AGENDA ITEM:
DISCUSSION:
CONSIDER APPROVAL OF A RESOLUTION ACCEPTING THE BIDS AND
AUTHORIZING THE EXECUTION OF TWO CITY STANDARDIZED
CONSTRUCTION CONTRACTS FOR THE PURCHASE AND INSTAllATION
OF STANDARDIZED EQUIPMENT FOR THE 2007 LIFT STATION
RECONSTRUCTION PROJECT
Introduction
The purpose of this agenda item is to accept the bids and authorize the
execution of two City standardized construction contracts for the purchase and
installation of standardized equipment for the 2007 Lift Station Reconstruction
Project.
Historv
This agenda item is part of the continuing process of Lift Station Rehabilitation
which was initiated by the Council's approval of a Standardized
Comprehensive Management and Rehabilitation Plan. Work to be completed
is due to the age and condition of the lift stations. Work is prioritized based on
need. Upon completion of this year's project, the City will have 5 of the 38 lift
stations left to rehabilitate.
On February 20,2007, the City Council approved a resolution authorizing
Advanced Engineering and Environmental Services (AEzS) to proceed with
design and specifications for Northwood and Fairview lift station
improvements. Additionally, on May 21,2007, the City Council approved a
resolution accepting plans and specifications and authorized advertisement for
bids for the project.
Rehabilitation components and replacement parts will follow the City of Prior
Lake's Lift Station Standardization Management and Rehabilitation Plan and
will include pumps, guide rails, electrical panels and other electrical
components, piping replacement, wet well covers and hatches.
Current Circumstances
Bids were received and opened on June 20,2007, for standardized supplies
and the installation of standardized supplies. City staff obtained pricing for City
provided standardized equipment and electrical services necessary for the
2007 Rehabilitation Project.
Bids for standardized supplies and installation are as follows:
Lift Station Ford Construction Electric Pump
Northwood $ 28,896.00 $ 28,968.00
Fairview $ 18,840.00 $ 23,909.25
Total $ 47,736.00 $ 52,877.25
www.cityofpriorlake.com
R\CouncillAgenda Reports\2007\07 16 07'Jifhlli1\!Pl1)52?4ij?,~goooj~t~~5~&.4 7.4245
Bids for electrical services are as follows:
Lift Station Hayes Electric Cedar Lake Electric
Northwood $ 5,100 $ 5,433
Fairview $ 5,900 $ 6,384
Total $11,000 $11,817
City staff will act as the general contractor and supply all components and
replacement equipment based on the Lift Station Standardization process.
Staff will complete and schedule all preparatory work, excavation and
restoration for each lift station site.
Conclusion
Staff is recommending awarding the City's Standardized Construction Contract
for the installation and electric services to the lowest responsible bidders, Ford
Construction and Hayes Electric, respectively. All work for this project will be
completed by October 15, 2007.
FINANCIAL
IMPACT:
With the City as general contractor, considerable money will be saved by not
paying marked up costs for replacement equipment and components at each
lift station. Costs related to contract services amount to $58,736. Costs for
standardized equipment to complete the project come to $145,798.15 which
cover the following items:
. Controls
. Control panels
· Structure improvements
. Hatches
· Electrical upgrades
. Restoration
The total project cost is $204,534.15. With $33,500 added to cover
engineering, the total project cost is $238,034.15; there is $240,000 allocated
for this project in the Sewer Operating budget.
ALTERNATIVES:
1. Approve a resolution accepting the bids and authorizing the execution of
two City Standard Construction Contracts: one with Ford Construction in
the amount of $47,736 for furnishing limited supplies and installation of
supplies and City supplied equipment; and one with Hayes Electric for
$11,000 for electrical services provided and $145,798.15 for the purchase
of standardized equipment to be installed by Ford Construction, Hayes
Electric and City staff, for the 2007 Lift Station Reconstruction Project.
2. Deny this item for a specific reason and provide staff with direction.
3. Table this item to a certain date in the future.
RECOMMENDED
MOTION:
Alternative #1.
Steve Albrecht, Public Works Director/City Engineer
R:\CouncillAgenaa Reports\2007\07 16 07\lift station reconstruction project agenda. doc
4646 Dakota Street S.E.
Prior Lake, MN 55372-1714
RESOLUTION 07 -xx
A RESOLUTION ACCEPTING THE BIDS AND AUTHORIZING THE EXECUTION OF TWO CITY
STANDARDIZED CONSTRUCTION CONTRACTS AND FOR THE PURCHASE AND INSTAllATION
OF STANDARDIZED EQUIPMENT FOR THE 2007 LIFT STATION RECONSTRUCTION PROJECT
Motion By:
Second By:
WHEREAS, City staff has identified the following lift stations for rehabilitation:
1. Northwood
2. Fairview; and
WHEREAS, The Capital Improvement Program for 2007-2011 has identified the rehabilitation
projects as a priority for the City and allocated funding therefor; and
WHEREAS, Ford Construction has provided the lowest price for installation services:
Lift Station Ford Construction Electric Pump
Northwood $ 28,896.00 $ 28,968.00
Fairview $ 18,840.00 $ 23,909.25
Total $ 47,736.00 $ 52,877.25
and
WHEREAS, Hayes Electric has provided the lowest price for electrical installation services:
Lift Station Hayes Electric Cedar lake Electric
Northwood $ 5,100 $ 5,433
Fairview $ 5,900 $ 6,384
Total $ 11,000 $ 11,817
and
WHEREAS, The City previously adopted a Standardized Comprehensive Management and
Rehabilitation Plan for the purchase of standardized equipment;
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCil OF PRIOR lAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City Council accepts the bids and authorizes the execution of two City standard construction
contracts; one with Ford Construction in the amount of $47,736.00 and one with Hayes Electric in
the amount of $11 ,000.00 for the 2007 Lift Station Reconstruction Project.
3. Staff is authorized to purchase necessary equipment for $145,798.15 in accordance with the Lift
Station Standardization Plan.
R:\Council\Agenda Reports\2007\07 16 07\lift station reconstruction project resolution.doc
www.cityofpriorlake.com
Phone 952.447.9800 / Fax 952.447.4245
4. The funding for the project shall come from the following Sewer and Water Utility Fund accounts:
601-49003-501 $58,736.00 and
601-49003-224 $145,798.15
PASSED AND ADOPTED THIS 16TH DAY OF JULY 2007.
YES
NO
Haugen Haugen
Erickson Erickson
Hedberg Hedberg
LeMair LeMair
Millar Millar
Frank Boyles, City Manager
R:\CouncillAgenda Reports\2007\07 16 07\lift station reconstruction project resolution. doc