meeting, Council adopted Resolution No. 99-50 authorizing staff to prepare a Feasibility Report for the 2000 Improvement projects as approved by the Council in the 2000-2004 Capital Improvement Program. The following five project areas were considered for the report: 1. Reconstruction of Oak Ridge Circle, Flandreau Circle, Indian Ridge Circle, Fulbright Circle, Euclid Avenue, Maves Trail, and Forsythe Road including storm sewer, retaining walls, aggregate base, concrete curb and gutter, bituminous surfacing, and appurtenant work. 2. Reconstruction of Shannon Trail, Shannon Circle, and Prior Circle including storm sewer, aggregate base, concrete curb and gutter, bituminous surfacing, and appurtenant work. 3. Mill and overlay of Fairlawn shores Trail from 150th Street to Trunk Highway 13. 4. Mill and overlay of Fish Point Road from Trunk Highway 13 to County Road 44. 5. Construction of Linden Circle including storm sewer, aggregate base, concrete curb and gutter, bituminous surfacing, and appurtenant work. Lift station renovations are also scheduled for 2000 in the 2000 - 2004 Capital Improvement Program. Due to the funding source (Trunk Reserve), the improvements are not required to go through the M.S. 429 process and are not included in the feasibility report. 1620~Qi:ligM9(i9~9\ve. S.E., Prior Lake, Minnesota 553y2-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER CURRENT CIRCUMSTANCES The attached report indicates the estimated City costs for each project, along with preliminary assessment estimates. At the end of the Feasibility Report, a project financing summary is included to show project cost splits. The total estimated cost of the five projects is $1,131,000. The following is a commentary on each project with regard to project need: Area 1 -Oak Rid!!e Court and Shan!!ri-La Additions Oak Ridge Circle, Flandreau Circle, Fulbright Circle, Indian Ridge Circle, Euclid Avenue, Maves Trail and Forsythe Road have bituminous curb and surfaces with widths varying from 16.5 feet to 30 feet. These roads were first paved in 1975. Area 2 - Prior Hill Shannon Trail, Shannon Circle, and Prior Circle have bituminous curb and surfaces with 30 foot widths. These roads were paved in 1982. Area 3 - Fairlawn Shores Trail Mill and Overlav Fairlawn Shores Trail has a 36 foot wide bituminous surface with concrete curb and gutter which and was constructed in 1979. Milling and a 2" bituminous overlay is proposed for this street between TH 13 and 150th Street. Area 4 - Fish Point Road Mill and Overlav Fish Point Road from Trunk Highway 13 to County Road 44 has a bituminous surface and concrete curb and gutter with widths varying from 28 feet to 44 feet. This roadway was constructed in 1979. Milling and a 2" bituminous overlay is proposed for this street. Area 5 - Linden Circle Linden Circle has a gravel surface and is rural in nature with no curb and gutter. Residents of this area have requested that the City improve the road. The area was originally platted in the 1930's. A 22-foot wide bituminous roadway, concrete curb and gutter, and storm sewer improvements are proposed for Linden Circle. The attached Feasibility Report outlines which portions of the cost for the above projects will be assessed to the benefiting properties. If the Council approves the Feasibility Report, the Chapter 429 special assessment projects require public hearings to be conducted prior to implementing the project. Staff proposes to conduct Informational G:\AGENDA99\OOFEAS.DOC 2 ISSUES: FINANCIAL IMPACT: G:\AGENDA99\OOFEAS.DOC Meetings prior to the Public Hearings to help the residents understand the proposed projects and to answer questions. ASSESSMENT METHOD The feasibility report outlines two assessment methods, front footage and unit, for Areas 1 through 4. In accordance with the City's assessment policy, the benefiting properties would be assessed for 40% of the cost of the improvements