HomeMy WebLinkAbout8A - 1999 Improvement Prject 99-02 CITY COUNCIL AGENDA REPORT DATE: AGENDA #: PREPARED BY: REVIEWED BY: SUBJECT: SEPTEMBER 20, 1999 SA SUE MCDERMOTT, ASSISTANT CITY ENGINEER GREG ILKKA, CITY ENGINEER CONSIDER APPROVAL OF CHANGE ORDER NO. 1 TO THE CONTRACT FOR THE 1999 IMPROVEMENT PROJECT, #99-02. DISCUSSION: HISTORY Project #99-02 is the lift station renovation project included in the 1999 public improvements through a contract with Braun Pump and Controls of New Prague, MN. The project consists of rehabilitation of three existing duplex submersible grinder pump lift stations. The work will vary somewhat at each location, but in general consists of replacing the upper portion of wet well, replacement of piping and wiring in the wet well, new pumps, new control panels, and site restoration. This project was originally bid as a part of the Candy Cove/Lakeside Manor Street Improvement project. The bids were rejected due the high cost of the lift station renovations. Council directed staff to readvertise the lift station renovations as a separate project. The force main and valve manhole installation required for lift station #12 remain in the Candy Covel Lakeside Manor project which was awarded to Northwest Asphalt, Inc. The existing forcemain will be removed during the proposed forcemain installation requiring bypass pumping in order to maintain sanitary sewer service to 35 homes during this construction. In separating the two projects, the bypass pumping was not addressed in the street reconstruction contract. 162(ill&;gglg Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER CURRENT CIRCUMSTANCES Northwest Asphalt is proposing to complete the forcemain and valve manhole construction in September. This work will be coordinated with Braun Pump and Controls for the lift station #12 renovations. Braun Pump and Controls' proposal for the bypass pumping totals $2,500.00. Staff has reviewed this proposal, agrees it is fair and equitable, and recommends approval. CONCLUSION Bypass pumping during forcemain installation is necessary to maintain sanitary sewer service for approximately 35 homes. FINANCIAL IMPACT: The original contract was $117,800.00. This change order is approximately 2% of the original contract. Funding for this change order is proposed to be from the Trunk Reserve fund due to the fact the extra work was required in conjunction with the lift station renovations. ALTERNATIVES: The alternatives are: 1. Approve Change Order No.1. 2. Deny this item for a specific reason and provide staff with direction. 3. Table this item until some date in the future. RECOMMENDED MOTION: A motion and second approving Change Order No. 1 to the Lift Station Renovations Project #99-02, funded through the Trunk Reserve fund. REVIEWED BY: REVIEWED BY: LIFTCOI.DOC o 0 BRAUN ,PUMP &CQN:TROLS, INC oRR4BOX474 o NEW PRAGUE,. MNS06071' 612-758-66000 t~~~;,~ ':~..~~~;~\;~~}'l2:~: SEP 1 0 1999 September 9~ 1999 0 SUe o McDermott '0, City of Prior 'Lake 0 '0 16200 Eagle Creek Ave . Prior Lake, MN 5~}72.,.1787 0 ' Dear SlJ,e, , Weare pleased to offer this quote f?r the obypass for Li~ Station # 13,oPioj~ct No 99-02. Pricing is as follows. ' , OLift Station Bypass 0 0 $2,5()O~OO o 0 o If you havean~ questions please Ogiveme a'calLTh,ank you. 0 Sincerely, : ~~a.u1~L . .Dave Braun 0 (jJ 0,' 0' o DB/sr .. : . .... . ".'. , - ~,,':: CHANGE ORDER CITY OF PRIOR LAKE 16200 EAGLE CREEK AVENUE SE PRIOR LAKE, MN 55372 CHANGE ORDER NO.1 TO: Braun Pump & Controls RR 4, Box 474 New Prague, MN 56071 DATE: September 20, 1999 FOR: Project No. 99-02, Lift Station Renovations OWNER: City of Prior Lake You are hereby directed to make the following change to your contract dated July 19. 1999. The change and the work affected thereby is subject to all contract stipulations and covenants. This Change Order will increase the contract sum by: Two-Thousand-Five-Hundred and Non 00 Dollars ($2.500.00) Add the following: Item Description Unit Ouantitv Unit Price Amount 1. Bypass Pumping LS 1 $2,500.00 $ 2,500.00 Total Additions $ 2,500.00 Amount of Original Contract 117.800.00 Change Order No. 1 $ $ $ 2.500.00 Revised Contract Amount 120.300.00 Contract time is not affected by this change. APPROVALS: Approved: City of Prior Lake Owner Approved: Braun Pump & Controls By By Mayor Date Date By Title City Manager Date G:\PROJECTS\I999\02LIFTS\CO I.DOC .- _.... .... ~""l_______'~'1"i~' ..~ '. ,. . ~... '....'. I"" ......-.-\.;;,- '1'. "lJ;.;,;i<jp~~..;.oft;i.; ~