with the remaining 60% paid by ad valorem tax levy. The estimated assessment rates using the front footage method for Areas 1 through 4 are summarized as follows: PROJECT AREA 1 (reconstruction) AREA 2 (reconstruction) AREA 3 (mill & overlay) AREA 4 (mill & overlay) RATE $36.25 $35.95 $12.16 $6.62 Area 5, Linden Circle, consists of twelve (12) benefiting properties with varying frontages which have access on Linden Circle. In accordance with the assessment policy, it is proposed to assess the properties 100% of the project cost as a first time improvement. It is proposed to assess these properties using the unit method as the lots are similar in size. In addition, since this is not a through street only twelve properties benefit, making the unit rate a straightforward method. The unit rate for street and storm sewer is $6,727.50/10t. The front footage rate shown in the feasibility report is $46.80/FF. CONCLUSION In summary, Areas 1 through 5 are feasible from an engineering and economic standpoint and in the staff s opinion will specially benefit the properties proposed to be assessed in the amount equal to or in excess of the assessment amount. Approval of the Feasibility Report does not grant final approval of any project. The 2000 improvement projects are proposed to be financed by special assessments, tax levy, and trunk reserve. Funding sources and amounts are as shown below: 1.) Assessments 2.) Tax Levy 3.) Trunk Reserve PROJECT COST TOTAL $474,890.00 $591,240.00 $64,870.00 $1,131,000.00 3 ALTERNATIVES: The alternatives are as follows: 1. Approve Resolution 99-XX accepting the Feasibility Report and establish a Public Hearing date as per Resolution 99-XX. 2. Table this item for a specific reason. 3. Deny Resolution 99-XX. RECOMMENDED MOTION: A motion and second to adopt Resolution 99-XX accepting the Feasibility Report and calling for a Public Hearing for the 2000 Improvement projects. G, 111 ' G:\AGENDA99\OOFEAS.DOC 4 RESOLUTION 99-XX RESOLUTION ACCEPTING FEASffiILITY REPORT AND CALLING FOR A PUBLIC HEARING ON 2000 IMPROVEMENT PROJECTS MOTION BY: SECONDED BY: WHEREAS, pursuant to Resolution 99-50 of the City Council, adopted on May 17, 1999, a report prepared by the City's Engineering Department with reference to the following improvements and the generally described project areas: 1. Reconstruction of Oak Ridge Circle, Flandreau Circle, Indian Ridge Circle, Fulbright Circle, Euclid Avenue, Maves Trail, and Forsythe Road including storm sewer, retaining walls, aggregate base, concrete curb and gutter, bituminous surfacing, and appurtenant work. 2. Reconstruction of Shannon Trail, Shannon Circle, and Prior Circle including storm sewer, aggregate base, concrete curb and gutter, bituminous surfacing, and appurtenant work. 3. Mill and overlay of Fairlawn shores Trail from I 50th Street to Trunk Highway 13. 4. Mill and overlay of Fish Point Road from Trunk Highway 13 to County Road 44. 5. Construction of Linden Circle including storm sewer, aggregate base, concrete curb and gutter, bituminous surfacing, and appurtenant work. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA, that 1. The Council will consider the improvement of such streets and areas in accordance with the report and the assessment of property as described in the report for all or a portion of the cost ofthe improvements pursuant to Minnesota Statutes Chapter 429 at an estimated total cost of the improvements of$I,131,000.00. 2. A Public Hearing shall be held on the following such proposed improvements on the following date at the Fire Station No.1, with the address of 16776 Fish Point Road, City of Prior Lake, Minnesota at the following time: A. AREA 1,2,3,4 and 5 @ 7:45 P.M., September 20, 1999. 1626~~~4}RcAve. S.E., Prior Lake, Minnesota 553y2-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER Passed and adopted this 16th day of August, 1999. Seal} G:\RESOL99\OOFEAS,DOC ,. -- YES Mader Kedrowski Petersen Schenck Wuellner NO Mader Kedrowski Petersen Schenck Wuellner Frank Boyles City Manager City of Prior Lake 2 ~IJ'~',' " a .. '.I.:.,".~j; .,..,J ..\;:.t,I'~~~' '~i. ,,'__""11'" NOTICE OF PUBLIC HEARING ON 2000 IMPROVEMENT PROJECTS INCLUDING GRADING, STORM SEWER, AGGREGATE BASE, CONCRETE CURB AND GUTTER, BITUMINOUS SURFACING, RETAINING WALLS, AND APPURTENANT WORK IN THE CITY OF PRIOR LAKE, SCOTT COUNTY, MINNESOTA Notice is hereby given that the City Council of the City of Prior Lake, Minnesota will meet in the Council Chambers in Fire Station No.1, 16776 Fish Point Road, on Monday, the 20th day of September, 1999 at 7:45 P.M. to consider the improvements for the following streets: PROJECT DESCRIPTION AREA 1 - Oak Rid~e Circle. Flandreau Circle. Fulbright Circle. Indian Ridge Circle. Euclid Avenue. Maves Trail. and Forsvthe Road Reconstruction of Oak Ridge Circle, Flandreau Circle, Fullbright Circle, Indian Ridge Circle, Euclid Avenue, Maves Trail from Fairlawn Shores Trail to Kortsch Trail, and Forsythe Road, including grading, storm sewer, aggregate base, concrete curb and gutter, bituminous surfacing, retaining walls and appurtenant work. The area proposed to be assessed is every lot, piece, and parcel benefiting from said improvement, whether abutting or not, within the following described areas: The northwest quarter Section 36, Township 115 north, Range 22 west, Scott County, Minnesota. Specific property descriptions are included in the above described area, but not inclusive, are as follows: Property abutting Area.l including: Oak Ridge Court Addition Oak Ridge Court First Addition Shangri-La Addition Maves Second Lake Addition 16200~~.o~rior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER AREA 2 - Shannon Trail. Prior Circle and Shannon Circle Reconstruction of Shannon Trail, Prior Circle, Shannon Circle including grading, storm sewer, aggregate base, concrete curb and gutter, bituminous surfacing and appurtenant work. The area proposed to be assessed is every lot, piece, and parcel benefiting from said improvement, whether abutting or not, within the following described areas: Part of the northeast quarter of Section 36, Township 115 north, Range 22 west, Scott County, Minnesota. Specific property descriptions included in the above-described area, but not inclusive, are as follows: Property abutting Area 2 including: Prior Hill Addition AREA 3 - Fairlawn Shores Trail Resurfacing of Fairlawn Shores Trail from Fish Point Road to 150th Street including milling and a 2" bituminous overlayment. The area proposed to be assessed is every lot, piece, and :parcel benefiting from said improvement abutting within the following described areas: Part of the northeast quarter of Section 36, Township 115 North, Range 22 West, Scott County, Minnesota. Specific property descriptions included in the above described area, but not inclusive are as follows: Property abutting Area 3: Prior Hill Addition Clayton's First Addition Shangri- La Addition Oak Ridge Court First Addition G:\PROJECTS\I998I22FEAS\PHNOTlCE.DOC :2 JI jJl _....,~[m:',:_.,,,.oi,,L ___~_ ~..~ ~,:r':;':~~_-, '_,'~E:":"..'.~ :1{ ~ ,:;_..j._JilE;.~ _~ ::;-' 7 lJ AREA 4 - Fish Point Road Resurfacing ofFish Point Road from Glory Circle S.E. to 160th Street S.E. (CSAH 44) includes milling and a 2" bituminous removal and overlayment. The area proposed to be assessed is every lot, piece, and parcel benefiting from said improvement whether abutting or not, within the following described areas: Part of the southeast quarter of Section 36, Township 115 North, Range 22 West, Scott County, Minnesota. Specific property descriptions included in the above described area, but not inclusive are as follows: Property abutting Area 4: Millers First Addition Millers Second Addition The Trees Addition Hidden Oaks First Addition Hidden Oaks Second Addition AREA 5 - Linden Circle N.W. Reconstruction of Linden Circle including grading, storm sewer, aggregate base, concrete curb and gutter, bituminous surfacing and appurtenant work. The area proposed .. to be assessed is every lot, piece, and parcel benefiting from said improvements, whether abutting or not, within the following described areas: Part of the northwest quarter of Section 3, Township 114 North, Range 22 West, Scott County, Minnesota. Specific property descriptions included in the above described area, but not inclusive are as follows: Property abutting Area 5: Northwood Addition Har Wil Lew Addition G:IPROJECTS\I998122FEAS\PHNOTICEDOC The Council proposes to proceed under the authority granted by Minnesota State Statutes Chapter 429. The total estimated cost of improvements for Areas 1 through 5 is $1,131,000. All persons desiring to be heard with reference to the proposed improvements will be heard at this meeting. Written or oral comments will be considered. Dated: August 16, 1999 ., By Order of the City Council /s/ Frank Boyles City Manager Published in the Prior Lake American, August 28, 1999 and September 4, 1999. G:\PROJECTS\1998122FEAS\PHNOTICEDOC ""H.N '1i18.,., . ...Jl; ''''i~#I,! ,.0, '1',- "(i...."::.?~. "< ,,-..\i,"v.titf'lI..ii.; 't. .-4.,:(,...._- PRELIMINARY REPORT FOR THE CITY OF PRIOR LAKE 2000 PUBLIC IMPROVEMENT PROJECTS INCLUDING STORM SEWER, GRADING, CONCRETE CURBING, STREET PAVING, RETAINNG WALLS, SURFACE IMPROVEMENTS, AND APPURTENANT WORK August 1999 I hereby certify that this Feasibility Report was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Minnesota. "-..::1~ 1 MeP.Lvw4-tt" Susan J. McDermott, P.E. Reg. No. 21715 8/9/ Cl q I Date INTRODUCTION On May 17, 1999, the Prior Lake City Council adopted Resolution 99-50, which ordered the preparation of a feasibility report for improvements to the project areas listed below: · Area 1 - Oak Ridge Circle, Flandreau Circle, Indian Ridge Circle, Fulbright Circle, Euclid Avenue, Maves Trail, and Forsythe Road are located within Section 36, Township 115 North, Range 22 West, Scott County, Minnesota. · Area 2 - Shannon Trail, Shannon Circle, and Prior Circle are located within Section 36, Township 115 North, Range 22 West, Scott County, Minnesota. · Area 3 - Fairlawn Shores Trail from 150th Street to TH 13 is located within the northeast quarter of Section 36, Township 115 North, Range 22 West, Scott County, Minnesota. . Area 4 - Fish Point Road from TH 13 to CSAH 44 is located within the southeast quarter of Section 36, Township 115 North, Range 22 West, Scott County, Minnesota. . Area 5 - Linden Circle is located within the northwest quarter of Section 3, Township 114 North, Range 22 West, Scott County, Minnesota. SCOPE This report evaluates the feasibility of reconstructing these streets. All existing infrastructure elements (streets, utilities, etc.) were evaluated, improvements recommended, cost estimates of the proposed improvements prepared and funding strategies developed by this report. DESCRIPTION OF PROJECT AREA 1 - Oak Rid!!e Circle. Flandreau Circle. Fulbrieht Circle. Indian Rid!!e Circle. Euclid Avenue. Maves Trail. and Forsythe Road Area 1 is shown on Exhibit 1. Oak Ridge Circle, Flandreau Circle, Fulbright Circle, Indian Ridge Circle, Euclid Avenue, Maves Trail, and Forsythe Road have failing bituminous surfaces and bituminous curb. The existing widths of all of the roads with the exception of Forsythe Road are 30 feet. Forsythe Road is currently 16.5 feet wide. There are some existing reinforced concrete storm sewers and culverts that carry storm water runoff to an existing system and ultimately to Prior Lake. These failing bituminous surfaces were originally paved in 1975. The streets no longer meet minimum design standards and it is not cost effective to continue to patch the streets. Sanitary sewer and watermain were installed in 1974. The watermain consists of 6" diameter ductile iron pipe. The sanitary sewer in the project area is 8" diameter vitrified clay pipe. The sanitary sewer was televised in 1995. The televising report indicates areas of pipe that show vertical sags, cracked joints, cracked pipe and roots. s:'froj_\1999\24fcu\REPORU4.00c 2 i.... .'i~lii4ii't!lI~""'" '. III 100 'II'. ili"", ~....~I' ;~f ',:.. . T "", +"i'\i"it'"~~~ ;. i Proposed improvements include 7-ton design street reconstruction with storm sewer, retaining walls, concrete curb and gutter, driveway restoration, and bituminous surfacing. Street widths for Oak Ridge Circle, Flandreau Circle, Fulbright Circle, Indian Ridge Circle, Euclid Avenue, and Maves Trail are proposed to be 28 feet. A street width of 20 feet is proposed on Forsythe Road due to the topography of the area. The typical street section is shown on Exhibit 4. Sanitary sewer will be repaired as necessary to correct sags and cracks. Additional fire hydrants will be added to the project as the existing hydrant spacing is not in conformance with City requirements. Existing storm sewer pipe will be utilized where possible. The existing right-of-way is 50 feet wide on all of the streets in Area 1. Temporary construction easements or right-of-entry agreements will be necessary for driveway restoration due to the topography of the area. No additional right-of-way requirements are anticipated. The benefiting property owners will be assessed for street and storm sewer construction. Tax levy funds will be used to finance the city portion of the street reconstruction costs. Trunk reserve funds will be used to finance the water and sanitary sewer repairs. AREA 2- Shannon Trail. Prior Circle and Shannon Circle Area 2 is shown on Exhibit 1. Shannon Trail, Prior Circle and Shannon Circle have bituminous surfaces with bituminous curb. The existing width of all of the roadways in Area 2 is 30 feet. There are some existing reinforced concrete storm sewers and culverts that carry storm water runoff to an existing system and ultimately to Prior Lake. The streets in Area 2 were originally paved in 1982. The streets in the Prior Hill Addition were constructed seven years after the streets in Area 1 and do not show as many sigIis of deterioration. Sanitary sewer and watermain were installed in 1982. The watermain consists of 6" diameter ductile iron pipe. The sanitary sewer in the project area is 8" diameter vitrified clay pipe. Sanitary sewer will be televised to determine if any repairs are necessary. The existing right-of-way is 50 feet wide on all of the streets in Area 2. Temporary construction easements or right-of-entry agreements will be necessary for. driveway restoration due to the topography of the area. No additional right-of-way requirements are anticipated. The benefiting property owners will be assessed for street and storm sewer construction. Tax levy funds will be used to finance the city portion of the street reconstruction costs. Trunk reserve funds will be used to finance any water and sanitary sewer repairs that may be necessary. AREA 3- Fairlawn Shores Trail Mill and Overlay Area 3 is shown on Exhibit 2. Fairlawn Shores Trail from Fish Point Road to 150th Street was constructed in 1979 to a Municipal State Aid standard with concrete curb and gutter at a width of 36 feet. The bituminous portion of the street is failing and no longer meets design standards. . Proposed improvements includes milling of bituminous edges with a 2" bituminous overlayment. g:lprojec1S\I999124fcas\REPORT24.DOC 3 The Fairlawn Shores Trail overlay project is proposed to be funded through special assessments to the benefiting property owners and tax levy funds. AREA 4 - Fish Point Road Mill and Overlav Area 4 is shown on Exhibit 2. Fish Point Road between Glory Circle and 160th Street (CSAH 44) is a Municipal State Aid roadway and was constructed with concrete curb and gutter in 1979. The existing street width is 28 feet from Glory Circle to Huron Street and 44 feet wide from Huron Street to 160th Street. A 5-foot wide concrete sidewalk was constructed along Fish Point Road in 1993. The bituminous portion of the street is failing. Proposed improvements includes milling of the bituminous edges and a 2" bituminous overlayment. The Fairlawn Shores Trail overlay project is proposed to be funded through special assessments to the benefiting property owners and tax levy funds. AREA 5 - Linden Circle Area 5 is shown on Exhibit 3. Linden Circle is located east of Northwood Road, north of Butternut Circle. Linden Circle has a gravel surface and I rural in nature with no curb and gutter. This area was originally platted in the 1930's. Storm water runoff currently flows overland to Prior Lake. Residents of Linden Circle submitted a petition for local improvement in March of 1999. Proposed improvements include 7-ton design street construction with storm sewer, concrete curb and gutter, and bituminous surfacing. A street width of 22 feet is proposed due to the topography of the area and existing right-of-way. The typical street section is shown on Exhibit 5. The existing right-of-way is 20 feet wide. Additional right-of-way and easements will be required to construct the roadway as proposed. In accordance with the assessment policy if street construction is done over a non-bituminous surface, benefiting properties are proposed to be assessed for 100% of the street and storm sewer costs. FEASmILITY From an engineering standpoint, the projects in Areas 1 through 5 are feasible, independent of each other, and can be accomplished as proposed, and not in conjunction with each other or any other project. ESTIMATED COST The following costs were prepared based upon an Engineer's Estimate and are subject to change, depending on the final design of the project, required easements and/or right of way, g:\proj_\\999I24feas\REPORT24.DOC 4 1i It 1111 ' .':!Ill'..f. . ,I I , ,j,",'iI!!" N1' t,."~ ~~ '. , o,>'l.~~I;tl~~. 'i I~ ;jl The estimated project cost for each project is for the installation of assocIated improvements and includes indirect project costs. Project costs in Areas 1 through 5 include special assessments. AREA 1 - Oak Rid!!e Circle. Flandreau Circle. Fulbright Circle. Indian Ridge Circle. Euclid Avenue. Maves Trail. and Forsvthe Road To rehabilitate or restore streets to a 7-ton design standard. Includes reconstruction of Oak Ridge Circle north of Trunk Highway 13, Shannon Trail, Flandreau Circle, Fulbright Circle, Indian Ridge Circle and Euclid Avenue, Forsythe Road, and Maves Trail. ITEM Street Storm Sewer Watermain Sanitary Sewer SUBTOTAL *Indirect Costs (30%) COST $425,350.00 $74,800.00 $10,000.00 $9,000.00 $519,150.00 $155.745.00 TOTAL PROJECT COST $674,895.00 AREA 2 - Shannon Trail. Prior Circle and Shannon Circle To rehabilitate or restore streets to a 7-ton design standard. Includes reconstruction of Shannon Trail, Shannon Circle and Prior Circle. ITEM Street Storm Sewer Watermain Sanitary Sewer SUBTOTAL *Indirect Costs (30%) COST $148,200.00 $5,500.00 $6,200.00 $2.400.00 $162,300.00 $48.690.00 TOTAL PROJECT COST $210,990.00 AREA 3 - Fairlawn Shores Trail Mill and Overlav Restore Fairlawn Shores Trail to a 9-ton design standard. ITEM Street SUBTOTAL *Indirect Costs (30%) COST $47.000.00 $47,000.00 $14.100.00 TOTAL PROJECT COST $61,100.00 g:\projedS\I999\24feas\REPORT24,DOC 5 AREA 4 - Fish Point Road Mill and Overlay Restore Fish Point Road to a 9-ton design standard. ITEM Street SUBTOTAL *Indirect Costs (30%) TOTAL PROJECT COST COST $57.150.00 $57,150.00 $17.145.00 $74,295.00 AREA 5 - Linden Circle Construction To construct Linden Circle to a 7-ton design standard. ITEM Street Sanitary Sewer Watermain SUBTOTAL *Indirect Costs (30%) TOTAL PROJECT COST COST $62,100.00 $3,700.00 $18.600.00 $84,400.00 $25.320.00 $109,720.00 *Indirect costs include: Engineering (17 %) Administration (5 %) Financing (8 %) The following is a summary of the projects: Project Area Project Total Area 1 Oak Ridge Circle, Flandreau Circle, $674,895.00 Fulbright Circle, Indian Ridge Circle, Euclid Avenue, Maves Trail, and Forsythe Road 2 Shannon Trail, Prior Circle and $210,990.00 Shannon Circle 3 Fairlawn Shores Trail $61,100.00 4 Fish Point Road $74,295.00 5 Linden Circle $109,720.00 TOTAL $1,131,000.00 a:\projeclS\1999\24feu\REPORn4.DOC 6 ~""'",""""""~,,~,,,",,",'1,!11 ~ \11I .,,~.~~~;fl,,-'JIl\I";'1 ,~' .,t'! ,;:",,"'\l1~_~~~" ,Ii " ~ If PROPERTY PROPOSED TO BE ASSESSED The area proposed to be assessed is every lot, piece, and parcel within the City limits benefiting from said improvement, whether abutting or not, within the following described areas: AREA 1 - Oak Ridge Circle. Flandreau Circle. Fulbright Circle. Indian Ridee Circle. Euclid Avenue. Maves Trail. and Forsythe Road Specific property descriptions included in the above-described area, but not inclusive, are as follows: Oak Ridge Court Addition Oak Ridge Court First Addition Shangri-La Addition Maves Second Lake Addition AREA 2 - Shannon Trail. Prior Circle and Shannon Circle Specific property descriptions included in the above-described area, but not inclusive, are as follows: Prior Hill Addition AREA 3 - Fairlawn Shores Trail Specific property desc~iptions included in the above-described area, but not inclusive, are as follows: Prior Hill Addition Clayton's First Addition Shangri- La Addition Oak Ridge Court First Addition AREA 4 - Fish Point Road Specific property descriptions included in the above-described area, but not inclusive, are as follows: Millers First Addition Millers Second Addition The Trees Addition Hidden Oaks First Addition Hidden Oaks Second Addition g:lprojects\1999l24feas\REPORT24.DOC 7 AREA 5 - Linden Circle Specific property descriptions included in the above - described area, but not inclusive, are as follows: Northwood Addition Har Wil Lew Addition ESTIMATED ASSESSMENTS The improvement cost can be assessed on a unit basis or an adjusted front footage basis to the benefiting properties as per the Assessment Policy adopted by the City Council on February 21, 1989, and as amended. Both methods are shown for Areas 1 and 2. For Areas I, 2, 3, and 4 the following breaks out estimates at 60% City cost and 40% assessment for streets and stonn sewer. Area 5 is 100% assessable as first time improvements. AREA 1 - Oak Rid!!e Circle. Flandreau Circle. Fulbrie:ht Circle. Indian Rid!!e Circle. Euclid Avenue. Maves Trail. and Forsythe Road Total Project Cost $674,895.00 Project Levy (60%) Trunk Reserve $390,117.00 $24,700.00 Project Assessment (40%) StreetlStonn Sewer Assessment Front Footage Method Estimated Assessable Front Footage Estimated Assessment Rate Unit Method Assessable Units Estirnated Unit Assessment $260,078.00 $260,078.00 7,175 FF $36.25/FF 59 Units $4,408. 1 O/Unit AREA 2 - Shannon Trail. Prior Circle and Shannon Circle Total Project Cost $210,990.00 Project Levy (60%) Trunk Reserve $119,886.00 $11,180.00 Project Assessment (40%) StreetlStonn Sewer Assessment Front Footage Method Estimated Assessable Front Footage Estimated Assessment Rate Unit Method Assessable Units Estimated Unit Assessment $79,924.00 $79,924.00 2,223 FF $35.95/FF 22 Units $3,632.91/Unit .:\projectl\1999\24feu\REPORT24.DOC 8 ~ ~~ .'"''' '!'I'lfi!'W~'-":" ....!;..:;;, ,.,' ,I-f ~... T"'!, -... ...~.,~.. .. '-'-< .:I"".,=.,.."....~'!lPIII'.... __...... AREA 3- Fairlawn Shores Trail Total Project Cost Project Levy (60%) Project Assessment (40%) Street/Storm Sewer Assessment Front Footage Method Estimated Assessable Front Footage Estimated Assessment Rate Unit Method Assessable Units Estimated Unit Assessment AREA 4 - Fish Point Road Total Project Cost Project Levy (60%) Project Assessment (40%) Street/Storm Sewer Assessment Front Footage Method Estimated Assessable Front Footage Estimated Assessment Rate Unit Method Assessable Units Estimated Unit Assessment AREA 5 - Linden Circle . Total Project Cost Trunk Reserve Project Assessment Street/Storm Sewer Assessment Front Footage Method Estimated Assessable Front Footage Estimated Assessment Rate Unit Method Assessable Units Estimated Unit Assessment g:\projec:ts\1999\24Ceas\REPORT24,DOC 9 $61,100.00 $36,660.00 $24,440.00 $24,440.00 2,010 FF $12.16/FF 17 Units $1,437.65/Unit $74,295.00 $44,577.00 $29,718.00 $29,718.00 4,486 FF $6.62/FF 47 Units $632.30/Unit $109,720.00 $ 28,990.00 $ 80,730.00 $ 80,730.00 1,725 FF $46.80/FF 12 Units $6727.50/Unit PROJECT FINANCING SUMMARY Project Area Assessments Tax Levy Trunk Project Total Area Reserve 1 Oak RidgeCircle, F1andreau Circle, $260,078 $390,117 $24,700 $674,895 Fulbright Circle, Indian Ridge Circle, Euclid A venue, Maves Trail, and Forsythe Road 2 Shannon Trail, $79,924 $119,886 $11,180 $210,990 Prior Circle and Shannon Circle 3 Fairlawn Shores $24,440 $36,660 $0 $61,100 Trail 4 Fish Point Road $29,718 $44,577 $0 $74,295 5 Linden Circle $80,730 $0 $28,990 $109,720 TOTALS 5474,890 5591,240 564,870 51,131,000 From an economic standpoint, projects 1 through 5 are feasible. With a total estimated project cost of $1,131,000, an estimated bond of $1,066,130 and an assessment total of $474,890 the assessed amount would be 44%. Minnesota Statutes Chapter 429 Special Assessment Bond issue requires that a minimum of 20% of the total bond amount be recovered through special assessments. PROJECT SCHEDULE The following project schedule outlines an approach to complete the assessable projects in 2000: Accept Feasibility Study/Call for Public Hearing 8/16/99 Hold Informational Meeting . 9/99 Conduct Public Hearing! Accept Project/Order Plans and Specifications 9/20/99 Hold Informational Meeting 1/00 Approve Plans and Specifications/Order Advertisements for Bids 3/00 Open Bids 4/00 Accept Bids/Award Contract 4/00 Begin Construction 4/00 Authorize Amount to be Assessed/Schedule Assessment Hearing for 9/00 8/00 Conduct Assessment Hearing! Adopt Assessment Roll 9/00 Complete Base Course of Bituminous 10/00 a:\projecU\I999\24r...\REPORT24.DOC 10 ., ~;.~'".m:iJ[~~:~j,;!tl;t..dl!l-',,'.,.... :", .,;.1.": ..........., CONCLUSION The total estimated cost of the recommended improvements is $1,131,000. A portion of these projects are proposed to be assessed to the benefiting property owners and the remainder through other funding sources. The projects are feasible from an engineering standpoint. S:\projecu\I999124fcas\REPORn4.DOC 11 4i ~ ~ ~f(..\~ \) R>' y-~ ~ ~ ST. ~ 152nd ST. 14 = Indian Ridge Circle ST. I- Z NO SCALE EXHIBIT 1 "~ . .:!,~~~,t'~::;.t::::}.': ::i:. ::7T ~.". '"" ,~ ~.~..... T::~:: ." , l' :-i=L::~.,,i...,,1~:!- ,"P' \:f'-~ <i~~ ~<;). ~ ~ N 152nd ST. ~ z 5 a.. AREA 4 ST. ST. I en G: S.E. NO SCALE , 158th l' WHITE DR. EXHIBIT 2 l> ~-~-~ ~, I ~ I ~ ~ N NO SCALE EXHIBIT 3 -- R.O.W. ct ROADWAY R.O.W. 25' 25' VARIESl 14' (11' u) I.' (11' ..) rVARlES B618 CONC. CURB c!c GUTTER ~ 6- CROWN ~ --J6-~ -16-1- 1.5 - 2331 TYPE 41 A BITUMINOUS WEAR COURSE 2357 TACK COAT 2.5 - 2331 TYPE 31B BITUMINOUS BASE COURSE 7- CLASS 5 AGGREGATE BASE * FORSYTHE ROAD RIGHT -OF -WAY IS 33'. ** FORSYTHE ROAD SE NOTE: ALL ROADS TO BE CONSTRUCTED TO A MIN. OF 7 TON DESIGN. PROPOSED STREET SECTION AREA 1 & 2 EXHIBIT 4 R.O.W. ct LINDEN CIRCLE R.O.W. VARIES 10'-15' VARIES 10'-15' 11' ,,' I B618 CONC. CURB &: GUTTER ~ 6" CROWN """ -J6"~ ~6"~ 1.5" 2331 lYPE 41A BITUMINOUS WEAR COURSE 2357 TACK COAT 2.5" 2JJ1 TYPE JIB BITUMINOUS BASE COURSE 7" CLASS 5 AGGREGATE BASE * THE ROAD WAS NOT CONSTRUCTED IN THE CENTER OF THE RIGHT -OF-WAY. SOME AREAS WILL REQUIRE ADDITIONAL RIGHT -OF -WAY OR ROADWAY EASEMENTS. PROPOSED STREET SECTION AREA 5 , EXHIBIT 5 ,... ... ......~Iliii....,:;.." .,:., .:l :iIt.:'.J.\",..:IIi;~. ..... .~i " W-~~~ ~ ~,I\ fO'-;';'~k"'i~~"'- ti.iiili ,.',~ ,',I